Skip to main content
C.F.R.Title 29Part 5—Labor Standards Provisions Applicable to Contracts Covering Federally Financed and Assisted Construction (Also Labor Standards Provisions Applicable to Nonconstruction Contracts Subject to the Contract Work Hours and Safety Standards Act)Subpart A—Davis-Bacon and Related Acts Provisions and Procedures

29 C.F.R. § 5.9 (2026)

Suspension of funds

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 ACTIVE · 3 IN 5Y cited 1979–2022 7citing cases
At a glance

Courts have cited this section in 7 opinions since 1979, 3 of them in the last five years.

(a) Suspension and withholding. In the event of failure or refusal of the contractor or any subcontractor to comply with the applicable statutes referenced by § 5.1 and the labor standards clauses contained in § 5.5, whether incorporated into the contract physically, by reference, or by operation of law, the Federal agency (and any other agency), may, upon its own action, or must, upon written request of an authorized representative of the Department of Labor, take such action as may be necessary to cause the suspension of the payment, advance, or guarantee of funds until such time as the violations are discontinued and/or until sufficient funds are withheld as may be considered necessary to compensate workers for the full amount of wages and monetary relief to which they are entitled, and to cover any liquidated damages and pre-judgment or post-judgment interest which may be due.

(b) Cross-withholding. To satisfy a contractor's liability for back wages on a contract, in addition to the suspension and withholding of funds from the contract(s) under which the violation(s) occurred, the necessary funds also may be withheld under any other Federal contract with the same prime contractor, or any other federally assisted contract that is subject to Davis-Bacon labor standards and/or the Contract Work Hours and Safety Standards Act and is held by the same prime contractor, regardless of whether the other contract was awarded or assisted by the same agency.

(c) Cross-withholding from different legal entities. Cross-withholding of funds may be requested from contracts held by other entities that may be considered to be the same prime contractor as that term is defined in § 5.2. Such cross-withholding is appropriate where the separate legal entities have independently consented to it by entering into contracts containing the withholding provisions at § 5.5(a)(2) and (b)(3). Cross-withholding from a contract held by a different legal entity is not appropriate unless the withholding provisions were incorporated in full or by reference in that different legal entity's contract. Absent exceptional circumstances, cross-withholding is not permitted from a contract held by a different legal entity where the Davis-Bacon labor standards were incorporated only by operation of law into that contract.

[88 FR 57740, Aug. 23, 2023]
The 6 cases that cite 29 C.F.R. § 5.9 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENFavel v. Am. Renovation & Constr. Co., 2002 MT 266, 59 P.3d 412.
cites § 5.9 8×cited by 22 cases
The case’s holding
A worker's state common law breach of contract claim seeking wages agreed to in a subcontract incorporating Davis-Bacon prevailing wages is not preempted by the Act and may proceed.
Later courts cite it for
“whether withholding was discretionary or mandatory, the usaf contracting officer had the unilateral authority to make such a decision . . . .” · 2 citing courts
2
GREENInt'l Bhd. Elec v. Farfield Co, 5 F.4th 315 (3d Cir. 2021).
cites § 5.9 1×cited by 32 cases
Where it cites § 5.9
“5,” 29 C.F.R. § 5.9 (emphasis added), but the relevant statute calls only for contractual stipulations that there “may be withheld -45- from the contractor so much of the accrued payments as the contracting officer considers necessary” to pay the required wages.”
The case’s holding
The False Claims Act amendments apply retroactively to all cases pending on or after June 7, 2008, regardless of when the underlying conduct occurred.
Later courts cite it for
“a materiality inquiry under the fca is a holistic, totality-of-the- circumstances examination of whether the false statement has 'a natural tendency to influence, or be capable of influencing, the payment or receipt of money or property.” · 2 citing courts
3
GREENSorenson v. Wadsworth Bros. Construct, 48 F.4th 1146 (10th Cir. 2022).
cites § 5.9 1×cited by 10 cases
Where it cites § 5.9
“…withheld payments, contract termination, and debarment.” T & H Servs., 8 F.4th at 956 (citing 40 U.S.C. §§ 3142–44; 29 C.F.R. §§ 5.9 , 5.12; 48 C.F.R. §§ 22 .406–9, 22.406–11). “If withheld sums are insufficient to adequately compensate employees who have been underpaid, the…”
4
GREENProj. B.A.S.I.C. v. Kemp, 947 F.2d 11 (1st Cir. 1991).
cites § 5.9 1×cited by 157 cases
Where it cites § 5.9
“See 29 C.F.R. § 5.9 (1990) (authorizing DOL orders to enforce prevailing wage-rate laws); see also Davis-Bacon Act, 40 U.”
The case’s holding
Civil contempt requires a violation of a clear and unambiguous order that leaves no reasonable doubt as to the expected behavior and the party responsible.
Later courts cite it for
“civil contempt will lie only if the putative contemnor has violated an order that is clear and unambiguous.” · 9 citing courts
5
GREENAmes Constr. Co. v. Dole, 727 F. Supp. 502 (D. Minn. 1989).
cites § 5.9 1×cited by 6 cases
Where it cites § 5.9
“a federal agency, upon its own action or upon written request of an authorized representative of the Department of Labor, shall take such action as may be necessary to cause a suspension of the payment, advance or guarantee of funds____ 29 C.F.R. § 5.9 . The Act provides that…”
6
REDStanley E. Coutu v. Universities Rsch. Ass'n, 595 F.2d 396 (7th Cir. 1979).
cites § 5.9 1×cited by 2 cases
Reversed by Universities Research Assn., Inc. v. Coutu (1981): the U.S. Supreme Court's own opinion in this case.
Where it cites § 5.9
“This remedy seems inadequate *401 to assure the employees of a full recovery in the present case for three reasons: (1) it is based on the assumption that there are stipulations in the contract, (2) it provides for withholding payment only until the violations are discontinued…”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
197920002022

One bar per year. Tallest: 2 cases in 2021. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
3rd Cir.21st Cir.110th Cir.17th Cir.1D. Minn.1Mont.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.