C.F.R.Title 18Chapter I—Federal Energy Regulatory Commission, Department of EnergySubchapter B—Regulations Under the Federal Power ActPart 16—Procedures Relating to Takeover and Relicensing of Licensed ProjectsSubpart D—Annual Licenses for Projects Subject to Sections 14 and 15 of the Federal Power Act

18 C.F.R. § 16.18 (2026)

Annual licenses for projects subject to sections 14 and 15 of the Federal Power Act

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 ACTIVE · 4 IN 5Y cited 1999–2025 8citing cases
At a glance

Courts have cited this section in 8 opinions since 1999, 4 of them in the last five years. The most litigated part is subsection (c) (1 case).

(a) This section applies to projects with licenses subject to sections 14 and 15 of the Federal Power Act.

(b) The Commission will issue an annual license to an existing licensee under the terms and conditions of the existing license upon expiration of its existing license to allow:

(1) The licensee to continue to operate the project while the Commission reviews any applications for a new license, a nonpower license, an exemption, or a surrender;

(2) The orderly removal of a project, if the United States does not take over a project and no new power or nonpower license or exemption will be issued; or

(3) The orderly transfer of a project to:

(i) The United States, if takeover is elected; or

(ii) A new licensee, if a new power or nonpower license is issued to that licensee.

(c) An annual license issued under this section will be considered renewed automatically without further order of the Commission, unless the Commission orders otherwise.

(d) In issuing an annual license, the Commission may incorporate additional or revised interim conditions if necessary and practical to limit adverse impacts on the environment.

[Order 513, 54 FR 23806, June 2, 1989, as amended by Order 513-A, 55 FR 18, Jan. 2, 1990; Order 540, 57 FR 21738, May 22, 1992]
The 7 cases that cite 18 C.F.R. § 16.18 most heavily, weighted by court and treatment. RelevanceNewestTreatment
cites § 16.18 4×subsections: (c)cited by 9 cases
Where it cites § 16.18
“, 50 FPC 758, 773 (1978)); see also, 18 C.F.R. § 16.18 (b). The Lac Courte court itself observed that “Commission and congressional action is proper even significantly after the license expiration date, and interim licenses should issue so long as the Commission is proceeding in…”
2
GREENCalifornia State Water Resourc v. Ferc, 43 F.4th 920 (9th Cir. 2022).
cites § 16.18 1×cited by 9 cases
Where it cites § 16.18
“§ 808 (a)(1); 18 C.F.R. § 16.18 . 12 CAL. STATE WATER RES.”
Later courts cite it for
“section 401 of the clean water act 33 u.s.c. 1341 'requires states to provide a water quality certification before a federal license or permit can be issued for activities that may result in any discharge into intrastate navigable waters.' states may adopt water quality standards that are more stringent than federal law requires, and any limitation included in the state certification becomes a condition on any federal license.” · 2 citing courts
3
GREENVill. of Morrisville, VT v. FERC, 136 F.4th 1117 (D.C. Cir. 2025).
cites § 16.18 2×cited by 1 case
Where it cites § 16.18
“§ 808 (a)(1); 18 C.F.R. § 16.18 . As a result, during the process of renewal, the withdrawal-and-resubmission practice can create perverse incentives.”
4
GREENRivers v. Comm'n, 201 F.3d 1186 (9th Cir. 2000).
cites § 16.18 1×cited by 19 cases
Where it cites § 16.18
“; 18 C.F.R. § 16.18 (b) (1998). . The Commission delegated its licensing authority to the Director.”
The case’s holding
The Commission may define the no-action alternative as continued operation under existing licenses and use existing environmental conditions as the baseline for environmental impact analysis.
Later courts cite it for
“we are mindful that this court steadfastly abides by the principle that 'legislative history-no matter how clear-can't override statutory text.” · 5 citing courts
5
GREENHoopa Valley Tribe v. Fed. Energy Regulatory Comm'n, 629 F.3d 209 (D.C. Cir. 2010).
cites § 16.18 1×cited by 2 cases
Where it cites § 16.18
“Contrary to the Tribe’s claim, moreover, the “unanticipated, serious impacts” test is consistent with 18 C.F.R. § 16.18 (d). By its terms, § 16.18(d) provides only that “the Commission may incorporate additional or revised interim conditions if necessary and practical to limit adverse impacts on the environment.””
6
GREENAm. Rivers v. Fed. Energy Regulatory Comm'n, 187 F.3d 1007 (9th Cir. 1999).
cites § 16.18 1×cited by 1 case
Where it cites § 16.18
“; 18 C.F.R. § 16.18 (b) (1998). . The Commission delegated its licensing authority to the Director.”
7
NEUTRALCnty. of Butte v. Dept. of Water Resources, 13 Cal. 5th 612 (2022).
cites § 16.18 1×
Where it cites § 16.18
“(See 18 C.F.R. § 16.18 (b)(1) (2022).) A. At the time DWR undertook the relicensing process, FERC regulations allowed applicants to pursue the traditional licensing process or an alternative.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199920122025

One bar per year. Tallest: 3 cases in 2022. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
9th Cir.4D.C. Cir.2Cal.2
By subsection
(c)1 case
California Trout, Inc. v. Fed. Energy Regulatory Comm'n S. California Edison Co., 313 F.3d 1131 (9th Cir. 2002).“, 50 FPC 758, 773 (1978)); see also, 18 C.F.R. § 16.18 (b). The Lac Courte court itself observed that “Commission and congressional action is proper even significantly after the license expiration date, and interim licenses should issue so long as the Commission is proceeding in…”
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.