Skip to main content
C.F.R.Title 48Chapter 1—Federal Acquisition RegulationSubchapter C—Contracting Methods and Contract TypesPart 14—Sealed BiddingSubpart 14.4—Opening of Bids and Award of Contract

48 C.F.R. § 14.404-1 (2026)

14.404-1 Cancellation of invitations after opening.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1985–2021 25citing cases
At a glance

Courts have cited this section in 25 opinions since 1985, 1 of them in the last five years. The most litigated part is subsection (e)(1) (1 case).

(a)(1) Preservation of the integrity of the competitive bid system dictates that, after bids have been opened, award must be made to that responsible bidder who submitted the lowest responsive bid, unless there is a compelling reason to reject all bids and cancel the invitation.

(2) Every effort shall be made to anticipate changes in a requirement before the date of opening and to notify all prospective bidders of any resulting modification or cancellation. This will permit bidders to change their bids and prevent unnecessary exposure of bid prices.

(3) As a general rule, after the opening of bids, an invitation should not be cancelled and resolicited due solely to increased requirements for the items being acquired. Award should be made on the initial invitation for bids and the additional quantity should be treated as a new acquisition.

(b) When it is determined before award but after opening that the requirements of 11.201 (relating to the availability and identification of specifications) have not been met, the invitation shall be cancelled.

(c) Invitations may be cancelled and all bids rejected before award but after opening when, consistent with paragraph (a)(1) above, the agency head determines in writing that—

(1) Inadequate or ambiguous specifications were cited in the invitation;

(2) Specifications have been revised;

(3) The supplies or services being contracted for are no longer required;

(4) The invitation did not provide for consideration of all factors of cost to the Government, such as cost of transporting Government-furnished property to bidders' plants;

(5) Bids received indicate that the needs of the Government can be satisfied by a less expensive article differing from that for which the bids were invited;

(6) All otherwise acceptable bids received are at unreasonable prices, or only one bid is received and the contracting officer cannot determine the reasonableness of the bid price;

(7) The bids were not independently arrived at in open competition, were collusive, or were submitted in bad faith (see subpart 3.3 for reports to be made to the Department of Justice);

(8) No responsive bid has been received from a responsible bidder.

(9) A cost comparison as prescribed in OMB Circular A-76 and subpart 7.3 shows that performance by the Government is more economical; or

(10) For other reasons, cancellation is clearly in the public's interest.

(d) Should administrative difficulties be encountered after bid opening that may delay award beyond bidders' acceptance periods, the several lowest bidders whose bids have not expired (irrespective of the acceptance period specified in the bid) should be requested, before expiration of their bids, to extend in writing the bid acceptance period (with consent of sureties, if any) in order to avoid the need for resoliciting.

(e) Under some circumstances, completion of the acquisition after cancellation of the invitation for bids may be appropriate.

(1) If the invitation for bids has been cancelled for the reasons specified in subparagraphs (c) (6), (7), or (8) of this subsection, and the agency head has authorized, in the determination in paragraph (c) of this subsection, the completion of the acquisition through negotiation, the contracting officer shall proceed in accordance with paragraph (f) of this subsection.

(2) If the invitation for bids has been cancelled for the reasons specified in subparagraphs (c) (1), (2), (4), (5), or (10) of this subsection, or for the reasons in subparagraphs (c) (6), (7), or (8) of this subsection and completion through negotiation is not authorized under subparagraph (e)(1) of this subsection, the contracting officer shall proceed with a new acquisition.

(f) When the agency head has determined, in accordance with paragraph (e)(1) of this subsection, that an invitation for bids should be canceled and that use of negotiation is in the Government's interest, the contracting officer may negotiate (in accordance with part 15, as appropriate) and make award without issuing a new solicitation provided—

(1) Each responsible bidder in the sealed bid acquisition has been given notice that negotiations will be conducted and has been given an opportunity to participate in negotiations; and

(2) The award is made to the responsible bidder offering the lowest negotiated price.

