C.F.R. homeSearch C.F.R.
C.F.R.Title 40Chapter I—Environmental Protection AgencySubchapter H—Ocean DumpingPart 230—Section 404(b)(1) Guidelines for Specification of Disposal Sites for Dredged or Fill MaterialSubpart A—General

40 C.F.R. § 230.6 (2026)

Adaptability

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1991–2021 19citing cases
At a glance

Courts have cited this section in 19 opinions since 1991, 1 of them in the last five years. The most litigated part is subsection (a) (1 case).

(a) The manner in which these Guidelines are used depends on the physical, biological, and chemical nature of the proposed extraction site, the material to be discharged, and the candidate disposal site, including any other important components of the ecosystem being evaluated. Documentation to demonstrate knowledge about the extraction site, materials to be extracted, and the candidate disposal site is an essential component of guideline application. These Guidelines allow evaluation and documentation for a variety of activities, ranging from those with large, complex impacts on the aquatic environment to those for which the impact is likely to be innocuous. It is unlikely that the Guidelines will apply in their entirety to any one activity, no matter how complex. It is anticipated that substantial numbers of permit applications will be for minor, routine activities that have little, if any, potential for significant degradation of the aquatic environment. It generally is not intended or expected that extensive testing, evaluation or analysis will be needed to make findings of compliance in such routine cases. Where the conditions for General permits are met, and where numerous applications for similar activities are likely, the use of General permits will eliminate repetitive evaluation and documentation for individual discharges.

(b) The Guidelines user, including the agency or agencies responsible for implementing the Guidelines, must recognize the different levels of effort that should be associated with varying degrees of impact and require or prepare commensurate documentation. The level of documentation should reflect the significance and complexity of the discharge activity.

(c) An essential part of the evaluation process involves making determinations as to the relevance of any portion(s) of the Guidelines and conducting further evaluation only as needed. However, where portions of the Guidelines review procedure are “short form” evaluations, there still must be sufficient information (including consideration of both individual and cumulative impacts) to support the decision of whether to specify the site for disposal of dredged or fill material and to support the decision to curtail or abbreviate the evaluation process. The presumption against the discharge in § 230.1 applies to this decision-making.

(d) In the case of activities covered by General permits or section 208(b)(4)(B) and (C) Best Management Practices, the analysis and documentation required by the Guidelines will be performed at the time of General permit issuance or section 208(b)(4)(B) and (C) Best Management Practices promulgation and will not be repeated when activities are conducted under a General permit or section 208(b)(4)(B) and (C) Best Management Practices control. These Guidelines do not require reporting or formal written communication at the time individual activities are initiated under a General permit or section 208(b)(4)(B) and (C) Best Management Practices. However, a particular General permit may require appropriate reporting.

