v.
United States Army Corps of Engineers
IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA
GREENWICH TERMINALS LLC and : CIVIL ACTION GLOUCESTER TERMINALS LLC : : v. : NO. 23-4283 : UNITED STATES ARMY CORP OF : ENGINEERS, DISTRICT : COMMANDER FOR THE : PHILADELPHIA DISTRICT OF THE : ARMY CORPS OF ENGINEERS, : JEFFREY BEEMAN, and THE CHIEF : OF THE REGULATORY BRANCH : FOR THE PHILADELPHIA : DISTRICT OF THE ARMY CORP OF : ENGINEERS, TODD A. SCHAIBLE :
THE PHILADELPHIA REGIONAL : CIVIL ACTION PORT AUTHORITY : : v. : NO. 24-1008 : UNITED STATES ARMY CORPS OF : ENGINEERS, DISTRICT : COMMANDER FOR THE : PHILADELPHIA DISTRICT OF THE : ARMY CORPS OF ENGINEERS, : JEFFREY BEEMAN, CHIEF OF THE : REGULATORY BRANCH FOR THE : PHILADELPHIA DISTRICT OF THE : ARMY CORPS OF ENGINEERS, : TODD A. SCHAIBLE :
MEMORANDUM KEARNEY, J. October 28, 2024 Our community relies upon the national government and its federal agency experts to carefully study applications which may affect large cargo ships safely passing through our interstate rivers to deliver products from around the World to riverside ports for our eventual use. Congress and those experts set standards to ensure exhaustive analysis of applications seeking to alter the present waterways. The experts must consider a variety of factors including the public interest of ensuring ships can safely pass on the river and the economic effects of changes to our rivers. We do not second guess the experts’ technical expertise, but Congress requires we must ensure the experts fulfill their crucial mission by studying all factors. And we ask experts to again
study applications if citizens with standing persuade us the experts did not meet the standards. Our case today involves applications affecting the Delaware River on the eastern boundary of our District. Congress authorized the deepening of the Delaware River Main Channel over thirty years ago. The Deepening Project involves initial and maintenance dredging of the Delaware River Main Channel to a depth of forty-five feet. This important public work allows large cargo vessels to navigate upriver to deliver products to previously inaccessible riverside ports from the Delaware Bay to Philadelphia. The United States partnered with the Philadelphia Regional Port Authority to fund the Deepening Project. This considered idea of deepening the Delaware River inspired Diamond State Port
Corporation, a corporate entity of the state of Delaware, to develop a new port along the Delaware River at Edgemoor, Delaware—a few miles south of the Pennsylvania/Delaware border. Delaware hopes this new port will generate hundreds of millions of dollars in economic benefit for her citizens. All agree the Edgemoor site poses logistical and size challenges. The site is located at a tight turn where the Delaware River Main Channel comes close to the shoreline. The anticipated problem is the large vessels need enough deep water and room to turn around at the Edgemoor site to deliver their cargo before heading back to the Atlantic Ocean. Diamond State proposed to overcome this obstacle through a planned combination of a forty-five-foot-deep berthing area connecting the proposed port at Edgemoor to the Main Channel and using the Main Channel as a turning basin for large vessels delivering products to the Edgemoor port. Congress requires Diamond State apply to the United States Army Corps of Engineers to obtain the District Commander’s: (1) approval of a dredging and construction permit under section 404 of the Clean Water Act and section 10 of the Rivers and Harbors Act, and (2) authorization
for use of a federal project under section 408 of the Rivers and Harbors Act because of the proposed location of the turning basin. We rely upon experts within the Corps to study applications and recommend actions to its District Commander. The Corps studied the applications, sought public comment, and recommended approval. Its District Commander issued the permit and the authorization. Three upriver port entities sued asking us to evaluate the Corps’ scrutiny of Diamond State’s applications. The Philadelphia Port Authority and two other upriver ports challenge the Corps’ decision making process under the Administrative Procedure Act. Our scope of review is narrow to avoid substituting our judgment for the Corps’ expertise. We consider whether the Corps
articulated a satisfactory explanation for its actions, including a rational connection between the facts found and the recommendation to the District Commander. We study the quality of the Corps’ decision making process, not the wisdom of the decision. We find the Corps did not engage in reasoned decision making as to the section 404/10 permit because it failed to consider the impact of the turning basin and dredging activities on the public interest in navigation and safety. We today vacate the section 404/10 permit in accompanying Orders. We also find the Corps arbitrarily and capriciously departed from its own procedures in recommending the 408 approval by not requiring Diamond State obtain a Statement of No Objection from the Philadelphia Port Authority as the sole non-federal sponsor of the Deepening Project. We vacate the section 408 authorization in the accompanying Orders. I. Factual Background! We study approvals necessary to expand ports along the Delaware River, which stretches from the Delaware Bay to Philadelphia and beyond in our District. Three states (Delaware, New Jersey, and Pennsylvania) border this important waterway in or near our District. The Delaware River connects ports in these states to World commerce. The Ports before us operate in and around Philadelphia. They naturally compete for shipping business with other ports along the Delaware River. ‘OAvondale r ULinwoow dirden oe coe Ardentownf |S" 2 Qvinterthur An af, i Choster OF Gockiond. m res County dflockessin St JoMentchanin Ae Phill i i giorth Star a 4 fi - fandenbers ' I é feunville ss A 3 i stent he , oa Sy ce a me & ismare f : Vad _— a SO A Al oPenns Grove fo | é nen \ wport. a J pf’ we an wt ‘ort of | pine cope tke Coton Cameys, oat New Castlé SX | ae SB 4 r le hain 7 yf at Ge 1 ne, a Wilhington Se ee ; ganer . = ee jiewark ne i. ad ; | . {f bls 1 onkside l, Sal em~, : \ J ‘ Cun | 7 _— f Gennsvil 10 05 1 15 2 25 Miles A \ PA erent oe, ae 7 f NS Sale| Glasgow MD” if oy ; | it | O&
Ports on the Delaware River are of economic importance to the border states. The Commonwealth of Pennsylvania established the Philadelphia Port Authority in 1989 to manage and operate Philadelphia’s ports. The State of Delaware through its General Assembly established Diamond State Port Corporation in 1995 to manage and operate the Port of Wilmington.[3] Greenwich Terminals LLC operates the Packer Avenue Marine Terminal in
Philadelphia, Pennsylvania.4 Gloucester Terminals LLC operates the Gloucester Marine Terminal in Gloucester City, New Jersey and the Paulsboro Marine Terminal in Paulsboro, New Jersey.5 Congress authorized the Delaware River Main Channel Deepening Project in 1992 with the goal of deepening the Main Channel to forty-five feet.6 Congress, in directing the Corps to develop the Delaware River Main Channel Deepening Project, intended to allow larger vessels to travel north to ports in Camden, New Jersey and Philadelphia.7 The Philadelphia Port Authority and the Corps’ Philadelphia District signed a Project Partnership Agreement for the Deepening Project.8 The Philadelphia Port Authority became a non-federal sponsor of the Deepening Project under this Agreement by agreeing to pay a percentage of the costs of construction and maintenance including the construction of new dredged material disposal facilities.9
The ports saw an increased need for deeper channels after the Panamanian government completed the Panama Lock Expansion Project in 2017.10 After 2017, “New Panamax ships, or ships that were too large to traverse the Panama Canal prior to expansion, are [now] able to more efficiently reach East and Gulf Coast Ports.”11 Diamond State purchased property in Edgemoor, Delaware in 2016 “[t]o capitalize on the economic benefits of the” Delaware River Deepening Project, “with the intent of re-developing the property into a multi-user containerized cargo port capable of accepting New Panamax cargo ships.”12 The State of Delaware signed a 50-year concession agreement in 2018 committing “to invest approximately $400 million to construct the Edgemoor facility.”13 Diamond State seeks a permit under section 10 of the Rivers and Harbors Act and section 404 of the Clean Water Act from the Corps to dredge and construct a new port at Edgemoor. Diamond State applied to the Corps for a permit under section 10 of the Rivers and Harbors Act of 1899 and section 404 of the Clean Water Act on March 10, 2020.14 The Corps, after receiving an application, evaluates the application and then either recommends or does not recommend the local Corps District Commander grant the permit or permission sought. Diamond State sought to develop the “new containerized cargo port” at its purchased Edgemoor site.15 Diamond State wanted to create a new, forty-five-foot deep access channel between the existing federal Delaware River Navigation Channel and the Edgemoor port.16 The proposed access
channel would terminate in a new ship berthing area. Diamond State would also construct a 2,600- foot, pile-supported wharf and retaining wall.17 Diamond State intended to store dredged material in the Corps’ Wilmington Harbor South confined dredge facility.18 Diamond State predicted it would need to dredge a total of 3,325,000 cubic yards of material.19 Access to this new harbor required “the construction of a 1,700-foot diameter turning basin on the downstream portion” of the Edgemoor Project.20 Diamond State swore its turning basin would be “inclusive of the Delaware River main shipping channel” because there is not enough space between the proposed port and the main shipping channel for the needed turning basin to be situated anywhere else as shown: XB ee
et Diamond State supported its application with an Environmental Assessment Technical Document,”” a Dredged Material Disposal Plan,”? a Port of Wilmington Economic Impact Study,”* and a Maritime Institute of Technology and Graduate Studies Full Mission Ship Simulation for Edgemoor Navigation Feasibility Study.” The Maritime Institute of Technology and Graduate Studies released a Report on the Study on September 18, 2019.*° The Institute sought to demonstrate the existence of the constructed terminal on the Edgemoor site would minimally impact vessels transiting on the Delaware River, validate the terminal turning basin designs for handling containerships up to 9,300 TEUs on a routine basis, provide suggestions on how to facilitate vessel movement in and out of the terminal, and provide “preliminary validation on the feasibility of a 12,000 TEU vessel to call on the terminal.””’ The Institute did not look at the impact of vessels using the turning basin on traffic in the main channel. The Institute did not look at the impact of Diamond State’s dredging on traffic in the main channel. The Institute pilots rated the safety of a single vessel turning in the basin with no traffic in the main channel a 5.4/10, with 10 being the safest.”® The Institute’s Feasibility Study
constituted a “preliminary” evaluation and the Institute clarified “[b]erthing procedures, tug power required, and emergency procedures will be developed in future simulation studies.”29 Diamond State projected the Edgemoor Port would increase traffic to Wilmington area ports by 55% and net $383 million a year to Delaware’s economy.30 “The benefits of the increased jobs, wages, and taxes [we]re expected to directly improve unemployment and reduce poverty in
the City of Wilmington” and add approximately 2,260 new jobs.31 Diamond State included limited information on maintenance dredging in its application and supporting materials for the Corps.32 But “[i]n order to reduce the volume of maintenance dredging associated with th[e] project and to maintain the functionality of the berths,” Diamond State proposed “to install a sedimentation reduction device along the face of the wharf consisting of a series of sediment fans[.]”33 Diamond State swore “[t]he disposal of the dredged materials from the construction represent[ed] a volume that is larger than typoial [sic] maintenance dredging volumes in the region.”34 Diamond State acknowledged “[t]here may be temporary impacts to commercial shipping during dredging, mobilization and project construction.”35
Diamond State seeks authorization under section 408 of the Rivers and Harbors Act from the Corps for the Edgemoor Project. Diamond State wrote to the Corps on April 3, 2020 referring the Corps to the materials submitted in support of its section 404/10 permit application and stated “[f]ollowing an initial discussion with the regulatoary [sic] program, we undersand [sic] that the construction of the project subject to a Sectoin [sic] 408 review due to its proximity to a federal navigation project (the Delaware River Main Channel Philadelphia to Sea Project ) and its anticpated [sic] use of a Federal Dredged Material Dispoal [sic] Area (Wilmingon [sic] Harbor South Disposal Area).”36 The Corps began a section 408 review in response to Diamond State’s section 408 application. The Corps issues a public notice seeking comment on Diamond State’s section 404/10 and section 408 applications. The Corps issued a public notice on July 24, 2020 and then revised and reissued the notice on July 30, 2020 seeking public comment on the proposed Edgemoor Project under section 404/10 and section 408.37 The Corps in its notice described Diamond State as seeking “authorization from the U.S. Army Corps of Engineers under the authorities of Section 404 of the Clean Water Act and Section 10 of the Rivers and Harbors Act to discharge fill material and to conduct dredging and disposal activities within, and adjacent to, navigable waters of the United States at the proposed Port of Wilmington Edgemoor Expansion project site.”38 The Corps included Diamond State’s estimate the Edgemoor Project required 3,325,000 cubic yards of material in initial dredging and 500,000 cubic yards of material in annual dredging.39 The Corps included Diamond State’s plans
