40 C.F.R. § 264.54
Amendment of contingency plan
The contingency plan must be reviewed, and immediately amended, if necessary, whenever:
(a) The facility permit is revised;
(b) The plan fails in an emergency;
(c) The facility changes—in its design, construction, operation, maintenance, or other circumstances—in a way that materially increases the potential for fires, explosions, or releases of hazardous waste or hazardous waste constituents, or changes the response necessary in an emergency;
(d) The list of emergency coordinators changes; or
(e) The list of emergency equipment changes.
Notes of Decisions
Cited in 1
case, 1983–1983 · leading case: Opinion No. (1983) (Mo. Att'y Gen. 1983).
Opinion No. (1983) (Mo. Att'y Gen. 1983). “011 (5)(E), (5)(G)2, and (5)(G)7, the state regulations require certain things be done promptly, whereas 40 CFR 264.54 , 264.56 (b) and 264.56 (g) require those same things to be done immediately.”