The 19 cases that cite 40 C.F.R. § 230.6 most heavily, weighted by court and treatment. RelevanceNewestTreatment
cites § 230.6 2×cited by 9 cases
Where it cites § 230.6
“3d at 1271 (quoting 40 C.F.R. § 230.6 (b) ). "The level of documentation should reflect the significance and complexity of the discharge activity.”
2
GREENGreater Yellowstone Coalition v. Flowers, 359 F.3d 1257 (10th Cir. 2004).
cites § 230.6 1×cited by 78 cases
Where it cites § 230.6
“” 40 C.F.R. § 230.6 (b). They further state that “[ajlthough all requirements in § 230.”
The case’s holding
An incidental take statement anticipating the loss of threatened species does not automatically require an agency to prepare a full environmental impact statement.
Later courts cite it for
“nepa's public involvement requirements are not as well defined when an agency prepares only an ea and not an eis.” · 7 citing courts
cites § 230.6 1×cited by 62 cases
Where it cites § 230.6
“” 40 C.F.R. § 230.6 (b). In addition, “[ajlthough all requirements in § 230.”
The case’s holding
An agency satisfies the Clean Water Act by providing record evidence that it took a hard look at alternatives and reached a meaningful conclusion.
Later courts cite it for
“this does not require a specific level of detail to rebut the presumption, but only record evidence the agency took a hard look at the proposals and reached a meaningful conclusion based on the evidence.” · 5 citing courts
4
GREENStewart v. Potts, 996 F. Supp. 668 (S.D. Tex. 1998).
cites § 230.6 3×cited by 16 cases
Where it cites § 230.6
“40 C.F.R. § 230.6 (b). Using this discretion, the Corps determined that, given the minimal acreage and minimal risks found to be associated with the discharge, its analysis was sufficient.”
The case’s holding
A federal agency acts irrationally, and fails NEPA, by excluding from its environmental review wetlands-adjacent forest that is functionally interdependent with a permitted section 404 project it treats as within its jurisdiction.
Later courts cite it for
“a couple of feet in diameter to less than one-quarter of an acre each.” · 3 citing courts
cites § 230.6 1×cited by 141 cases
The case’s holding
A reviewing court's inquiry must end if the agency's determination is reasonably supported by the administrative record.
Later courts cite it for
“cjourts require a strong showing of bad faith or improper behavior before ordering the supplementation of the administrative record.” · 4 citing courts
6
GREENGreat Rivers Habitat v. US Army Corps of Enginr., 437 F. Supp. 2d 1019 (E.D. Mo. 2006).
cites § 230.6 3×cited by 6 cases
Where it cites § 230.6
“"In evaluating whether a given alternative site is practicable, the Corps may legitimately consider such facts as cost to the applicant and logistics." Sylvester, 882 F.2d at 409.”
7
GREENUtah Council v. United States Army Corp. of Engineers, 187 F. Supp. 2d 1334 (D. Utah 2002).
cites § 230.6 3×cited by 4 cases
Where it cites § 230.6
“The ACE applies these guidelines at the time that it promulgates the NWPs, and no further evaluation pursuant to section 404(b)(1) is required when a project proponent requests to undertake activities pursuant to an established NWP.”
8
GREENFlorida Wildlife Fed'n v. United States Army Corps of Engineers, 401 F. Supp. 2d 1298 (S.D. Fla. 2005).
cites § 230.6 2×cited by 7 cases
Where it cites § 230.6
“40 CFR § 230.6 and .10(a). The Corps must balance “benefits which reasonably may be expected to accrue from the proposal” against the proposal’s “reasonably foreseeable detriments.”
Later courts cite it for
“theory of 'independent utility' on a record such as this can only be considered a post-hoc rationalization to secure a permit as rapidly as possible.” · 2 citing courts
cites § 230.6 1×cited by 16 cases
Where it cites § 230.6
“, 40 C.F.R. §§ 230.6 (d), 230.10. According to the guidelines, the Corps can issue a general permit only where the activities being authorized by the permit are similar both in nature and in impact.”
The case’s holding
An agency's environmental assessment must consider cumulative impacts on non-wetland resources of a permitted project, and mitigation measures may support a no-significant-impact finding only if legally required or integral to the proposal.
Later courts cite it for
“must be imposed by statute or regulation or have been so integrated into the initial proposal that it is impossible to define the proposal without the mitigation.” · 2 citing courts
10
GREENGouger v. US Army Corps of Engineers, 779 F. Supp. 2d 588 (S.D. Tex. 2011).
cites § 230.6 2×cited by 4 cases
Where it cites § 230.6