to use sedimentation fans along the new port face to reduce the amount of required maintenance dredging.40 The Corps explained Diamond State also sought, under section 408, “permission to have a section of their proposed ship turning basin to fall within the boundaries of the Main Navigation Channel of the Delaware River, Philadelphia to Sea Federal Navigation Project.”41 The Corps stated it would review Diamond State’s proposed use of the Corps’ dredge disposal facilities under “Section 217(b) of the Water Resources Development Act of 1986” and added, “[t]he anticipated 217(b) request is not a subject of this public notice.”42 The Corps issued a September 1, 2020 Notice to extend the comment period an additional thirty days and to clarify the turning basin
required using the Main Navigation Channel of the Delaware River.43 The turning basin clarification included the diagram shown above for the public’s consideration.44 Submitted concerns about navigation, maintenance dredging plans, and safety. The Philadelphia Port Authority submitted comments on September 17, 2020.45 It requested public hearings be held in New Jersey, Pennsylvania, and Delaware.46 It wanted to publicly address (1) Diamond State’s application hinged on Corps’ approvals for dredged material disposal and maintenance but Diamond State had not yet applied for these approvals and the notice did not contain enough information for the public to understand the plan47; (2) the Edgemoor
Project should not be approved until the impacts on the Delaware River Main Navigation Channel maintenance had been adequately assessed, including the impacts of the proposed sedimentation fans48; (3) the public notice and Diamond State’s application did not address the public interest factors and this information should be made available for public comment49; (4) the discharge of fill material to build a wharf required compensatory mitigation, and the notice’s suggestion it did not fulfill compensatory mitigation requirements contravened Corps policy50; (5) the Corps should require Diamond State to identify disposal sites for initial dredging and at least twenty years of maintenance dredging51; and (6) the Corps’ notice did not contain information allowing meaningful public input on the proposed turning basin.52 The Philadelphia Port Authority also
highlighted its status as a non-Federal sponsor of the Delaware River Deepening Project entitling it “to a detailed delineation of how [Diamond State] intends to conduct its dredging in a manner that is completely protective of the maintenance of the Main Navigation Channel, contributes no dredge material to the annual burden associated with that Project, and protects the benefits off [sic] its contract with the federal government” and explained “[u]nder the Project Partnership Agreement, [the Philadelphia Port Authority] has agreed to contribute 35 percent of the costs of construction (among other costs)[.]”53 South Jersey Port Corporation submitted comments twelve days later addressing impacts to navigation on the Delaware River, “especially the request to use the main navigation channel as a cargo ship turning basin.”54 South Jersey Port Corporation pointed out the navigation feasibility study “did not assess whether there would be delays or impacts to ships in the main navigation channel as a result of the turning basin. A large cargo ship turning in the main channel creates an obvious risk of a collision and will inevitably cause delays as ships slow down or stop altogether to accommodate the turning ship, thereby negatively harming port operators up and down the
River.”55 South Jersey Port Corporation emphasized the Corps’ failure to consult with the Coast Guard to assess the impact the proposed sedimentation fans and turning basin would have on ship traffic and safety on the Delaware River.56 The Pennsylvania Attorney General submitted comments a couple days later explaining the application did not contain information about all activities Diamond State Port Corporation planned to undertake; did not contain adequate information about the dredged material disposal plan; did not meet the requirements applied to the Delaware River Deepening Project required under 33 C.F.R. section 322.5; and did not explain where the dredged materials will go if the federal dredging facilities have no capacity.57
The Greenwich and Gloucester Ports submitted comments the same day as the Attorney General addressing Diamond State’s plan for the proposed turning basin occupying the entire Delaware River Main Channel during use58; the failure of the Institute’s Feasibility Study to simulate ships using the turning basin and the effect on navigation in the Main Channel59; whether Diamond State intended to implement the Institute’s suggestion in its Feasibility Study that navigation into and out of Edgemoor only be attempted in certain tide and wind conditions60; and noted the application did not contain information about emergency situations.61 Greenwich and Gloucester included a memorandum authored by Craig Jones, Ph.D, addressing how sedimentation fans could impact navigation.62 They also provided a report by Captain Jerzy J. Kichner, a retired United States Coast Guard Captain, detailing specific concerns with the Institute’s Feasibility Study and the uncertain impacts of using the Delaware River Main Channel as a turning basin.63 Captain Kichner highlighted the coordination and machinery needed to turn a ship with tugboats and the care captains must take to ensure the ship does not run aground.64 He highlighted international authorities on navigation including the Permanent
International Association of Navigation Congresses, the International Association of Ports and Harbors, the International Maritime Pilots Association, and the International Association of Lighthouse Authorities, issued 2014 public harbor approach guidelines recommending no turning basin intrude on a deep draft channel.65 Captain Kichner expressed concern the Institute’s Feasibility Study did not account for the size of various vessels using the Delaware River Main Channel as they pass Edgemoor and did not conduct a simulation assessing the impact of a turning basin across the entirety of the Main Channel.66 Captain Kichner explained some large vessels, such as car carriers and large container ships, are impacted by winds and must maintain sufficient speed to maintain vessel maneuverability. He stated “large vessels constrained to the confines of
the channel . . . cannot slow down without potentially impacting their own navigational safety under certain weather conditions.”67 He further highlighted the study only focused on days of clear visibility and average tide.68 The Corps issues a supplemental public notice. The Corps issued a supplemental public notice over thirteen months later detailing changes to the Edgemoor Project proposal and seeking input on the newly-added compensatory mitigation plan.69 The Corps informed the public “[t]he sedimentation fans have been removed from the proposed project to minimize the impacts to aquatic resources and plans for an on-site confined disposal facility . . . in uplands have been added to the project.”70 The Corps again highlighted Diamond State “requested Corps of Engineers [sic] permission under Section 14 of the Rivers and Harbors Act of 1899 (33 U.S.C. 408; hereinafter Section 408) to utilize a portion of the Main Navigation Channel of the Delaware River, Philadelphia to Sea Federal Navigation Project as their ship turning basin.”71 The Corps did not include information in the notice regarding the impact of removing the
sedimentation fans on the volume of required annual maintenance dredging and commenters noted the removal of these fans would increase the required yearly maintenance dredging volume in the supplemental comment period.72 Commenters also noted the Corps should apply scrutiny to the lack of details provided regarding Diamond State’s proposed maintenance dredging activities because Diamond State expressed an intent to seek federal funding for the maintenance dredging under section 204(f).73 Commenters further addressed the scale of the annual maintenance dredging project would require exclusive use of the areas being dredged plus a safety radius but the Institute’s Feasibility Study failed to look at the impact of maintenance dredging operations on traffic in the Delaware River Main Channel.74
The Corps’ Philadelphia District recommends approval of the section 408 request. The Corps reviewed Diamond State’s section 408 request under its published Policy and Procedural Guidance.75 The Corps explained (1) the Edgemoor Project’s close proximity to the Main Channel warranted the Corps’ review to assess “possible increased [operation and maintenance] costs due to the increased sedimentation rates caused by construction and subsequent operation of the [Edgemoor] Project;” and “(2) possible impacts to navigation caused by use of a portion of the [Delaware River] Federal Navigation Channel as a ship turning basin.”76 The Corps recommended the District Commander approve Diamond State’s section 408 request on June 23, 2022.77 The Corps explained it was “required” to determine whether a Safety Assurance Review was warranted “by EC 1165-2-220.” The Corps “determined that a Safety Assurance Review was not required because the Proposed Project, as presented in this Section 408 Request, does not physically alter the Philadelphia to the Sea Project.”78 The Corps further explained, based on the Agency Technical Review, it deemed impacts to future operations and maintenance of the Delaware River Main Channel Deepening Project negligible because Diamond State “provided a thorough Hydrodynamic Model that was reviewed
by [Corps] Subject Matter Experts, who determined that the conclusions presented in the model were scientifically sound and that increased sedimentation within the boundaries of the Philadelphia to the Sea Project would not occur . . . [and] increased [operation and maintenance] costs are not a concern,;]” therefore, “the Proposed Project is not injurious to the public interest and does not impair the usefulness of the Philadelphia to the Sea Project.”79 The Corps “determined, in coordination with the Marine Advisory Committee/Delaware River Pilot’s Association, that the construction of the Proposed Project will not negatively impact navigation along the [Delaware River] Federal Navigation Channel.”80 The Corps found “considering potential impacts of the Turning Basin on navigation is outside the scope of the Section 408
review” because other ports “have turning basins within Federally authorized navigation channels” and the “USACE-Philadelphia District is not responsible for operating/coordinating marine traffic within the Federal Navigation Channel on the Delaware River.”81 The Corps concluded, under the heading “Non-Federal Sponsor,” “[t]he Delaware River, Philadelphia to the Sea River Federal Navigation Project is maintained at 100% Federal expense.”82 The Corps did not mention a Statement of No Objection from the Philadelphia Port Authority or an attempt to secure one. The Corps answers public comments and recommends issuance of the section 404/10 permit. The Corps waited approximately seven weeks after issuing its section 408 recommendation before recommending the District Commander approve the section 404/10 permit on August 4, 2022 in its section 404/10 Decision Document.83 The Corps anticipated 3,325,000 cubic yards of initial dredging consistent with Diamond State’s first application.84 The Corps departed from the originally envisioned 500,000 cubic yards in annual maintenance dredging with sedimentation fans. The Corps predicted “the access channel and berth site would require annual maintenance dredging to remove approximately 275,000 cubic yards of accumulated sediment. Annual maintenance dredging totals include 155,000 cubic yards for dredging of the access channel and 120,000 cubic yards for dredging the berthing area.”85 The Corps did not explain how the removal
of the sedimentation fans from the project plan did not increase the anticipated maintenance dredging, and instead decreased the proposed figure. The Corps detailed plans to store dredged material in Corps-owned disposal facilities, Wilmington Harbor North and Wilmington Harbor South. The Corps noted a hydraulic pipeline would transport dredged material to the disposal area.86 The Corps stated “a public meeting/hearing was requested but was not held. The public hearing was not held because the Corps determined issues raised in the request for a public hearing were insubstantial and could be addressed without a public hearing.”87 The Corps did not explain what those issues were, why they were insubstantial, or how the Corps addressed them. The Corps
advised Diamond State identified “Wilmington Harbor South and Wilmington Harbor North[,] to use for placement of dredged material from initial construction.”88 Diamond State’s representative completed a study to determine if Wilmington Harbor South would have sufficient capacity for dredging material because Wilmington Harbor North had limited capacity.89 The Corps then explained “[t]here is sufficient capacity in the Wilmington Harbor North CDF to accommodate the material from yearly maintenance dredging of the private berth area[,]” but did not specify for how many years the harbor could accommodate this material.90 The Corps noted Diamond State intended “to request Federal assumption of maintenance of the access channel under Section 204(f) of the Water Resources Development Act” and if the Corps granted Diamond State’s request, “the
[Confined Disposal Facilities] utilized for the maintenance dredging of the access channel would likely be at the Pedricktown Complex of [Confined Disposal Facilities], but w[ould] be the responsibility of the Corps and may be modified.”91 The Corps included information pertinent to some public interest factors defined by the Code of Federal Regulations.92 The Corps through these public interest factors assesses the impacts of the proposed activity and its intended use on the public interest.93 The Corps marked the economics of the Project as “beneficial,” navigation as “neutral (mitigated),” and safety as “not applicable.”94 The Corps did not assess safety in its Decision Document beyond marking it not applicable.