[48 FR 42171, Sept. 19, 1983, as amended at 50 FR 1738, Jan. 11, 1985; 50 FR 52429, Dec. 23, 1985; 55 FR 52790, Dec. 21, 1990; 60 FR 48248, Sept. 18, 1995; 62 FR 51230, Sept. 30, 1997]
The 20 cases that cite 48 C.F.R. § 14.404-1 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENVets. Contracting Grp., Inc. v. United States, 920 F.3d 801 (Fed. Cir. 2019).
cites § 14.404-1 4×cited by 27 cases
Where it cites § 14.404-1
“UNITED STATES 48 C.F.R. § 14.404-1 (c)(6), which permits cancellation when “[a]ll otherwise acceptable bids received are at un- reasonable prices.”
The case’s holding
A solicitation cancellation is not arbitrary or capricious if the contracting officer has a reasonable motivation for the cancellation.
Later courts cite it for
“in a bid protest, we follow administrative procedure act 706 and set aside agency action 'if it is arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” · 11 citing courts
2
GREENNat'l Forge Co. v. United States, 779 F.2d 665 (Fed. Cir. 1985).
cites § 14.404-1 4×cited by 38 cases
Where it cites § 14.404-1
“1 It argued that the government failed to comply with 48 C.F.R. § 14.404-1 , which limits an agency’s authority to cancel a solicitation after the bids have been opened.”
The case’s holding
In a pre-ADRA case, a court reviewing post-opening cancellation of a solicitation asks only whether the contracting officer's interpretation and cancellation decision were unreasonable or an abuse of discretion under the regulation.
Later courts cite it for
“the claims court correctly restricted its legal review to whether the contracting officer's interpretation of, and later decision to cancel, the solicitation was unreasonable or an abuse of discretion under the requirements for cancellation set forth in 48 c.f.r. 14 .404-1(c)” · 2 citing courts
3
GREENFirst Enter. v. United States, 61 Fed. Cl. 109 (Fed. Cl. 2004).
cites § 14.404-1 3×cited by 22 cases
Where it cites § 14.404-1
“” 48 C.F.R. § 14.404-1 (a)(l) (2004). A compelling reason includes instances where “the agency head determines in writing that [a]ll otherwise acceptable bids received are at unreasonable prices.”
Later courts cite it for
“an agency has virtually a carte blanche right to decide the amount of funding it will spend on a given project.” · 2 citing courts
4
GREENBrickwood Contractors, Inc. v. United States, 49 Fed. Cl. 148 (Fed. Cl. 2001).
cites § 14.404-1 5×cited by 5 cases
Where it cites § 14.404-1
“” 48 C.F.R. § 14.404-1 (c)(3). Assuming for the moment that the present case fits under the (c)(3) criteria, the FAR (at FAR 14.404-l(e)(l)) does not permit a conversion to a negotiated procurement when an IFB is cancelled under (c)(3).”
5
GREENMORI Assocs., Inc. v. United States, 102 Fed. Cl. 503 (Fed. Cl. 2011).
cites § 14.404-1 1×cited by 72 cases
Where it cites § 14.404-1
“703, 713-14 (1985) (applying the higher “compelling reason” standard of 48 C.F.R. § 14.404-1 (a)(1)). But in the absence of any specific limitation on cancellation of a solicitation, a cancellation was subject to the “constraints .”
The case’s holding
Lost potential profits from arbitrary procurement actions constitute irreparable injury sufficient to support a claim for injunctive relief.
Later courts cite it for
“it is well-established that the potential profits that are lost to offerors when arbitrary procurement actions would deprive them of the opportunity to compete for a contract will normally be sufficient to constitute irreparable injury.” · 5 citing courts
6
GREENCalifornia Marine Cleaning, Inc. v. United States, 42 Fed. Cl. 281 (Fed. Cl. 1998).
cites § 14.404-1 3×cited by 12 cases
Where it cites § 14.404-1
“This statutory provision grants this court jurisdiction to address California Marine’s protest of the cancellation of the solicitation because its protest is founded upon an alleged violation of FAR 14.404-1, 48 C.F.R. § 14.404-1 , which prescribes the circumstances under which the Government may cancel a solicitation after bid opening.”
Later courts cite it for