“" 40 C.F.R. § 230.6 (b). The regulations also provide, "[i]t is anticipated that substantial numbers of permit applications will be for minor, routine activities that have little, if any, potential for significant degradation of the aquatic environment.”
11
REDSierra Club v. United States Army Corps of Engineers, 450 F. Supp. 2d 503 (D.N.J. 2006).
cites § 230.6 1×cited by 7 cases
Vacated by Sierra Club v. United States Army Corps of Engineers (2008): the Court of Appeals for the Third Circuit's own opinion in this case.
Where it cites § 230.6
“10 ; 40 C.F.R. § 230.6 (b); see also Greater Yellowstone Coal.”
12
GREENBragg v. Robertson, 72 F. Supp. 2d 642 (S.D. W. Va. 1999).
cites § 230.6 1×cited by 8 cases
Where it cites § 230.6
“See 40 C.F.R. § 230.6 (c). 32 . The terms " 'aquatic environment’ and 'aquatic ecosystem’ mean waters of the United States, including wetlands, that serve as habitat for interrelated and interacting communities and populations of plants and animals.”
Later courts cite it for
“the director has a nondiscretionary duty under the buffer zone rule to deny variances for valley fills in intermittent and perennial streams because they necessarily adversely affect stream flow, stream gradient, fish migration, related environmental values, water quality and quantity, and violate state and federal water quality standards,” · 2 citing courts
cites § 230.6 1×cited by 3 cases
Where it cites § 230.6
“40 C.F.R. § 230.6 . The adaptability of the Guidelines is again mentioned in the short introductory note to § 230.”
Later courts cite it for
“serve as habitat for interrelated and interacting communities and populations of plants and animals.” · 2 citing courts
14
GREENAlaska Ctr. for the Env't v. West, 157 F.3d 680 (9th Cir. 1998).
cites § 230.6 1×cited by 3 cases
Where it cites § 230.6
“Thus, the general permits allow the Corps to circumvent the process of specific approval “where numerous applications for similar activities are likely_” 40 C.F.R. § 230.6 (a). General permits may issue for only five years, and the Corps has the authority to revoke them if it…”
Later courts cite it for
“buffer zones to protect adjacent wetlands and waterbodies of higher environmental value; limits on the type of discharge materials; a requirement that the applicant receive an initial opinion of compliance from the municipality” · 1 citing court
15
NO FLAGClatsop Residents Against Walm v. U.S. Army Corps of Engineers, No. 16-35767 (9th Cir. May 25, 2018).
cites § 230.6 1×cited by 0 casesunpublished
Where it cites § 230.6
“” 40 C.F.R. § 230.6 (b). Given that the fill permit at issue in this case relates to a .”
16
NO FLAGFriends of the Capital C.T. v. United States Army Corps, No. 20-1544 (4th Cir. May 13, 2021).
cites § 230.6 1×cited by 0 casesunpublished
Where it cites § 230.6
“”); see also 40 C.F.R. § 230.6 (b) (explaining that the “level[] of effort” required of the Corps will vary with the “degree[] of [aquatic] impact” of the project).”
cites § 230.6 1×cited by 0 casesunknown
Where it cites § 230.6
“” Likewise, 40 C.F.R. § 230.6 specifies that when it comes to permit applications for projects that “have little, if any, potential for significant degradation of the aquatic 2 Because the Court rejects Plaintiffs’ arguments regarding the alleged superiority of this alignment,…”
cites § 230.6 1×cited by 0 casesunknown
Where it cites § 230.6
“” Likewise, 40 C.F.R. § 230.6 specifies that when it comes to permit applications for projects that “have little, if any, potential for significant degradation of the aquatic 2 Because the Court rejects Plaintiffs’ arguments regarding the alleged superiority of this alignment,…”
19
GREENTown of Norfolk v. United States Army, No. 91-2215 (1st Cir. July 15, 1992).
cites § 230.6 1×subsections: (a)cited by 0 cases
Where it cites § 230.6
“Clearly, the guidelines contemplate an analysis which varies in magnitude depending on the impact of the proposed discharge, rather than the dogmatic scrutiny suggested by the Towns.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199120062021

One bar per year. Tallest: 2 cases in 1992. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
10th Cir.31st Cir.29th Cir.2D. Md.2S.D. Tex.24th Cir.1S.D. Fla.1D. Mass.1

The 8 courts with the most citing cases, of 13 courts in all.

By subsection
(a)1 case
Town of Norfolk v. United States Army, No. 91-2215 (1st Cir. July 15, 1992).“Clearly, the guidelines contemplate an analysis which varies in magnitude depending on the impact of the proposed discharge, rather than the dogmatic scrutiny suggested by the Towns.”
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com