In its economic consideration, the Corps stated “[e]conomic development opportunities are enhanced through the construction of a -45-ft. berth and access channel as a result of the ability to attract larger container vessels” and container ports with berths less than forty-five feet will not be competitive in the mid-Atlantic region in the future.95 As to navigational impacts, the Corps remarked “[a]lthough the tuning [sic] basin for the proposed port is located in the federal navigation channel, navigation in the Delaware River will not be impacted by the proposed project. Please refer to section 9.8 Effects on Corps Civil Works Projects[.]”96 The Corps explained in section 9.8 “[o]n 22 June 2022, the Corps granted Section 408 Permission” because the Corps concluded the Edgemoor Project “will not adversely affect the Philadelphia to the Sea Project because it will not limit the ability of the Philadelphia to the Sea Project to function as authorized, does not impair the Corps’ ability to operate and maintain the Philadelphia to the Sea Project to its authorized dimensions, . . . will not increase the Corps’ future [operation and maintenance] costs[, . . .] is not injurious to the public interest and will not impair the usefulness of the Philadelphia to the Sea Project.”?’ The Corps attached its response to public comments to its Decision Document recommending approval of the 404/10 permit.°® The Corps provided the following responses to comments concerning navigation, economics, and safety pertinent to our review”: Diamond State’s Response Corps’ Response
The U.S. Army Corps of It is the Applicants understanding | The Section 408 review Engineers (USACE) should not | that the new dredging associated | analysis [sic] impacts to the issue Section 404 and Section with the main channel navigation channel on [sic] the 10 permits to Diamond State “deepening’ [sic] was completed | proposed activity and Port Corporation (DSPC) for the | in 2020. Thus the Edgemoor determined that the proposed Edgemoor Expansion project project will not impact the project | activity would not impacts until the potential negative completion. The information [sic] the federal navigation impacts of the Edgemoor provided in the Applicant’s channel. The Corps agrees Expansion project on the hydrodynamic analysis (EATD with the response regarding completion of the Delaware Appendix 10) and Preliminary the completion of the River Deepening Project, the Modeling report provided to Delaware deepening project ongoing maintenance of the address Section 408 comments being completed in 2020. Delaware River Main both demonstrate that the Navigation Channel, and the construction of this project will New Jersey sites in this area not have an adverse impact have been adequately assessed, | (increase the sedimentation rate) including the impacts of the on the ongoing maintenance of the proposed Sedimentation Fans. Delaware River Main Channel. In performing the public interest | The Applicant has provided The Corps reviews the analysis under 33 C_F.R. § economic justifications consistent | economic need for the project 320.4, USACE should conduct | with the justifications provided based on the Applicant’s an independent review of the for similar construction permits purpose and need statement. economic need for the project on the Delaware River and will The purpose and need for the and should consider the support appropriate analysis proposed activity is local to economic impacts to the required by USACE. the Delaware River. national and regional economy, Reviewing economic need on not just local benefits to a national scale would be Delaware.
[*17]Comment Diamond State’s Response Corps’ Response
outside of the NEPA scope of analysis for this project. The Public Notice and DSPC’s__| The Application provides the The Corps agrees with application documentation do requisite information about the DSPC’s response. not contain the requisite management of maintenance information about DSPC’s material in the portion of the dredged material disposal plan | project which is to be the responsibility of the applicant during the 10 year period of the permit action USACE should not approve Information related to the turning | The Corps agrees with DSPC’s Section 408 request to | basin was provided in the DSPC’s response. allow a section of its proposed navigation simulation provided in ship turning basin to fall within | Appendix 23 of the applicant’s the boundaries of the Main EATD. The navigation simulation Navigation Channel of the program was developed by the Delaware River without applicant and was approved by the additional information and USACE Deep Draft Navigation assurances on the impact to ship | Center, which provided in person traffic. review of the simulation. The simulation was performed by Delaware River Pilots, who are responsible for the navigation on the river, and the layout of the basin was adjusted based on the comments received in the simulation by the pilots, tug boat captains and the USACE Representatives. The current design reflects this input. A letter from the Delaware River Pilots Association confirming their involvement and recommendation has been provided. The Public Notice has The notice for extension to the The Corps agrees with insufficient information to allow | pubic [sic] comment period issued | DSPC’s response. meaningful input on the request | on September 1, 2020 included for a turning basin, and such detailed information on the information should be provided | turning basin. in another public notice. The USACE must analyze and | C.F.R. §§ 320 and 325 include The Corps agrees with give great weight to the language that requires a public DSPC’s response.
[*18]Comment Diamond State’s Response Corps’ Response
reasonably foreseeable interst [sic] but does not imply detrimental impacts on the that USACE should pick favorites economic vitality of other between State run Public Ports. entities in the area, including However, the independent other regional maritime ports. economic analyis [sic] being See 33 C.F.R. §§ 320 and 325. | performed by the USACE Deep To fulfill this obligation, the Draft Navigation Center does USACE has specific guidance allocate future growth on what must be included in an _| proportional between regional appropriate accounting analysis. | public ports, and does not As applied to the instant reallocate shiping [sic] from ports application, the guidance beyond the existing Port of requires that the accounting Wilmington container operations include an analysis of whether the proposed additional port on the Delaware River is needed or whether this proposed port will pull customers away from other ports on the river and thus undermine the economic viability of the existing ports. This application proposes to The application identifies four Since the removal of the conduct dredging and disposal constructed dredged disposal sedimentation fans, dredging activities. Despite this central areas along the Delaware River activities and disposal of focus of the application, the that are requested for regulatory dredged material have been application does not provide approval in support of a Section evaluated appropriately information about the site and 217 application. Each of the plans for disposal of the dredged | disposal areas is identifed [sic] in material from maintenance the EATD and are operated by dredging — an activity that the USACE Philadelpha [sic] and are applicant plans to undertake. well documented. DSPC’s application hinges on The application documents Dredging activities and USACE approvals for dredged | include the portions of the project | disposal of dredged material material disposal and which are subject to regulatory have been evaluated maintenance that have not yet approvals and is complete. There | appropriately. been applied for and which are _| is not a separation of 404 not included as part of the approvals, which are requested for Public Notice. DSPC has the impacted CDFs. The segmented its Section 404 subsequent application noted in approvals to exclude the public notice (Section 217b problematic dredge disposal and | and 204f applications) are not aquatic life issues that it cannot | regulatory permits and have each currently address. USACE must | been indicated at this time. Both require that the Section 404 applications require regulatory Comment Diamond State’s Response Corps’ Response
[*19]Application address all approval as a prerequiste [sic] to foreseeable aspects of the be considered. Edgemoor Development Project DSPC’s application fails to The applicant has provided Dredging activities and provide any meaningful detail estimates of the initial dredge disposal of dredged material with respect to dredge disposal, | volume, anticipated maintenance | have been evaluated the most critical aspect of its dredge volumes for the 10 -year appropriately. dredging proposal. The Public life of the dredging permit, Notice fails to include any several viable alternatives for substantive information to upland storage of dredged justify the summary material and has assessed the identification of CDFs potential for sediment and water quality impacts associated with dredging activities. This information is found in the applicant’s EATD. As the non-Federal sponsors of | It is understood that Philaport was | Dredging activities and the dredging of the Main the non-federal sponsor of the disposal of dredged material Navigation Channel, PhilaPort | construction main channel have been evaluated and the Commonwealth of deepening project that was appropriately. Pennsylvania are entitled to a completed in 2020, and the detailed delineation of how USACE is 100% responsible for DSPC intends to conduct its the O&M of the main channel. dredging in a manner that is The hydraulic modeling completely protective of the demonstrates that the Edgemoor maintenance of the Main project does not increase the Navigation Channel, contributes | sedimentation in the main no dredge material to the annual | channel. Further, the requirements burden associated with that of the section 204(f) guidance Project, and protects the benefits | require that the maintenance of its contract with the federal dredging disposal capacity be government. provided separate from the existing capacity of the federal navigation project. The expanded dredging volume | The hydraulic modeling Dredging activities and and footprint for the Edgemoor | demonstrates that the Edgemoor disposal of dredged material Development Project must be project does not increase the have been evaluated considered in assessing all of the | sedimentation in the main appropriately. impacts the Edgemoor channel, and further demonstrates Development Project may have | de minimus impacts to salinity, on the Main Navigation Channel | tidal flow and other aspects of the main navigation channel. Chapter 5 of the EATD discusses Comment Diamond State’s Response Corps’ Response
[*20]addtional [sic] cumulative impact of the project. The Public Notice and available | Relevant public interest factors The Corps agrees with application materials provide are identified and discussed in the | DSPC’s response. virtually no information onthe | Environmental Assessment public interest factors specified | Technical Document as part of the in 33 C.F.R. § 320.4. applicant’s permit application. These include economics, aesthetics, general environmental concerns, wetlands, fish and wildlife values, flood hazards, navigation, recreation, water supply and water quality. The Public Notice Extension The turning basin indicated which | The Section 408 review provided for the first time a plan | represendes [sic] a potential 1,700 | analysis [sic] impacts to the showing the location of the foot diamter [sic] turning basin navigation channel on [sic] the proposed turning basin. As only shows the maximum proposed activity and shown on the plan, the proposed | potential area which may be determined that the proposed turning basin occupies the entire | available under some conditions. | activity would not impacts main navigation channel. The majority of the ships which [sic] the federal navigation Placing a turning basin so that it | are anticated [sic] to operate in channel. occupies the entire main harbor are less than 1,200 feet in navigation channel is contrary to | lenght [sic] and would only recognized industry and utilzied [sic] a portion of the government best practices and channel. The 2018 Delaware standards, including River PAWSA does not indicate recommendations by the World | stakeholder concerns beyound Association for Waterborne [sic] seasonal maintentance [sic] Transport Infrastructure dredging in this vicinity of the (PIANC) Maritime Navigation | river and notes the heavy taffic Commission. The proposed [sic] is primiarly [sic] in Delaware Edgemoor project and turning City and Marcus Hook. basin is also located at a critical turn in the main channel, and so is likely to affect visual navigational aids and vessel maneuverability. Efforts should be made to relocate the proposed turning basin. The Navigation Study does not | The navigation study The Section 408 review include any simulations demonstrates that typical activity | analysis [sic] impacts to the involving a turning ship or use in the turning basin would occur _| navigation channel on [sic] the of the turning basin. In over a 10 to 15 minute period proposed activity and Comment Diamond State’s Response Corps’ Response
[*21]connection with safety in the before berthing occurs in the determined that the proposed main channel, MITAGS only harbor. The typical shipping activity would not impacts conducted simulations of two traffic in the Delaware River [sic] the federal navigation ships passing in the main consist of an average of 151 ships | channel. channel under favorable (>1600GRT) per month conditions. A ship that is turning | (DEPAWSA, 2018), or 5 per day, in the main channel would or | per 5 hours along the entire prevent use of this section of the | shipping channel. The risk of main channel for a significant turning basins activity (0.2 hours) period of time resulting in coinciding with the one vessel potential delays to upbound and | every 5 hours is not significant. downbound traffic, and could force other ships to slow down or have to stop, thereby affecting these other ships’ maneuverability and safety. Neither the Navigation Study The navigation study, the scope of | The Section 408 review nor any of the application which was developed with input analysis [sic] impacts to the materials address the potential the project and river stakeholders | navigation channel on [sic] the emergency situations that ships | and approved by the appropriate | proposed activity and could encounter in connection center of expertise at USACE determined that the proposed with the Edgemoor project and | demonstrates that the turmng activity would not impacts turning basin. DSPC’s studies basins is appropriately configured | [sic] the federal navigation fail to demonstrate that use of and that there is not an adverse channel. the proposed turning basin will | impact to shipping in the not have significant adverse navigation channel. impacts on the ports and ship- dependent businesses north of the Edgemoor project.