“government installation' refers to the entire government facility in which the 'designated office' is located.” · 2 citing courts
7
GREENOverstreet Elec. Co. v. United States, 47 Fed. Cl. 728 (Fed. Cl. 2000).
cites § 14.404-1 1×subsections: (e)(1)cited by 107 cases
Where it cites § 14.404-1
“48 C.F.R. 14.404-1(e)(1) and (f). 11 Plaintiff, however, argues that the Corps erred in rejecting its low bid as including an unreasonable price, alleging that determination was based on an inadequate estimate of the project that materially understated its costs.”
The case’s holding
Potential loss of valuable business may constitute irreparable harm (basis).
Later courts cite it for
“lost opportunity to compete in a fair competitive bidding process for a contract . . . has been found sufficient to prove irreparable harm.” · 5 citing courts
8
GREENGreat Lakes Dredge & Dock Co. v. United States, 60 Fed. Cl. 350 (Fed. Cl. 2004).
cites § 14.404-1 1×cited by 32 cases
Where it cites § 14.404-1
“See 48 C.F.R. § 14.404-1 (“FAR 14.404-1”). Paragraph (a)(1) provides that the “[preservation of the integrity of the competitive bid system dictates that, after bids have been opened, award must be made to that responsible bidder who submitted the lowest responsive bid, unless…”
Later courts cite it for
“the agency has not considered all relevant factors and articulated a rational connection between the facts found and the choice made.” · 3 citing courts
9
GREENFFTF Restoration Co. v. United States, 86 Fed. Cl. 226 (Fed. Cl. 2009).
cites § 14.404-1 1×cited by 28 cases
Where it cites § 14.404-1
“404 — 1[, 48 C.F.R. 14.404-1 (2004) ]). Thus, the government’s argument amounts to an assertion that cancellation decisions in the negotiated procurement context, such as the one at issue in this case, are immune from any sort of judicial review, including both the “rational…”
The case’s holding
The Court of Federal Claims has jurisdiction under 28 U.S.C. 1491(b)(1) to review an agency's cancellation of a negotiated procurement for compliance with FAR 1.102's mandatory integrity, fairness, and openness duties.
Later courts cite it for
“28 u.s.c. 1491(b)(1) authorizes this court to review cancellations of negotiated procurements to ensure compliance with the requirements of 'integrity, fairness, and openness' in far 1.102(b)(3) and the requirement that 'all contractors and prospective contractors shall be treated fairly and impartially' in far 1.102-2(c)(3).” · 3 citing courts
10
GREENUnited States v. Int'l Bus. MacHines Corp., 892 F.2d 1006 (Fed. Cir. 1990).
cites § 14.404-1 1×cited by 74 cases
Where it cites § 14.404-1
“By restricting the class of eligible protesters to those with a direct economic interest in the award, Congress deliberately relied on the mechanism of economic self-interest to police agencies’ conduct of ADPE procurements.”
The case’s holding
In a sealed-bid procurement where bids differ only in price, the speculative prospect of cancellation and reprocurement is insufficient to grant standing to bidders other than the second-lowest bidder.
Later courts cite it for
“had congress intended to make the exemptions permanent, it knew how: it could and we believe would have used words of futurity....” · 12 citing courts
11
GREENJohn C. Grimberg Co. v. United States, 869 F.2d 1475 (Fed. Cir. 1989).
cites § 14.404-1 2×cited by 12 cases
Where it cites § 14.404-1
“1985) (affirming the Claims Court’s decision upholding the cancellation of a solicitation by the contracting officer on the grounds the contracting officer did not abuse his discretion under 48 C.F.R. § 14.404-1 (c)(l) to cancel the solicitation); Caddell Constr.”
12
GREENCalifornia Marine Cleaning, Inc. v. United States, 43 Fed. Cl. 724 (Fed. Cl. 1999).
cites § 14.404-1 1×cited by 40 cases
Where it cites § 14.404-1
“” 48 C.F.R. §§ 14.404-1 (a)(1), 14.404-1(c)(10) (1997).”
The case’s holding
Cost of living adjustments are contemplated under the Equal Access to Justice Act when an applicant alleges an increase measured by the Consumer Price Index.
