Florida Statutes homeSearch Florida Statutes
Fla. Stat.Title XL — Real and Personal PropertyChapter 713 — Liens, Generally

Fla. Stat. § 713.37 (2026)

Rule of construction.

Edition and currency
2026 Florida Statutes: through the 2026 Regular Session. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENT2026 Florida Statutes: through the 2026 Regular Session cited 1982–2010 12citing cases
At a glance

Courts have cited this section in 12 opinions since 1982.

713.37 Rule of construction.—This part shall not be subject to a rule of liberal construction in favor of any person to whom it applies.
History.—s. 15, ch. 77-353.
The 12 cases that cite Fla. Stat. § 713.37 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENTrytek v. Gale Indus., Inc., 3 So. 3d 1194 (Fla. 2009).
cites § 713.37 2×cited by 52 cases
Where it cites § 713.37
“Further, in 1977, the Legislature enacted section 713.37, which states that “[the Construction Lien Law] shall not be subject to a rule of liberal construction in favor of any person to whom it applies.”
The case’s holding
Trial courts must apply the significant issues test to determine the prevailing party for attorney fees in construction lien actions regardless of whether the lienor obtains a judgment.
Later courts cite it for
“it is well-settled that attorneys' fees can derive only from either a statutory basis or an agreement between the parties.” · 8 citing courts
2
GREENSprinkler Fitters v. FITR SERV., 461 So. 2d 144 (Fla. 3d DCA 1984).
cites § 713.37 4×cited by 7 cases
Where it cites § 713.37
“See § 713.37, Fla. Stat. (1981) ("This part [the Mechanics' Lien Law] shall not be subject to a rule of liberal construction in favor of any person to whom it applies.”
The case’s holding
A laborer is not entitled to a mechanics' lien unless the labor is performed under a properly authorized contract directly connecting the laborer to the owner, contractor, or subcontractor.
3
GREENJulian E. Johnson & Sons, Inc. v. Balboa Ins. Co., 408 So. 2d 1044 (Fla. 1982).
cites § 713.37 2×cited by 9 cases
Where it cites § 713.37
“29 reads as follows: In any action brought to enforce a lien under part I of this chapter, the prevailing party shall be entitled to recover a reasonable fee for the services of his attorney, to be determined by the court, which shall be taxed as part of his costs. [3] Ch.…”
The case’s holding
Attorney's fees in suits against a surety on a construction payment bond are limited to 12.5 percent of the judgment under the specific construction bond statute.
4
GREENSaleh v. Watkins, 415 So. 2d 858 (Fla. 5th DCA 1982).
cites § 713.37 2×cited by 6 cases
Where it cites § 713.37
“The contractor shall execute the affidavit and deliver it to the owner at least 5 days before instituting an action as a prerequisite to the institution of any action to enforce his lien under this chapter, even if the final payment has not become due because the contract is…”
The case’s holding
A contractor's failure to deliver the required affidavit at least five days before instituting a lien action renders any amendment to the complaint futile and mandates dismissal.
5
GREENZalay v. Ace Cabinets of Clearwater, Inc., 700 So. 2d 15 (Fla. 2d DCA 1997).
cites § 713.37 2×cited by 6 cases
Where it cites § 713.37
“Thus, the Zalays' argument could apply in virtually any lien action involving persons not in privity. Since 1977, the construction lien statutes have provided that they should not be liberally construed in favor of any person.”
The case’s holding
Statutory limitations on construction liens do not preclude the inclusion of attorneys' fees and costs awarded in a successful lien foreclosure action.
6
GREENCDC Builders, Inc. v. Riviera Almeria, LLC, 51 So. 3d 510 (Fla. 3d DCA 2010).
cites § 713.37 1×cited by 2 cases
Where it cites § 713.37
“” Instead, the trial court relied on its interpretation that chapter 713, when read as a whole, “requires a contractor to comply with all provisions contained therein.”
The case’s holding
Filing inaccurate interim payment affidavits or withholding retainage in accordance with a contract does not warrant the discharge of an otherwise valid construction lien.
7
GREENNew Image Carpets, Inc. v. SANDERY CONST., INC., 541 So. 2d 1235 (Fla. 2d DCA 1989).
cites § 713.37 2×cited by 1 case
Where it cites § 713.37
“§ 713.37, Fla. Stat. (1987) ("This part shall not be subject to a rule of liberal construction.”
The case’s holding
A subcontractor must serve timely notice to the owner to perfect a mechanic's lien, regardless of the general contractor's joint venture status.
8
GREENBracco v. Cardozo, 434 So. 2d 1024 (Fla. 2d DCA 1983).
cites § 713.37 2×cited by 1 case
Where it cites § 713.37
“1981), that the legislature, by enacting section 713.37, which became effective July 1, 1978, abrogated the rule of liberal construction enunciated in Crane Company v.”
9
GREENDavis Water & Waste Indus., Inc. v. Embry Dev. Corp., 603 So. 2d 1357 (Fla. 1st DCA 1992).
cites § 713.37 2×cited by 1 case
Where it cites § 713.37
“§ 713.37, Fla. Stat. (1989). The analysis employed by the special assessment cases is not applicable, since such assessments are statutorily allowed for specially benefitted property, and fairly expansive procedural requirements are imposed by statute in the case of special…”
10
NEUTRALAction Labor of Florida v. Liberty Mut., 879 So. 2d 1240 (Fla. 3d DCA 2004).
cites § 713.37 2×cited by 1 case
Where it cites § 713.37
“01 to include "a temporary help firm as defined in *1242 § 443.”
The case’s holding
A temporary help firm is not a subcontractor under the 1998 Florida Construction Lien Law and therefore cannot claim a lien on real property.
11
NEUTRALWalter E. Heller & Co. Se. v. Palmer-Smith, 504 So. 2d 511 (Fla. 5th DCA 1987).
cites § 713.37 1×cited by 1 case
Where it cites § 713.37
“Section 713.37 provides that “[t]his part shall not be subject to a rule of liberal construction in favor of any person to whom it applies.”
12
NEUTRALTrytek v. Gale Indus., Inc., 997 So. 2d 365 (Fla. 2008).
cites § 713.37 2×cited by 0 cases
Where it cites § 713.37
“Further, in 1977, the Legislature enacted section 713.37, which states that "[the Construction Lien Law] shall not be subject to a rule of liberal construction in favor of any person to whom it applies.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
198219962010

One bar per year. Tallest: 2 cases in 1982. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Fla. Dist. Ct. App.9Fla.3
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments
History.—s. 15, ch. 77-353.
Versions

Edition shown: 2026 Florida Statutes: through the 2026 Regular Session. Syfert holds no earlier or later version of this section.

Florida Statutes Home  |  Search Florida Statutes  |  Search cases for this section  |  syfert.com

This Florida statute resource is curated by this site's author, a Jacksonville, Florida personal injury and workers' compensation attorney (Florida Bar No. 39104). For legal consultation, call 904-383-7448.