The District Commander formally approves the 404/10 permit and 408 authorization. The Corps’ District Commander formally approved the Edgemoor Project in its 404/10 Permit and 408 Approval Package on August 4, 2022 in response to the Corps’ recommendations (the same day as the Corps’ 404/10 recommendation).!° The District Commander explained “Tujpon recommendation of the Chief of Engineers and under the provisions of Section 10 of the Rivers and Harbors Act . . . and Section 404 of the Clean Water Act” Diamond State was authorized to undertake the work described in the attached permit.!°! The District Commander further explained “[t]he North Atlantic Division of the [Corps] has completed its review of your request pursuant to . . . 33 U.S.C. 408 (Section 408). This evaluation was performed in accordance with Engineer Circular (EC) 1165-2-220.”102 The District Commander granted Diamond State “permission to construct a wharf and bulkhead; and create a new berthing area and access channel adjacent to the Delaware River Philadelphia to the Sea Federal Navigation Project; subject to
[*22]compliance with the enclosed Section 408 Permission Decision Letter[.]”103 The Ports sue challenging the permits and authorizations. Greenwich and Gloucester timely sued last November under the Administrative Procedure Act challenging the Corps’ issuance of the section 404/10 permit and section 408 authorization.104 They claim the “Corps failed to adequately evaluate, study, consider, and mitigate the [Edgemoor] Project’s negative impacts on navigation, safety, economics, and the Delaware Deepening Project.”105 The Philadelphia Port Authority sued under the Administrative Procedure Act approximately four months later joining Greenwich and Gloucester’s challenges to the Corps’ issuance of the section 404/10 permit and section 408 authorization.106 The Philadelphia Port
Authority sought to challenge the section 408 authorization on the additional ground the Corps did not seek or obtain a Statement of No Objection from the Philadelphia Port Authority.107 We consolidated these cases for summary judgment briefing on the section 404/10 permit and section 408 approval.108 The parties timely cross moved for summary judgment on the section 404/10 permit and section 408 authorization followed by extensive oral argument.109 II. We apply a modified summary judgment standard of review under the Administrative Procedure Act. The Ports seek judicial review of the District Commander’s approvals under the Administrative Procedure Act. We begin with an overview of the unique standard of review.110 Congress through section 702 of the Administrative Procedure Act provides a “person suffering legal wrong because of agency action, or adversely affected or aggrieved by agency action within the meaning of a relevant statute, is entitled to judicial review thereof.”111 Summary judgment is the proper mechanism for deciding whether an agency’s action is supported by the administrative record.112 But the usual summary judgment standard does not apply in such cases
because we sit as an appellate tribunal.113 Congress, under section 706 the Administrative Procedure Act, allows us to set aside agency action if it is “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.”114 Our scope of review is narrow to avoid substituting our judgment for the agency’s.115 An agency’s decision is lawful when it “articulate[s] a satisfactory explanation for its action[,] including a rational connection between the facts found and the choice made.”116 But we find agency decision making arbitrary and capricious where “the agency relied on factors outside those Congress intended for consideration, completely failed to consider an important aspect of the problem, or provided an explanation that is contrary to, or implausible in light of, the evidence.”117 We must look at the reasons articulated by the agency itself at the time
of the decision rather than post-hoc rationalizations.118 As a general rule we only reverse agency decisions where “the administrative body not only has erred but has erred against objection made at the time appropriate under its practice.”119 But “[a] party need not rehearse the identical argument made before the agency; it need only confirm that the government had notice of the challenge during the public comment period and a chance to consider in substance, if not in form, the same objection now raised in court.”120 And our Court of Appeals finds petitioners have not waived an objection where an issue is “obvious” or “otherwise brought to the agency’s attention.”121 The Corps’ determinations of its statutory authority and the Corps’ interpretation of the applicable statutes are not waivable issues.122 We decide all questions of law.123 III. Analysis The Ports’ claims require we decide whether the Corps’ decision making leading to the District Commander’s August 4, 2022 issuance of the 404/10 permit and 408 approval was
“arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law” under the Administrative Procedure Act.124 Our review is deferential as the Corps has expertise and experience in administering Congress’ mandates and its internal policies. But we must ensure agencies engaged in “reasoned decisionmaking.”125 The Corps did not engage in reasoned decision making on material concerns raised by commenters. We find the Ports enjoy standing to challenge the Corps’ decision making. We find Congress required the Corps assess the impact of the turning basin under both its section 404/10 review and its section 408 review. We further find the Corps arbitrarily and capriciously recommended the District
Commander issue the section 404/10 permit because the Corps “failed to consider an important aspect of a problem” in: (1) dismissing navigation concerns raised by commenters and relying on traffic data submitted by Diamond State and conclusions drawn from the data without any attempt at independent verification; and, (2) finding safety concerns “not applicable” to the Edgemoor Project despite safety concerns raised by commenters.126 But we also find the Corps engaged in reasoned consideration of economic impact and the Corps did not need to assess impacts on regional competition. We today vacate the 404/10 permit and expect the Corps will reevaluate the Project consistent with this opinion. We find the Corps arbitrarily and capriciously issued the section 408 decision because the Corps departed from its standard procedure of obtaining a Statement of No Objection from non- federal sponsors of the federal project the applicant seeks to modify before beginning its review. The Corps did not justify the troubling departure in the record and we are not satisfied it departed with good reason. We do not reach whether the District Engineer appropriately exercised
discretion by not conducting a formal Safety Assurance Review under Corps’ guidance because we find the omitted Statement of No Objection dispositive. We vacate the section 408 authorization as the Corps could not begin its review without first ensuring Diamond State had sought a Statement of No Objection from the Philadelphia Port Authority. A. The Clean Water Act and Rivers and Harbors Act define the parties’ obligations. We analyze the Corps’ actions taken under a congressional grant of authority to it in the Clean Water Act and the Rivers and Harbors Act.
[*43]We deal with the Corps’ two errors—in relying on unconfirmed data and in relying on a report in a challenged aspect—in turn. The Corps argues nothing prohibits the Corps from relying on data provided by an applicant.234 We agree with its argument as a basic premise but “the Corps must undertake some independent effort to verify or discredit . . . challenged material.”235 The Corps knew traffic in the
Delaware River Main Channel had been increasing and projected to further grow because Diamond State included this information in its application materials.236 Diamond State’s application admitted “[c]urrent annual vessel traffic on the Delaware River is estimated to be 2,427 ships . . . [and] the new port at Edgemoor will promote vessel traffic increase of 55% over the current annual vessel traffic at the Port of Wilmington[.]”237 Diamond State further noted “[c]ontainer ship traffic on the Delaware River is expected to increase to an estimated 648 vessels annually from 418 vessels currently; an increase of 230 additional vessels, in part attributable to the additional port capacity being developed in Philadelphia and New Jersey.”238 The Corps never considered (or at least did not publicly advise) whether Diamond State’s figure of “one ship every five hours” is (1)
accurate, (2) reliable, (3) properly restricted by vessel size, (4) stale due to recent increases in vessel traffic, or (5) inaccurate for reasons such as tidal patterns or seasonality of shipping. The lack of described analysis leads us to find unreasoned decision making. We next turn to the improper conclusion the Corps drew from the Feasibility Study. The record is “teeming with specific factual challenges to [the Institute’s Feasibility Study] tendered to the Corps[.]”239 “Specific challenges to a report used by the Corps in its public interest review require specific responses or a determination that the report is not being relied upon in its challenged aspects.”240 The Corps, in endorsing Diamond State’s unreasoned response to concerns about the turning basin and navigation, relied on the Feasibility Study to justify its conclusion use of the turning basin would not impact traffic in the main channel. The Corps argues, despite these infirmities, we must defer to an agency’s resolution of a fact dispute in its area of expertise, citing Friends of Capital Crescent Trail v. Federal Transit Administration.241 But the Court of Appeals for the District of Columbia Circuit in Friends of
Capital Crescent Trail considered an agency’s reliance on the findings of its own experts, holding “[w]hen specialists express conflicting views, an agency must have discretion to rely on the reasonable opinions of its own qualified experts[.]”242 And even where the agency relied on its own expert, the Court of Appeals for the District of Columbia Circuit cautioned we “should not automatically defer to [agency experts]. . . without carefully reviewing the record and satisfying [our]selves that the agency has made a reasoned decision based on its evaluation of the significance—or lack of significance—of the new information.’”243 Commenters raised concerns to the Corps about traffic resulting from use of the turning basin. The Corps had an independent obligation to ensure the soundness and reliability of studies
and data it relied upon through Diamond State in concluding there would be no impacts to navigation.244 The Corps did not carry out these duties when responding to comments about the deficiencies in the Feasibility Study and further studies which might be required. The Corps either adopted Diamond State’s dismissals without explanation or provided a response which simply concluded there were no impacts.245 We agree with reasoning from the United States Court of Appeals for the Second Circuit “a decision made in reliance on false information, developed without an effort in objective good faith to obtain accurate information, cannot be accepted as a ‘reasoned’ decision.”246 The language used by the Corps in responding to public comments is “cryptic and perfunctory[,]” which our colleagues have found can render agency decision making arbitrary and capricious.247 And our Court of Appeals directs “an agency’s order must be upheld on the same basis articulated in the order by the agency itself” so the Corps cannot now remedy its lack of investigation or explanation.248
The Corps argues its consideration of the navigation public interest factor is still entitled to “substantial deference.”249 We agree with colleagues “[u]nder the ‘public interest’ review, the Corps conducts a general balancing of a number of economic and environmental factors and its ultimate determinations are entitled to substantial deference.”250 The Corps’ overall and ultimate balancing of the public interest factors is entitled to “deference” but the Corps’ failure to consider important aspects of the problem on the way to making a decision is not. The Ports further argue the Corps “failed to consider the significant amount of initial and ongoing [operation and maintenance] dredging that will be required to maintain the Edgemoor Terminal and the impact it will cause considering its proximity to the Channel.”251 The Ports noted
in public comments an ongoing dredging operation of the scale anticipated for Edgemoor will lead to congestion at Edgemoor for periods of time each year.252 The Ports in their comment noted dredging equipment would “require exclusive use of the areas of the river they occupy” and “present an additional hazard to navigation” and the dredge pipes would “creat[e] additional traffic and safety concerns for all commercial vessels[.]”253 Diamond State told the Corps there would be dredging activities in the main channel and the dredge pipeline might impact traffic in the main channel, but the Corps did not provide further comment on the issue and marked the matter “closed” without “further comment” in its Decision Document.254 We agree the impact maintenance dredging will have on navigation could be significant, especially where the maintenance dredging is anticipated to be significant and to involve dredging directly next to and with pipelines across the main channel. The Corps “completely failed to consider an important aspect of the problem, or provided an explanation that is contrary to, or implausible in light of, the evidence.”255 The Corps should consider whether these operations will impact navigation in the main channel.