Later courts cite it for
“cost of living adjustments are specifically contemplated in the eaja.” · 6 citing courts
13
GREENBean Dredging Corp. v. United States, 19 Cl. Ct. 561 (Ct. Cl. 1990).
cites § 14.404-1 2×cited by 9 cases
Where it cites § 14.404-1
“First, plaintiffs contend that the Corps violated Federal Acquisition Regulation (FAR) § 14.404-1, codified at 48 C.F.R. § 14.404-1 (1988). That section requires the contract to be awarded to the lowest responsible bidder in the absence of a compelling reason for bid rejection and cancellation of the invitation.”
Later courts cite it for
“the relative harm to the defendant, if any, is slight, inasmuch as an award to plaintiffs would be at the lowest competitively bid price . . . .” · 2 citing courts
14
GREENCaddell Constr. Co. v. United States, 7 Cl. Ct. 236 (Ct. Cl. 1985).
cites § 14.404-1 1×cited by 20 cases
Where it cites § 14.404-1
“” 48 C.F.R. § 14.404-1 (c)(6). The authority vested in the contracting officer to decide whether to cancel an IFB and readvertise is extremely broad.”
Later courts cite it for
“a determination concerning the unreasonableness of the prices bid is a matter of administrative discretion which should not be questioned unless the determination is shown to be unreasonable or that there is a showing of fraud or bad faith.” · 2 citing courts
15
GREENNat'l Forge Co. v. United States, 7 Cl. Ct. 530 (Ct. Cl. 1985).
cites § 14.404-1 2×cited by 6 cases
Where it cites § 14.404-1
“Nevertheless, the contracting officer determined that the “inadequate or ambiguous specifications” in the solicitation constituted a compelling reason for cancellation pursuant to 48 CFR § 14.404-1 (1984). Plaintiff was notified of the contracting officer’s decision in an…”
16
GREENDelta Chem. Corp. v. Togo D. West, Jr., 33 F.3d 380 (4th Cir. 1994).
cites § 14.404-1 2×cited by 5 cases
Where it cites § 14.404-1
“48 C.F.R. § 14.404-1 (1993). This provision, which was not discussed by either party, governs the sole issue on appeal, that is, whether an agency must cancel an IFB that includes an overstatement.”
Later courts cite it for
“undeserving of judicial deference!,” · 2 citing courts
17
cites § 14.404-1 2×cited by 3 cases
Where it cites § 14.404-1
“48 C.F.R. § 14.404-1 (a)(1) (emphasis the Court’s).”
18
GREENNationwide Roofing & Sheet Metal Co. v. United States, 14 Cl. Ct. 733 (Ct. Cl. 1988).
cites § 14.404-1 1×cited by 7 cases
Where it cites § 14.404-1
“This is not a case in which the Air Force awarded the contract to Nationwide while having knowledge of another lower responsive bid. Not to have terminated Nationwide’s contract would have resulted in a violation of the procurement regulations by allowing a contract to be…”
19
GREENPrineville Sawmill Co. v. United States, 14 Cl. Ct. 186 (Ct. Cl. 1988).
cites § 14.404-1 1×cited by 3 cases
Where it cites § 14.404-1
“” 48 C.F.R. § 14.404-1 (a)(1) (1986) (previously codified in the Federal Procurement Regulations at § 1-2.”
20
GREENWill H. Hall & Son, Inc. v. United States, 54 Fed. Cl. 436 (Fed. Cl. 2002).
cites § 14.404-1 1×cited by 1 case
Where it cites § 14.404-1
“The acceptance period for plaintiffs bid expired in sixty days, unless the contracting officer requested an extension pursuant to Federal Acquisition Regulation (FAR), 48 C.F.R. § 14.404-1 (d) (1995). In preparing its bid, plaintiff solicited and received quotes from…”

Show all 25 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
198520032021

One bar per year. Tallest: 3 cases in 1985. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Fed. Cl.11Ct. Cl.6Fed. Cir.5M.D. Ala.14th Cir.1D.D.C.1
By subsection
(e)(1)1 case
Overstreet Elec. Co. v. United States, 47 Fed. Cl. 728 (Fed. Cl. 2000).“48 C.F.R. 14.404-1(e)(1) and (f). 11 Plaintiff, however, argues that the Corps erred in rejecting its low bid as including an unreasonable price, alleging that determination was based on an inadequate estimate of the project that materially understated its costs.”

Show all 25 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.