NRS
108.225 Priority of liens.
1. The liens provided for in NRS 108.221 to 108.246, inclusive, are preferred to:
(a) Any lien, mortgage or other encumbrance which
may have attached to the property after the commencement of construction of a
work of improvement.
(b) Any lien, mortgage or other encumbrance of
which the lien claimant had no notice and which was unrecorded against the
property at the commencement of construction of a work of improvement.
2. Every mortgage or encumbrance imposed
upon, or conveyance made of, property affected by the liens provided for in NRS 108.221 to 108.246, inclusive, after the commencement
of construction of a work of improvement are subordinate and subject to the
liens provided for in NRS 108.221 to 108.246, inclusive, regardless of the date
of recording the notices of liens.
(Added to NRS by 1965,
1160; A 1993,
2056; 1995,
1506; 2003,
2596)
Notes of Decisions
Je Dunn Northwest, Inc. v. Corus Const. Venture (2011)
nev · cites it 12×
“The district court denied Dunn's motion, finding that pursuant to NRS 108.225 and NRS 108.22112, Dunn's work must have been visible from a reasonable inspection of the property prior to the date that Corus Bank recorded its deed of trust, and Dunn failed to make that showing.”
Wilmington Trust FSB v. A1 Concrete Cutting & Demolition, LLC (2012)
nev · cites it 5×
“It expressly provides that every other mortgage or encumbrance imposed after the commencement of construction of a work of improvement is subordinate and subject to the mechanics’ liens regardless of the recording dates of the notices of liens. Because principles of equity…”
Aladdin Heating Corp. v. Trustees of Central States (1977)
nev · cites it 3×
“Appellants contend this *260 preparatory labor constitutes “work done,” thereby causing their liens to attach and take priority over the deed of trust pursuant to NRS 108.225. 1 It is clear that the “work done” provision of NRS 108.”
Erickson Construction Co. v. Nevada National Bank (1973)
nev · cites it 2×
“The priority of liens in this State is established by NRS 108.225, which provides that mechanics’ liens are superior to mortgages or other encumbrances only when such liens or encumbrances have attached subsequent to the time construction was commenced or when the lienholder had…”
A.F. Construction Co. v. Virgin River Casino Corp. (2002)
nev
“Regarding priority of interests, NRS 108.225(l)(a) provides that mechanic’s liens are preferred to “[a]ny lien, mortgage or other encumbrance which may have attached after the time when the building, improvement or structure was commenced, work done, or materials were commenced…”
Nevada National Bank v. Snyder (1992)
nev
“There, this court held that surveying the land, drafting architectural plans and soil testing did not constitute “work done” within the meaning of NRS 108.225. This court stated: [AJctual on-site construction had not yet started and the architectural, soil testing, and survey…”
Byrd Underground, L.L.C. v. Angaur, L.L.C. (2014)
nev · cites it 20×
“Can a mechanic's lien claimant properly claim lien priority under NRS 108.225 when the dirt/material that is the basis of the lien on the project was placed on a prospective building project site months before the building permit was issued or the general contractor hired?…”
In re Manhattan W. Mechanic's Lien Litig. (2015)
nev · cites it 11×
“Further, nothing in NRS 108.225 changes the priority of a mechanic's lien to a partially SUPREME COURT OF NEVADA 5 (0) 1947A subordinated lien recorded before the mechanic's lien became effective.”
APCO CONSTRUCTION, INC. VS. DIST. CT. (SCOTT FINANCIAL) (2015)
nev · cites it 11×
“Further, nothing in NRS 108.225 changes the priority of a mechanic's lien to a partially SUPREME COURT OF NEVADA 5 (0) 1947A subordinated lien recorded before the mechanic's lien became effective.”
— Nev. Rev. Stat. § 108.225(1) — 1 case
— Nev. Rev. Stat. § 108.225(1)(a) — 1 case
— Nev. Rev. Stat. § 108.225(2) — 1 case
— Nev. Rev. Stat. § 108.225(l)(a) — 1 case
A.F. Construction Co. v. Virgin River Casino Corp. (2002)
nev
“Regarding priority of interests, NRS 108.225(l)(a) provides that mechanic’s liens are preferred to “[a]ny lien, mortgage or other encumbrance which may have attached after the time when the building, improvement or structure was commenced, work done, or materials were commenced…”
Annotations are extracted automatically from the opinions in the
Syfert caselaw corpus and ranked by authority, recency, and
treatment. Dots show Syfertize treatment of the citing case itself.