We find the Corps’ consideration of the navigation public interest factor arbitrary and capricious. ii. The Corps must consider the safety factor. The Ports argue the Corps needed to consider the safety impacts of the Edgemoor Project. The Corps disagrees. But its documents confirm the Corps’ decision whether to issue a permit is “based on an evaluation of the probable impacts, including cumulative impacts, of the proposed activity and its intended use on the public interest” and the Corps enumerates “safety” as a factor to be considered.256 And the Corps knew of the safety concerns. Commenters raised safety concerns about the
Edgemoor Project and its intended use. For example, one expert requested a “simulation to adequately assess the safety of [ship] maneuvers needs to be done under adverse conditions of night transits, sudden squalls, and restricted visibility so as to determine the safe limits of vessel navigation and maneuvering alongside the Terminal.”257 And the Institute pilots in the Feasibility Study relied on by Diamond State and the Corps rated the safety of a single vessel turning in the basin with no traffic in the main channel a 5.4/10, with 10 being the safest.258 Some pilots even raised specific safety concerns about the single-ship turning maneuver in their Study comments.259 For example, one pilot noted “I would not make this transit in this vessel in these conditions . . . . I used these tugs to maximize their efficiency and barely controlled the vessel.”260 But the Corps concluded in its Decision Document the “safety” factor was “Not Applicable” to the Project.261 The Corps therefore did not weigh or consider this factor in determining whether the Project ran contrary to the public interest. But “[n]onsignificant impact does not equal no impact.”262 And the Corps never addressed the safety concerns raised by the Study Pilots despite the
Corps’ reliance on the Feasibility Study in other respects. When an agency “cites (allegedly) favorable evidence and disregards unfavorable evidence” from “the same discrete source,” “[s]uch cherry-picking embodies arbitrary and capricious conduct.”263 The Corps argues the Ports impermissibly conflate their navigation concerns with safety concerns and do not present safety concerns untied to navigation.264 But it is Corps, not the Ports, who conflates safety with navigation. The Corps argues it considered safety because it considered navigation.265 The Corps cannot now say it considered an issue it claimed to not consider in its Decision Document with no supporting record evidence.266 But there is record evidence of commenters raising specific safety concerns. The Corps needed to at least respond to public
comments and explain why safety concerns were unwarranted. An agency’s decision is arbitrary and capricious when the agency “entirely fail[s] to consider an important aspect of the problem.”267 We conclude the Corps’ largely non-existent consideration of the safety public interest factor is arbitrary and capricious. The Corps must either consider and weigh the safety risks associated with the project or explain why there are none. iii. The Corps properly considered the Project’s economics. The parties disagree as to whether the Corps appropriately considered the economics of the Edgemoor Project. The Corps’ regulations on the “economics” public interest factor provide: “[w]hen private enterprise makes application for a permit, it will generally be assumed that appropriate economic evaluations have been completed, the proposal is economically viable, and is needed in the market place. However, the district engineer in appropriate cases, may make an independent review of the need for the project from the perspective of the overall public interest.”268 The parties begin by disagreeing as to whether the Corps needed to find Diamond State is
entitled to a presumption of economic viability. The Corps argues it must presume economic viability of the Edgemoor Project because a “private enterprise” submitted the proposal.269 The Ports argue Diamond State is not a “private enterprise” and is in fact a public corporation, which receives public funds and is an arm of the State.270 We remind the Corps we must decide all matters of law.271 The Delaware General Assembly explained in the statute creating Diamond State “[t]here shall be established within the Department of State a body corporate and politic, with corporate succession, constituting a public instrumentality of the State, and created for the purpose of exercising essential governmental functions which is to be known as the ‘Diamond State Port Corporation.’”272 Diamond State is tax exempt and is funded by Delaware taxpayers as allocated by its General Assembly.273 Diamond State is plainly not a private enterprise. The
Corps’ leap to a presumption based on this misimpression lacks merit. The Corps argues, presumption or not, it reasonably found the Edgemoor Project would provide economic benefits to Wilmington.274 The Ports argue the Corps needed to assess the economic impacts of the project on the broader Delaware River region.275 Diamond State supplied considerable information about the economic need for and projected impacts of the Edgemoor Project.276 Many commenters supported the Project for economic reasons including job creation.277 Others argued the Corps should conduct a full economic analysis demonstrating the Edgemoor Project’s need and addressing the economic impacts to the regional and national economies.278 Diamond State and the Corps responded to these concerns during the comment period and made clear the Corps’ Deep Draft Navigation Center considered regional impacts.279 The Corps found, in its Decision Documents, “[e]conomic development opportunities are enhanced through the construction of a 45-ft. berth and access channel as a result of the ability to
attract larger container vessels and the associated reduced transportation costs per TEU.”280 The Corps also found “[t]he new port at Edgemoor is expected to increase jobs, wages, and tax revenue opportunities for the City of Wilmington, and the socioeconomic region” and “is expected to support the growth of over 4,000 jobs annually.”281 The Corps concluded “these changes are expected to benefit the quality of life for many residents in the area.”282 The Corps found these economic and general welfare benefits can be realized only by the Edgemoor Project. The Corps also found the Project addressed an “increase in trade shipping to the eastern seaboard is expected to come through the use of new ships that are larger than those currently in service” and, therefore, “[t]to accommodate these new ships entering east coast ports, the Applicant [Diamond State] anticipates that there will be a demand for expansion of east coast port operations.”283
The Ports argue the Corps needed to consider the potential for Edgemoor to siphon business from other Ports on the Delaware River.284 But the Ports do not cite authority supporting this competition-based argument. The Corps disagrees, relying on Judge Wolf’s analysis thirty-seven years ago in In Mall Properties, Inc. v. Marsh.285 There, Judge Wolf remanded the issues back to the Corps after it denied a Section 404/10 permit for a mall development because of the economic impact it might have on neighboring areas.286 Judge Wolf explained he would “not attribute to Congress and the President the intention to delegate to the Corps the power to deny Mall Properties a permit because a mall anywhere in North Haven would, in its view, unduly injure the economy of New Haven while benefitting North Haven.”287 The Philadelphia Port Authority might feel it is unfair to be subjected to competition from a neighboring port benefitting from the public work the Philadelphia Port Authority agreed to fund. But this is not an appropriate factor for our consideration and we decline to do so. The Corps appropriately considered the economic impacts of the project in its Decision Document.
On balance, we find the Corps’ consideration of the navigation and safety public interest factors is arbitrary and capricious, but the Corps’ consideration of the economic public interest is supported by the record.288 b. The Corps erred in granting section 408 authorization. The parties also disagree as to whether the Corps’ section 408 authorization is arbitrary and capricious. We concluded the Corps needed to review the turning basin in its section 408 review. And we earlier examined the navigation, safety, and economics determinations for the overall project in depth, so we now focus on those issues specific to the section 408 decision. The Corps argues Diamond State did not need to obtain a Statement of No Objection from
the Philadelphia Port Authority (and the omission was harmless error if the Corps had been obligated).289 We conclude the Corps’ own guidance binds it and the Corps should have required Diamond State to obtain a Statement of No Objection from the Philadelphia Port Authority. i. The Project Partnership Agreement noticed the Corps and Diamond State of the Philadelphia Port Authority’s’ interest.
The Ports urge we start with their longstanding obligations under the Project Partnership Agreement. We must first decide whether we can consider the Project Partnership Agreement at all. The Corps argues the Philadelphia Port Authority’s Statement of No Objection argument relies solely on the Philadelphia Port Authority’s Project Partnership Agreement with the Corps for the Delaware River Main Channel Deepening Project, which is extra record evidence, and therefore the Philadelphia Port Authority cannot support its argument.290 The Corps cannot claim it reasonably excluded the Project Partnership Agreement from the administrative record to begin with. The Corps knew about the contract because the Corps is a party to the contract. Even if the Corps somehow forgot about the Project Partnership Agreement
for federal work on the Delaware River worth hundreds of millions of dollars, Diamond State reminded the Corps in its application “[t]he [Corps], in partnership with the Philadelphia Port Authority, currently is deepening the main channel from Philadelphia to the Atlantic Ocean from 40 to 45 feet.”291 And the Philadelphia Port Authority raised its status as the non-federal sponsor of the Delaware River Main Channel Deepening Project in its September 17, 2020 public comments.292 Our Court of Appeals instructs the administrative record can be supplemented “where the administrative record does not disclose the factors considered by an agency or the agency’s construction of the evidence[.]”293 The Corps had to consider the Project Partnership Agreement
in its section 408 decision when it concluded, under the heading “Non-Federal Sponsor,” “[t]he Delaware River, Philadelphia to the Sea River Federal Navigation Project is maintained at 100% Federal expense.”294 Because the Corps could not have reached its conclusion without considering the Project Partnership Agreement, we supplement the administrative record to include the Project Partnership Agreement.295 To exclude it from the record where the Corps necessarily consulted it and drew a conclusion from it would defy logic. And, if the Corps did fail to consider the Project Partnership Agreement with the sole non- federal sponsor of the Delaware Main Channel Deepening Project when a third party sought to alter the project and reached the above conclusion without referencing the contract, the Corps “completely failed to consider an important aspect of the problem” and its section 408 decision is arbitrary and capricious on this ground alone.296 ii. The Corps did not ensure a Statement of No Objection. The Philadelphia Port Authority is the sole non-federal sponsor of the Delaware Main Channel Deepening Project. The Corps requires applicants, as memorialized in the Corps’ POLICY
AND PROCEDURAL GUIDANCE FOR PROCESSING REQUESTS TO ALTER US ARMY CORPS OF ENGINEERS CIVIL WORKS PROJECTS PURSUANT TO 33 USC 408, to obtain and Statement of No Objection from the non-federal sponsor of a federal project before considering the section 408 application.297 The Corps explains the purpose of the Statement of No Objection is to ensure the Non-Federal sponsor “is aware of the scope of the Section 408 request and does not object to the request” before the Corps “initiate[s] the evaluation of the request.”298 The parties disagree as to whether the Corps needed to require Diamond State to obtain a Statement of No Objection from the Philadelphia Port Authority before beginning its section 408 review. The Corps first argues no commenters raised this issue during the comment period, so the
Philadelphia Port Authority waived the argument and it cannot be a basis for overturning the Corps’ decision.299 But our Supreme Court recently rejected a similarly hyper-technical waiver argument.300 And even if we applied waiver to the power of the Corps to approve a Section 408 request without first obtaining the Statement of No Objection, there are exceptions to the waiver rule. The Philadelphia Port Authority did not waive the issue because it is “obvious” and “otherwise brought to the agency’s attention,” which are two recognized exceptions to the waiver rule.301 It is “obvious” to an agency it must follow its own rules and it is “obvious” to an agency a non-federal partner for a project exists where the agency entered into the very Project Partnership Agreement at issue.302 The Corps signed the Project Partnership Agreement with the Philadelphia Port Authority. Suggesting the Corps did not know about a contract to which it is a party defies logic. And, even if it weren’t already obvious, the Philadelphia Port Authority raised its status as the non-federal sponsor of the Delaware River Main Channel Deepening Project and the impact of the Edgemoor Project to its ongoing responsibilities as a non-federal sponsor in its September 17, 2020 public comments, meaning its status as a non-federal sponsor was “otherwise brought to the
agency’s attention.”303 As our Court of Appeals explained, “[b]ecause the Corps ‘had independent knowledge of the very issue that concerns [the Philadelphia Port Authority] in this case, . . . there is no need for a commentator to point them out specifically in order to preserve its ability to challenge a proposed action.’”304 The Corps then argues because its obligation to require applicants to obtain a Statement of No Objection stems from guidance and not a statute or regulation, the Corps’ noncompliance cannot be a basis for overturning the agency action.305 We note the Corps represented in its Diamond State section 408 Decision Document it followed its POLICY AND PROCEDURAL GUIDANCE FOR PROCESSING REQUESTS TO ALTER US ARMY CORPS OF ENGINEERS CIVIL WORKS PROJECTS PURSUANT TO 33 USC 408.306 We conclude agency action is arbitrary and capricious
where an agency fails to adhere to its own procedures without explanation, as is the case here.307 This rule is not conditioned on the source of the procedure in question. The Corps did not attempt to obtain a Statement of No Objection on Diamond State’s behalf or require Diamond State to do so itself, nor did it offer an explanation for failing to follow its own procedures other than to say the federal government maintains the Delaware River Main Channel at 100% federal expense.308 The Corps further argues even if its compliance with its guidance could be the basis for overturning the 408 Approval, the Corps excepts the requirement “when [the Corps] has all operation and maintenance responsibilities for the portion of the [the Corps] project proposed to be altered.”309 The Corps claims it would apply this exception in the present suit because only the Corps has operation and maintenance responsibilities for the portion of the Delaware River Main Channel being altered.310 But the Corps only applies these exceptions where a Statement of No Objection cannot be obtained, and neither Diamond State nor the Corps ever asked the Philadelphia Port Authority in the first instance. We also cannot ignore the Philadelphia Port Authority has
ongoing financial obligations under its Project Partnership Agreement with the Corps for construction and maintenance costs for dredge disposal facilities anywhere within the scope of the Delaware River Main Channel Deepening Project.311 The Corps claims this exception is met because the Edgemoor Project will not increase the Delaware River Main Channel Deepening Project costs. But this theory is not the criteria for the exception. The Philadelphia Port Authority had a right to express concerns regarding Diamond State’s Section 408 request and object to modifications because the Philadelphia Port Authority is a contributing non-federal sponsor of the Delaware River Main Channel Deepening Project, which Diamond State requests navigation- altering use of in perpetuity. And we otherwise do not entertain a post-hoc rationalization: “It is a
foundational principle of administrative law that judicial review of agency action is limited to the grounds that the agency invoked when it took the action.”312 The Corps lastly argues its failure to require a Statement of No Objection is harmless error.313 But obtaining a Statement of No Objection from non-federal sponsors is a threshold requirement. The Corps cannot begin a section 408 review without it. We apply the rule of harmless error where the mistake has no bearing on the substantive decision; the Corps here could not make a decision, substantive or otherwise, without the Statement of No Objection. This mistake if fundamental to beginning the process. It is not harmless error. We do not need to rehash here why the Philadelphia Port Authority had interests worth protecting had it been appropriately consulted. The Corps’ failure to require Diamond State to obtain a Statement of No Objection without explanation is an arbitrary and capricious departure from past practice. The Corps’ section 408 decision is arbitrary and capricious.314
IV. Conclusion We vacate the section 404/10 permit. We vacate the section 408 authorization. The Corps may now reevaluate Diamond State’s applications and take action consistent with their obligations following our conclusions addressing: (1) the scope of the Corps’ review under the Clean Water Act and the Rivers and Harbors Act; (2) the need for reconsideration of navigation and safety issues; and, (3) the Corps’ obligation to ensure Diamond State obtains a Statement of No Objection from the Philadelphia Port Authority. We do not vacate the decisions to require a longer record. We are instead compelled by the extensive record to find the Corps’ decision making arbitrary and capricious.
1 40410AR-__ is a citation to the administrative record for the 404/10 permit, 408AR-__ is a citation to the administrative record for the 408 approval, and PA__ is an extra-record citation to an exhibit to the Ports’ Motion for summary judgment. All cited materials can be found at No. 23- 4283, ECFs 28, 29, 35, and 38. Unless there is a specific citation to a different docket, all ECF citations are to the No. 23-4283 docket for ease of reference.
40410AR-000119 (editorialization in green).
40410AR-000047.
40410AR-004831.
Id.
Water Resources Development Act, Pub. L. No. 102-580, § 101 (6), 106 Stat. 4797 (1992).
40410AR-000047, -62. 40410AR-000148; PA0018.
PA0018–61.
40410AR-000047.
Id.
40410AR-000047–48.
40410AR-000048.
40410AR-000008–33; 33 U.S.C. § 403 (section 10); 33 U.S.C. § 1344 (section 404).
40410AR-000009.
Id.
40410AR-000074.
40410AR-004723; 40410AR-000010.
40410AR-000034–219.
40410AR-000558–70.
40410AR-002709–30.
40410AR-003415–83.
Id.
40410AR-003420. TEU is twenty-foot equivalent units as measurement for cargo capacity.
40410AR-003440.
40410AR-003420, -42.
40410AR-000132–33. 40410AR-000133, -179.
See, e.g., 40410AR-000075.
40410AR-000076. Sediment fans use water propulsion to protect dredged areas from sedimentation.
40410AR-000078; 40410AR-000010.
40410AR-000181.
408AR-000001.
40410AR-004674–83.
40410AR-004674.
40410AR-004675.
40410AR-004676–77.
40410AR-004681.
Id.
40410AR-004721. This first comment period closed on October 1, 2020. Id.
40410AR-004723.
40410AR-004724–41.
40410AR-004725.
40410AR-004726–30.
40410AR-004730–34.
40410AR-004735–37.
40410AR-004737–39.
40410AR-004739–40.
40410AR-004740–41. 40410AR-004730–31.
40410AR-004814.
40410AR-004814–15.
40410AR-004815.
40410AR-004723–28.
40410AR-004832. In their October 1, 2020 comments, Greenwich and Gloucester reference their earlier-submitted August 28, 2020 comments and attach a copy of the same. 40410AR- 004837. Here we highlight comments raised in both submissions.
40410AR-004832.
40410AR-004832–33.
40410AR-004833.
40410AR-004846–50.
40410AR-004852–60.
40410AR-004856.
Id.
40410AR-004857–58.
40410AR-004858.
40410AR-004858–59.
40410AR-008189–93.
40410AR-008190.
Id.
40410AR-008315.
40410AR-008319–20.
40410AR-008329; 40410AR-008334. 408AR-007350 (citing CORPS, EC 1165-2-220 POLICY AND PROCEDURAL GUIDANCE FOR PROCESSING REQUESTS TO ALTER US ARMY CORPS OF ENGINEERS CIVIL WORKS PROJECTS PURSUANT TO 33 USC 408, https://www.mvs.usace.army.mil/Portals/54/EC_1165-2-220.pdf).
76 408AR-007351.
77 408AR-007351–88.
78 408AR-007352.
79 Id.; 408AR-007371–79. A “team from the Philadelphia District and The Coastal Processes Branch, Coastal and Hydraulics Laboratory, U.S. Army Engineer Research and Development Center (ERDC)” conducted an Agency Technical Review as a component of the section 408 review. 408AR-007371–73.
The Agency Technical Review panel flagged the impact to navigation which could accompany the maintenance dredging, but the Corps deemed it unworthy of a responsive comment. 408AR- 007380. The ATR Panel was also informed by Diamond State Port Corporation the dredge pipeline for the maintenance dredging operation may be “required to cross the navigation channel,” and therefore require the installation of “a submerged pipeline,” but the Agency Technical Review Panel stated it had “no further comment” on this point. Id.
408AR-007352.
408AR-007352–53. USACE stands for the United States Army Corps of Engineers.
408AR-007355.
40410AR-010020–84.
40410AR-010021.
Id.
40410AR-010021–22.
40410AR-010029.
40410AR-010042.
Id.
40410AR-010042–43.
40410AR-010043. Confined disposal facilities hold materials dredged from bodies of water. 33 C.F.R. § 320.4(a).
40410AR-010054–55.
40410AR-010055.
40410AR-010056.
40410AR-010075–76.
40410AR-010242–77.
Id. Repeat comments have been listed only once for brevity. 40410AR-010331–48.
40410AR-010331.
Id.
40410AR-010331.
ECF 1.
Id. ¶ 9.
No. 24-1008, ECF 1 ¶ 81.
Id. ¶¶ 81–101.
ECF 24.
ECFs 28, 29, 35, 38, 40. The Philadelphia Port Authority alone brings a separate challenge to the Corps’ section 204(f) authorization, which will be the subject of a later round of briefing.
110 Because the standard for summary judgment is different in Administrative Procedure Act appeals, factual determinations are made by the agency. See, e.g., NVE, Inc. v. Dep’t of Health & Hum. Servs., 436 F.3d 182, 185 (3d Cir. 2006) (in an Administrative Procedure Act case “the District Court’s review is limited to the administrative record”). “[O]ur focus is the administrative record already in existence, not some new record made initially in the reviewing court.” Camp v. Pitts, 411 U.S. 138, 142 (1973). But there are limited exceptions to this rule. We find one such exception applies in this case and we supplement the administrative record to include the Project Partnership Agreement between the Philadelphia Port Authority in the Corps, as we discuss at length below. Other than this limited exception, our review of extra-record facts is limited to our standing inquiry. See Trenton Threatened Skies, Inc v. FAA, 90 F.4th 122, 130 (3d Cir. 2024) (quoting Prometheus Radio Project v. Fed. Commc’ns Comm’n, 939 F.3d 567, 578 (3d Cir. 2019), rev’d on other grounds, 592 U.S. 414 (2021)) (“It is well established that petitioners challenging agency action may supplement the administrative record for the purpose of establishing Article III standing, even though judicial review of agency action is usually limited to the administrative record.”).
111 5 U.S.C. § 702.
112 See Uddin v. Mayorkas, 862 F. Supp .2d 391, 399 (E.D. Pa. 2012) (citations omitted).
113 See id.
114 5 U.S.C. § 706(2)(A); Mirjan v. Attorney Gen. of U.S., 494 Fed. App’x 248, 250 (3d Cir. 2012) (citing Donovan v. Adams Steel Erection, Inc., 766 F.2d 804, 807 (3d Cir. 1985)).
115 Judulang v. Holder, 565 U.S. 42, 52–53 (2011).
116 CBS Corp. v. Fed. Commc’ns Comm’n, 663 F.3d 122, 137 (3d Cir. 2011) (citing Motor Vehicle Mfrs. Ass’n of U.S., Inc. v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983)).
117 NVE, Inc., 436 F.3d at 190; see also Fed. Commc’ns Comm’n v. Fox Television Stations, Inc., 556 U.S. 502, 515 (2009) (noting “the requirement that an agency provide reasoned explanation for its action”).
118 Motor Vehicle Mfrs., 463 U.S. at 50.
119 Culclasure v. Comm’r of Soc. Sec. Admin., 375 F. Supp. 3d 559, 570 (E.D. Pa. 2019) (quoting United States v. L. A. Tucker Truck Lines, Inc., 344 U.S. 33, 37 (1952)).
120 Ohio v. EPA, 144 S. Ct. 2040, 2055 (2024) (cleaned up).
121 Del. Riverkeeper Network v. U.S. Army Corps of Eng’rs, 869 F.3d 148, 155 (3d Cir. 2017) (citation omitted).
122 5 U.S.C. § 706 (“To the extent necessary to decision and when presented, the reviewing court shall decide all relevant questions of law, interpret constitutional and statutory provisions, and determine the meaning or applicability of the terms of an agency action.”); see also Natural Res. Council v. EPA, 755 F.3d 1010, 1022–23 (D.C. Cir. 2014) (no waiver where challenge was to EPA’s “key assumption” it had statutory authority to exempt some hazardous-waste-derived fuels from regulation).
123 Loper Bright Enters. v. Raimondo, 144 S. Ct. 2244, 2273 (2024).
124 5 U.S.C. § 706(2)(A). 125 Michigan v. EPA, 576 U.S. 743, 750 (2015) (quoting Allentown Mack Sales & Serv., Inc. v. NLRB, 522 U.S. 359, 374 (1998)).
NVE, Inc., 436 F.3d at 190.
Id. § 1344.
40 C.F.R. § 230, et seq.
States v. Pa. Indus. Chem. Corp., 411 U.S. 655, 663 (1973).
33 C.F.R. § 322, et seq.
Id. §§ 325.3(a), (a)(13).
Id. § 320.4(a); see also Towns of Norfolk & Walpole v. U.S. Army Corps of Eng’rs, 772 F. Supp. 680, 683 (D. Mass. 1991), aff’d sub nom. Town of Norfolk v. U.S. Army Corps of Eng’rs, 968 F.2d 1438 (1st Cir. 1992).
135 33 C.F.R. § 320.4(a)(1) (emphasis added).
136 Id.; see also id. § 320.4(a)(2) (general considerations for all permits).
137 Id. § 320.4(a)(3) (emphasis added).
138 33 U.S.C. § 408.
139 Id.
140 CORPS, EC 1165-2-220 POLICY AND PROCEDURAL GUIDANCE FOR PROCESSING REQUESTS TO ALTER US ARMY CORPS OF ENGINEERS CIVIL WORKS PROJECTS PURSUANT TO 33 USC 408, 408AR-0078718–817, https://www.mvs.usace.army.mil/Portals/54/EC_1165-2-220.pdf.
141 The Corps reaffirmed and extended the Section 408 Guidance in November 2023. See Corps, ACOE Memorandum for Commanders, Major Subordinate Command and Districts entitled Extension of EC 1165-2-220 dated 30 September 2018, Policy and Procedural Guidance for Processing Requests to Alter US Army Corps of Engineers Civil Works Projects Pursuant to 33 U.S.C. 408 (Nov. 14, 2023), https://www.nap.usace.army.mil/Portals/39/docs/regulatory/408/EC- 1165-2-220-Extension-14-Nov-2023-Signed.pdf?ver=-9WO4vs44NbVRFweHZ2T0A%3D%3D. In the reaffirmation, the Corps explained it was in the process of promulgating regulations under section 408 and the POLICY AND PROCEDURAL GUIDANCE FOR PROCESSING REQUESTS TO ALTER US ARMY CORPS OF ENGINEERS CIVIL WORKS PROJECTS PURSUANT TO 33 U.S.C. 408 would govern until such rules were finalized.
142 CORPS, EC 1165-2-220 POLICY AND PROCEDURAL GUIDANCE FOR PROCESSING REQUESTS TO ALTER US ARMY CORPS OF ENGINEERS CIVIL WORKS PROJECTS PURSUANT TO 33 USC 408, 408AR-0078718–817, at 21, https://www.mvs.usace.army.mil/Portals/54/EC_1165-2-220.pdf.
143 Id. at 16 (emphasis added).
144 Id. at 17.
145 We apply the zone of interests test to determine whether a “statute grants the plaintiff the cause of action that he asserts,” presuming “a statute ordinarily provides a cause of action ‘only to plaintiffs whose interests fall within the zone of interests protected by the law invoked.’” Bank of Am. Corp. v. City of Miami, Fla., 581 U.S. 189, 196–97 (2017) (quoting Lexmark Int’l, Inc. v. Static Control Components, Inc., 572 U.S. 118, 127–28 (2014)).
146 Toll Bros. v. Twp. of Readington, 555 F.3d 131, 137 (3d Cir. 2009) (quoting Lujan v. Defenders of Wildlife, 504 U.S. 555, 560 (1992)).
147 Am. Farm Bureau Fed’n v. EPA, 792 F.3d 281, 293 (3d Cir. 2015) (quoting Massachusetts v. EPA, 549 U.S. 497, 517 (2007)) (emphases removed).
148 ECF 35 at 8–16.
149 Id.
150 ECF 29-2 at 14–18.
151 “It is well established that petitioners challenging agency action may supplement the administrative record for the purpose of establishing Article III standing, even though judicial review of agency action is usually limited to the administrative record.” Trenton Threatened Skies, Inc, 90 F.4th at 130 (quoting Prometheus Radio Project, 939 F.3d at 578).
152 In re Schering-Plough Corp. Intron/Temodar Consumer Class Action, 678 F.3d 235, 244 (3d Cir. 2012) (citation omitted).
153 Doe 1 v. Perkiomen Valley Sch. Dist., 585 F. Supp. 3d 668, 680 (E.D. Pa. 2022) (citation omitted).
154 PA0322–23 (citing National Oceanic and Atmospheric Administration, the Bureau of Ocean Energy Management, and the United States Coast Guard Navigation Center).
155 See, e.g., PA0003; PA0006. 156 PA0003; see also PA0008 (“The scheduling of the ships is done years, months and days ahead of time, being updated as necessary, and the schedule allots each ship a specified window of time to dock at our Terminal.”).
Id.
PA0003. Counsel confirmed the Ports’ pay obligations upon questioning during oral argument.
Id., PA0009.
PA0002–05; see also PA0009.
PA0007.
ECF 29-2 at 52–55.
Mountain States Legal Found. v. Glickman, 92 F.3d 1228, 1234 (D.C. Cir. 1996).
ECF 29-2 at 18.
Id.
ECF 35 at 15.
Lujan, 504 U.S. at 572 n.7. The Court stated more fully:
There is this much truth to the assertion that “procedural rights” are special: The person who has been accorded a procedural right to protect his concrete interests can assert that right without meeting all the normal standards for redressability and immediacy. Thus, under our case law, one living adjacent to the site for proposed construction of a federally licensed dam has standing to challenge the licensing agency’s failure to prepare an environmental impact statement, even though he cannot establish with any certainty that the statement will cause the license to be withheld or altered, and even though the dam will not be completed for many years. . . . Id.
Food & Drug Admin. v. All. for Hippocratic Med., 602 U.S. 367, 382 (2024).
Id. (quoting Lujan, 504 U.S. at 562).
Lujan, 504 U.S. at 562.
Food & Drug Admin., 602 U.S. at 383 (quoting California v. Texas, 593 U.S. 659, 675 (2021)).
Id. at 384. Id. at 384–85 (collecting cases).
ECF 35 at 14 (quoting Food & Drug Admin., 602 U.S. at 383).
ECF 38 at 8 n.3 (citing Mountain States Legal Found., 92 F.3d at 1234–35 (finding standing when government error could lead to wildfire); Sound Action v. U.S. Army Corps of Eng’rs, No. 18-733, 2019 WL 446614, at[*12] (W.D. Wash. Feb. 5, 2019) (plaintiffs claiming aesthetic injury from residents armoring shorelines without a permit had standing to challenge Corps decision leading to the armoring, even though Corps was not “sole source” of injury)).
176 40410AR-010035.
177 Clean Air Council v. United States, 362 F. Supp. 3d 237, 246 (E.D. Pa. 2019).
178 Ctr. for a Sustainable Coast v. U.S. Army Corps of Eng’rs, 100 F.4th 1349, 1356 (11th Cir. 2024).
179 Food & Drug Admin., 602 U.S. at 381.
180 Competitive Enter. Inst. v. Nat’l Highway Traffic Safety Admin., 901 F.2d 107, 117–18 (D.C. Cir. 1990).
181 Id. at 118.
182 No. 24-1008, ECF 1 at 45.
183 See also Ocean Advocates v. U.S. Army Corps of Eng’rs, 402 F.3d 846, 860 (9th Cir. 2005) (plaintiffs challenged Corps’ approval to extend a dock because it would increase tanker traffic and create a “greater potential for an oil spill” and sufficient for standing because evidence showed the dock “would contribute to the risk of an oil spill”); Mountain States Legal Found., 92 F.3d at 1234–35 (plaintiffs had standing to challenge government plan to harvest timber based on risk error could lead to wildfire); Kentuckians for Commonwealth v. U.S. Army Corps of Eng’rs, 963 F. Supp. 2d 670, 672–81 (W.D. Ky. 2013) (plaintiffs had standing to challenge Corps’ public interest review of mining permits based on risk of impacts to human health).
184 5 U.S.C. § 706; Loper Bright, 144 S. Ct. at 2273 (“Courts must exercise their independent judgment in deciding whether an agency has acted within its statutory authority, as the APA requires.”).
185 In its Notice of Specific Challenges, the Philadelphia Port Authority noticed an intent to challenge the Corps’ decision to not hold public hearings, arguing “[t]he Army Corps’ statement that ‘the Corps determined that issues raised in the request for a public hearing were insubstantial and could be addressed without a public hearing’ is not adequately supported.” No. 24-1008, ECF 20 at 9. Although the Philadelphia Port Authority submitted comments asking for a public hearing, it did not allege the Section 404/10 Permit should be overturned because the Corps did not hold a public hearing. The Ports also did not brief this argument in their motion for summary judgment. The argument has been waived.
186 Congress mandates in full:
The creation of any obstruction not affirmatively authorized by Congress, to the navigable capacity of any of the waters of the United States is prohibited; and it shall not be lawful to build or commence the building of any wharf, pier, dolphin, boom, weir, breakwater, bulkhead, jetty, or other structures in any port, roadstead, haven, harbor, canal, navigable river, or other water of the United States, outside established harbor lines, or where no harbor lines have been established, except on plans recommended by the Chief of Engineers and authorized by the Secretary of the Army; and it shall not be lawful to excavate or fill, or in any manner to alter or modify the course, location, condition, or capacity of, any port, roadstead, haven, harbor, canal, lake, harbor of refuge, or inclosure within the limits of any breakwater, or of the channel of any navigable water of the United States, unless the work has been recommended by the Chief of Engineers and authorized by the Secretary of the Army prior to beginning the same.
187 Sierra Club v. Andrus, 610 F.2d 581, 594 (9th Cir. 1979), rev’d on other grounds sub nom. California v. Sierra Club, 451 U.S. 287 (1981), and vacated on other grounds sub nom. Sierra Club v. Watt, 451 U.S. 965 (1981).
188 Id.
189 Id.
190 33 U.S.C. § 403.
191 ECF 28 at 21 (citing Town of Norfolk, 968 F.2d at 1454–55; Envtl. Coal. of Broward Cnty., Inc. v. Myers, 831 F.2d 984, 986 (11th Cir. 1987)).
192 Loper Bright, 144 S. Ct. at 2273.
193 5 U.S.C. § 706(2)(A).
194 ECF 35 at 16–17.
195 Id.
196 33 U.S.C. § 403. 197 Wyandotte Transp. Co. v. United States, 389 U.S. 191, 201 (1967); see also United States v. Republic Steel Corp., 362 U.S. 482, 488 (1960) (The “broad construction given s 10 of the 1890 Act was carried over to s 10 of the 1899 Act[.]”).
199 40410AR-010056.
200 W.R. Grace & Co. v. EPA, 261 F.3d 330, 338 (3d Cir. 2001).
201 Setting the use of the turning basin aside, construction of the turning basin as an element of the Edgemoor Project required dredging itself, which is undoubtably subject to a 404/10 permit and review. The Corps admitted “[t]he ship pilots in the Navigation and Safety Study recommended that the design plans consider deepening an additional area near the Wilmington Port Expansion ‘to provide additional maneuvering space as inbound vessels turn in the turning basin.’” ECF 28 at 24 (citing 40410AR-003442). Per the Corps, “Diamond State Port Corporation adopted the ship pilots’ design recommendation to deepen those additional areas in the final plans.” Id. at 25 (citing 40410AR-010243) (“The simulation was performed by Delaware River Pilots, who are responsible for the navigation on the river, and the layout of the basin was adjusted based on the comments received in the simulation by the pilots, tug boat captains and the USACE Representatives.”). The Corps has not and cannot argue dredging activities in the waters of the United States are not subject to its review.
202 33 U.S.C. § 408.
203 ECF 35 at 18–19. The Corps further argues Congress prohibits impairing the usefulness of a public works project by “fastening vessels” to it, but because transient vessels in the Turning Basin are not “fastened” they are outside of section 408’s scope. The Corps argues the construction rule the “specific governs the general” controls. Ki Se Lee v. Ashcroft, 368 F.3d 218, 223 (3d Cir. 2004) (specific governs the general in statutory construction). But “fastening vessels” is an enumerated example posed in the alternative to “take possession of,” “or make use of for any purpose, “or in any manner whatever impair the usefulness of.” The “or”s in the statute must be given their meaning, and the specific does not govern the general where the terms at issue are phrased in the alternative.
204 ECF 35 at 19 (citing 46 U.S.C. § 70001(a)).
205 33 U.S.C. § 408.
206 See United States v. Fed. Barge Lines, Inc., 573 F.2d 993, 997 (8th Cir. 1978). Federal Barge Lines concerned whether a sunken barge “impair[ed] the usefulness” under Section 408 of a nearby dam when the barge did not cause physical damage to the dam, but instead created turbulence below. The United States Court of Appeals for the Eighth Circuit was “convinced that section 408 should be interpreted broadly to cover [such an] impairment to the usefulness of the dam” because the plain language of the statute is not limited to structural impairment. Id. This “interpretation,” the court explained, “accords with the purpose of the Rivers and Harbors Act,” which is “to protect, preserve, and make safe the Nation’s navigable waterways.” Id.; see also Russelville Legends LLC v. U.S. Army Corps of Eng’rs, 24 F. 4th 1192, 1195 (8th Cir. 2022) (stating the breadth of the language “impairing the usefulness” of a work in Section 408 “in any manner whatever” is “significant because someone could undoubtedly impair the usefulness of a Corps project from outside its boundaries.”).
40410AR-004721–22.
408AR-007352–53.
See, e.g., 46 U.S.C. § 70001.
Id.
Id. § 320.4(a)(3).
Ohio Valley Envtl. Coalition v. U.S. Army Corps of Eng’rs, No. 08-0979, 2013 WL 1305732, at *9 (S.D. W.Va. Mar. 28, 2013).
216 The parties disagree as to whether the Corps needed to consider the cumulative impacts of the public interest factors. ECF 28 at 31–32; ECF 29-2 at 30–31. But the Corps makes clear in its regulations “[t]he decision whether to issue a permit will be based on an evaluation of the probable impacts, including cumulative impacts, of the proposed activity and its intended use on the public interest.” 33 C.F.R. § 320.4(a)(1) (emphasis added).
Id. § 320.4(a)(3).
40410AR-003415–83.
Id.
40410AR-003428–32, 37–39.
40410AR-010047.
See, e.g., 40410AR-004721–23.
40410AR-010056. 40410AR-010075–76.
408AR-007352–53.
ECF 28 at 23–26; ECF 35 at 24 (“Although the Corps was not required to analyze the navigation and safety impacts of the Turning Basin, it reasonably relied upon the MITAGS Navigation and Safety Study to conclude that the Wilmington Port Expansion and Turning Basin would not impair navigability of the Delaware River Channel.” (citing 40410AR-003441-42)).
ECF 28 at 22–23; ECF 35 at 24.
40410AR-004832.
40410AR-004852–60.
40410AR-004856–58.
ECF 28 at 28.
Id. (citing 40410AR-010268).
ECF 35 at 26 (citing Friends of the Earth v. Hintz, 800 F.2d 822, 834–35 (9th Cir.1986)).
Van Abbema v. Fornell, 807 F.2d 633, 639 (7th Cir. 1986). “The Corps certainly may utilize reports and facts derived from outside reports and sources” but the Corps is “responsible for the independent verification of specifically challenged information obtained from applicants or outside consultants.” Id.
236 See, e.g., 40410AR-000047 (“According to the DSPC Strategic Master Plan, conservative assumptions forecast that the share of the Asian trade arriving at East Coast ports will expand between 27 to 32 percent above the average volumes experienced over the past five years.”); 40410AR-000132 (“[T]he expansion of the Port to Edgemoor will promote vessel traffic to increase 55% over current traffic[.]”; 40410AR-000181 (“Commercial shipping activity is expected to increase in the project area upon completion of the new container port facility.”); 40410AR-000161 (“The increase in underwater noise generated from ship traffic will be an insignificant change, given that the Delaware River is frequently traversed by large commercial vessels.”).
237 40410AR-000191.
238 Id.
239 Van Abbema, 807 F.2d at 643.
240 Id. 241 ECF 35 at 25 (citing 877 F.3d 1051, 1059 (D.C. Cir. 2017)).
242 Friends of Cap. Crescent Trail, 877 F.3d at 1059 (quoting Marsh v. Oregon Nat. Res. Council, 490 U.S. 360, 378 (1989)).
243 Id. (quoting Marsh, 490 U.S. at 378).
244 Van Abbema, 807 F.2d at 643.
245 See, e.g., Envtl. Health Trust v. Fed. Commc’ns Comm’n, 9 F.4th 893, 904–06 (D.C. Cir. 2021) (an agency cannot justify decision making based upon the unreasoned analysis of a third party).
246 Sierra Club v. U.S. Army Corps of Eng’rs, 701 F.2d 1011, 1035 (2d Cir. 1983).
247 HLI Lordship Industries, Inc. v. Comm. for Purchase from the Blind and other Severely Handicapped, 791 F.2d 1136, 1141 (4th Cir. 1986); see also Pub. Emps. for Envtl. Resp. v. Nat’l Park Serv., 605 F. Supp. 3d 28, 41 (D.D.C. 2022) (“An agency must do more than merely nod to concerns raised by commenters only to dismiss them in a conclusory manner . . . .” (cleaned up)).
248 W.R. Grace & Co., 261 F.3d at 338.
249 ECF 35 at 23 (citing Town of Norfolk, 968 F.2d at 1454–55; Myers, 831 F.2d at 986; Forsyth Cnty. v. U.S. Army Corps of Eng’rs, 633 F.3d 1032, 1041–42 (11th Cir. 2011)).
Town of Norfolk, 968 F.2d at 1454–55 (emphasis added).
ECF 29-2 at 57 (citing 408AR-007380).
40410AR-008329.
Id.
408AR-007380.
NVE, Inc., 436 F.3d at 190.
40410AR-004858.
40410AR-003440.
See, e.g., 40410AR-003457 (did not complete berthing as “wind was too high directly on the beam”). 260 40410AR-003462.
261 40410AR-010055.
262 State of N.C. v. Hudson, 665 F.Supp. 428, 446 (E.D.N.C. July 7, 1987); see also Sierra Club v. FERC, 867 F.3d 1357, 1375 (D.C. Cir. 2017) (“[W]hen an agency thinks the good consequences of a project will outweigh the bad, the agency still needs to discuss both the good and the bad.”).
Sierra Club, 177 F. Supp. 3d at 540.
ECF 35 at 27–28.
ECF 28 at 22–27.
W.R. Grace & Co., 261 F.3d at 338.
Motor Vehicle Mfrs. Ass’n, 463 U.S. at 43.
ECF 28 at 32–33 and n.17.
ECF 29-2 at 46–47 n.24 (citing 29 Del. Code §§ 8781, 8788).
29 Del. Code § 8781 (emphasis added).
Id. § 8787 (“[T]he Corporation will be exercising essential governmental functions. To this end, the Corporation shall not be required to pay any taxes or assessments or charges of any character[.]”); id. § 8788 (“If the Corporation’s final budget for any fiscal year includes a proposal for an appropriation from the General Assembly for operating or capital funds, the budget shall be approved by the Chair of the Corporation before its submission to the General Assembly as part of the Governor’s proposed capital or operating budget.”).
274 ECF 35 at 28–31.
275 ECF 29-2 at 55–57.
276 40410AR-000116–33; 40410AR-002709–30.
277 See, e.g., 40410AR-004799; 40410AR-004805; 40410AR-004807; 40410AR-004809; 40410AR-004811; 40410AR-004819.
278 See, e.g., 40410AR-004700; 40410AR-004735; 40410AR-004813; 40410AR-004821; 40410AR- 004825. 279 See, e.g., Comment: “The USACE must analyze and give great weight to the reasonably foreseeable detrimental impacts on the economic vitality of other entities in the area, including other regional maritime ports. See 33 C.F.R. §§ 320 and 325. To fulfill this obligation, the USACE has specific guidance on what must be included in an appropriate accounting analysis. As applied to the instant application, the guidance requires that the accounting include an analysis of whether the proposed additional port on the Delaware River is needed or whether this proposed port will pull customers away from other ports on the river and thus undermine the economic viability of the existing ports.”
Applicant Response: “C.F.R. §§ 320 and 325 include language that requires a public interst [sic] but does not imply that USACE should pick favorites between State run Public Ports. However, the independent economic analyis [sic] being performed by the USACE Deep Draft Navigation Center does allocate future growth proportional between regional public ports, and does not reallocate shiping [sic] from ports beyond the existing Port of Wilmington container operations.”
Corps Evaluation: The Corps agrees with DSPC’s response.
40410AR-010248.
40410AR-010055.
40410AR-010056.
Id.
ECF 29-2 at 55–57.
672 F. Supp. 561 (D. Mass 1987).
Id. at 567–69, 575.
Id. at 574; see also id. at 573 (“[D]ecisions concerning which competing constituency’s economic interests ought to be preferred are traditionally made by democratically accountable officials” and not by the Corps, which only has “a central role in this process because of its expertise in matters relating to our nation’s waterways” and not economics).
288 See, e.g., Friends of the Mahoning River v. U.S. Army Corps of Eng’rs, No. 19-2771, 2021 WL 4133763, at *6 (N.D. Ohio Sept. 9, 2021) (reversing Corps’ public interest review); Hudson, 665 F.Supp. at 450 (same); Van Abbema, 807 F.2d at 643 (same). 289 ECF 28 at 43–45.
290 Id. at 43 n.20 (citing ECF 29-13).
291 40410AR-000148.
292 40410AR-004730–31.
293 New Jersey v. U.S. Army Corps of Eng’rs, No. 09-5591, 2010 WL 2771771, at *4 (D.N.J. July 13, 2010) (citing Horizons Int’l, Inc. v. Baldrige, 811 F.2d 154, 161–62 (3d Cir. 1987) and NVE, Inc., 436 F.3d at 195), aff’d sub nom. Del. Dep’t of Nat. Res. & Envtl. Control v. U.S. Army Corps of Eng’rs, 685 F.3d 259 (3d Cir. 2012).
294 408AR-007355.
295 Bergen Cnty. v. Dole, 620 F. Supp. 1009, 1017 (D.N.J. 1985) (quoting Lloyd v. Illinois Regional Transportation Authority, 548 F. Supp. 575, 590 (N.D. Ill. 1982)), aff’d sub nom. Appeal of Bergen Cnty., 800 F.2d 1130 (3d Cir. 1986); State of Del. Dep’t of Nat. Res. & Envtl. Control v. U.S. Army Corp of Eng’rs, 722 F. Supp. 2d 535, 541 (D. Del. 2010) (citing Pac. Shores Subdivision Cal. Water Dist. v. U.S. Army Corps of Eng’rs, 448 F. Supp. 2d 1, 4 (D.D.C. 2006)) (“[T]he record ‘before the agency’ includes all documents and materials ‘directly or indirectly’ considered by agency decision-makers.”).
296 NVE, Inc., 436 F.3d at 190.
297 CORPS, EC 1165-2-220 DISTRICT STANDARD OPERATING PROCEDURE PURSUANT TO 33 U.S.C. § 408, at 16, 408AR-0078718–817, https://www.mvs.usace.army.mil/Portals/54/EC 1165-2- 220.pdf.
298 Id. Similarly, the Corps provides in its Process Guide it is required to obtain a written Statement of No Objection from a non-federal sponsor to document awareness of the scope of the request and there are no objections to the request. If a Statement of No Objection cannot be obtained, the District/Division will not proceed with the Section 408 review unless an exception in the Guidance is identified. Corps, Section 408 Process Guide, Slide 3, https://usace.contentdm.oclc.org/utils/getfile/collection/p16021coll11/id/6569.
299 ECF 28 at 43 (citing Kleissler v. U.S. Forest Serv., 183 F.3d 196, 201 (3d Cir. 1999); Camp, 411 U.S. at 142).
300 See Ohio v. EPA, 144 S. Ct. 2040, 2055 (2024) (“A party need not rehearse the identical argument made before the agency; it need only confirm that the government had notice of the challenge during the public comment period and a chance to consider in substance, if not in form, the same objection now raised in court.”) (cleaned up). The Philadelphia Port Authority further argues the Corps was required to obtain a statement of no objection before it began its Section 408 review, so the Philadelphia Port Authority could not object during the comment period because the error had already occurred.
301 Del. Riverkeeper Network, 869 F.3d at 155.
302 Dep’t of Transp. v. Public Citizen, 541 U.S. 752, 766 (2004) (“[T]he agency bears the primary responsibility to ensure that it complies [with applicable law]” and the flaws in the agency’s analysis “might be so obvious that there is no need for a commentator to point them out specifically in order to preserve its ability to challenge a proposed action.”).
303 40410AR-004730–31.
304 Del. Riverkeeper Network, 869 F.3d at 156 (quoting ‘Ilio’ulaokalani Coal. v. Rumsfeld, 464 F.3d 1083, 1093 (9th Cir. 2006)).
305 ECF 28 at 44 (citing Batterton v. Marshall, 648 F.2d 694, 702 (D.C. Cir. 1980)).
306 408AR-007350, -7352–53, -7377.
307 Hoosier Envtl. Council v. Nat. Prairie Indiana Farmland Holdings, 564 F. Supp. 3d 683, 707 (N.D. Ind. 2021) (“[W]hen an agency follows a procedure inconsistent with the [guidance] manuals, an arbitrary and capricious conclusion can only be avoided if the deviation includes a sufficient explanation why.”); Sierra Club v. Salazar, 177 F. Supp. 3d 512, 537 (D.D.C. 2016) (agency’s “decision to disregard its own guidance is tantamount to the inconsistent treatment of similar situations,” rendering the agency’s decision arbitrary and capricious).
308 Hoosier, 564 F. Supp. 3d at 710 (Corps’ “[f]ailure to follow” its own guidance and policies, “absent an explanation why, is arbitrary and capricious” (citing Bourcher v. USDA, 934 F.3d 530, 547 (7th Cir. 2021)).
309 CORPS, EC 1165-2-220 DISTRICT STANDARD OPERATING PROCEDURE PURSUANT TO 33 U.S.C. § 408, at 16–17, 408AR-0078718–817, https://www.mvs.usace.army.mil/Portals/54/EC 1165-2- 220.pdf.
310 408AR-007355 (“USACE-Philadelphia District is 100% responsible for maintaining the Philadelphia to the Sea Project to authorized depths and reporting depths to all stakeholders along the USACE Project.”); id. (“The Delaware River, Philadelphia to the Sea River Federal Navigation Project is maintained at 100% Federal expense.”).
311 The Philadelphia Port Authority is responsible for the cost of constructing dredge disposal facilities as needed. The Philadelphia Port Authority and the Corps, in Article VII.B of the Project Partnership Agreement, state the Corps is responsible for “all financial obligations” for the operations and maintenance of the Delaware River Main Channel Deepening Project in the first instance. PA0048 (Art. VIII.B). But, as the parties to the agreement detail in Article IV.B.[3] of the Project Partnership Agreement, the Philadelphia Port Authority shares financial responsibility with the Corps for both the construction and the operations and maintenance of dredge disposal facilities on the back end. Id. at PA0042 (Art.VI.B.[3]).
312 Dep’t of Homeland Security v. Regents of the Univ. of Cal., 591 U.S. [1], 20 (2020) (cleaned up).
313 ECF 35 at 22 (citing Del. Riverkeeper Network v. Sec’y Pennsylvania Dep’t of Envtl. Prot., 833 F.3d 360, 377 (3d Cir. 2016)).
314 We will not consider the Ports’ challenge to the Corps’ determination a Safety Assurance Review is not required for the section 408 authorization because we conclude the Statement of No Objection omission dispositive.