48 C.F.R. § 16.202-1 (2026)
16.202-1 Description.
Edition and currency
Other sources
Courts have cited this section in 30 opinions since 1986, 3 of them in the last five years.
A firm-fixed-price contract provides for a price that is not subject to any adjustment on the basis of the contractor's cost experience in performing the contract. This contract type places upon the contractor maximum risk and full responsibility for all costs and resulting profit or loss. It provides maximum incentive for the contractor to control costs and perform effectively and imposes a minimum administrative burden upon the contracting parties. The contracting officer may use a firm-fixed-price contract in conjunction with an award-fee incentive (see 16.404) and performance or delivery incentives (see 16.402-2 and 16.402-3) when the award fee or incentive is based solely on factors other than cost. The contract type remains firm-fixed-price when used with these incentives.
- Where it cites § 16.202-1
- “” See 48 C.F.R. § 16.202-1 . Further, the contract incorporated several standard Federal Acquisition Regulation (“FAR”) provisions, such as a Changes clause, FAR 52.”
- The case’s holding
- A constructive acceleration claim requires a timely extension request that the government denies, and the government is not liable for the sovereign acts of a foreign nation.
- Later courts cite it for
- “constructive acceleration often occurs when the government demands compliance with an original contract deadline, despite excusable delay by the contractor.” · 3 citing courts
- Where it cites § 16.202-1
- “The government contended that this claim should be dismissed for failure to state a claim upon which relief can be granted because ACG entered into a firm-fixed-price contract for design/build services, and thus under 48 C.F.R. § 16.202-1 , plaintiff assumed the “maximum risk”…”
- Later courts cite it for
- “in making such a determination, if the court will have to review the same or related evidence to make its decision, then only one claim exists, but if the claim presented to the contracting officer requires examination of a different or unrelated set of operative facts, then the claims are separate.” · 3 citing courts
- Where it cites § 16.202-1
- “48 C.F.R. § 16.202-1 (1995). 5 According to the Federal Acquisition Regulations (“FAR”), fixed-price contracts are “suitable for acquiring commercial items .”
- The case’s holding
- A contractor is barred from seeking an equitable adjustment for a patent ambiguity if it fails to seek clarification before submitting its proposal.
- Later courts cite it for
- “because fixed-price contracts do not contain a method for varying the price of the contract in the event of unforeseen circumstances, they assign the risk to the contractor that the actual cost of performance will be higher than the price of the contract.” · 4 citing courts
- Where it cites § 16.202-1
- “See 48 C.F.R. § 16.202-1 (“A firm-fixed-priee contract provides for a price that is not subject to any adjustment on the basis of the contractor’s cost experience in performing the contract.”
- The case’s holding
- The original Cost Accounting Standard 413.50(c)(12) permits only cost adjustments and does not allow the government to recover pension surpluses from firm-fixed-price contracts.
- Later courts cite it for
- “teledyne retained responsibility for the pensions, but not the contracts over which the gains and losses attributable to the government's share of pension costs would ordinarily be amortized.” · 3 citing courts
- Where it cites § 16.202-1
- “See 48 C.F.R. §§ 16.202-1 , 16.301-1. Accordingly, while a contractor’s ability to control costs is critically important to the government in a cost-reimbursement contract, it is of little moment in a firm, fixed-price contract.”
- The case’s holding
- An agency must perform a meaningful tradeoff analysis by determining whether the relative strengths and weaknesses of competing proposals justify paying a higher price.
- Later courts cite it for
- “to be sure, as noted at the outset, plaintiffs have a significant burden of showing error in that regard because a court must accord considerable deference to an agency's best-value decision in trading off price with other factors.” · 20 citing courts
- Where it cites § 16.202-1
- “”); see also 48 C.F.R. § 16.202-1 ("A firm fixed-price contract provides for a price that is not subject to any adjustment on the basis of the contractor's cost experience in performing the contract.”
- The case’s holding
- Invalidation of a contract is not a necessary consequence of a statutory violation and must be considered in light of the statutory purpose and the policy of supporting contract integrity.
- Later courts cite it for
- “invalidation of the contract is not a necessary consequence when a statute or regulation has been contravened, but must be considered in light of the statutory or regulatory purpose, with recognition of the strong policy of supporting the integrity of contracts made by and with the united states.” · 6 citing courts
- Where it cites § 16.202-1
- “” 48 C.F.R. § 16.202-1 . Once the final price is agreed upon, Wolf Creek can begin No.”
- Later courts cite it for
- “that a false statement was made with the requisite scienter, materiality, and causation.” · 1 citing court
- Where it cites § 16.202-1
- “The FAR addresses “Firm-Fixed-Price Contracts” at 48 C.F.R. § 16.202-1 , and provides: A firm-fixed-price contract provides for a price that is not subject to any adjustment on the basis of the contractor’s cost experience in performing the contract.”
- Where it cites § 16.202-1
- “” 48 C.F.R. § 16.202-1 . “This contract type places upon the contractor .”
- Where it cites § 16.202-1
- “See 48 C.F.R. § 16.202-1 . On this contract, however, Matte-son claims the government invited contractors to “come up with other options” to the pre-selected disposal areas, which “change[d] the contractual relationship.”
- Later courts cite it for
- “is settled law that where an agreement contains general and specific provisions that conflict, 'the provision directed to a particular matter controls over the provision which is general in its terms.” · 2 citing courts
- Where it cites § 16.202-1
- “” J.A. 320, 292. Indeed, the solicitation clearly states that each task order issued for the performance of work is a “Firm Fixed-Price” contract.”
- The case’s holding
- In a firm fixed-price contract, the contractor assumes the risk of unexpected costs including pricing inaccuracies and inflation.
- Later courts cite it for
- “the essence of a firm fixed-price contract is that the contractor, not the government, assumes the risk of unexpected costs.” · 9 citing courts
- Where it cites § 16.202-1
- “at 27 (citing 48 C.F.R. § 16.202-1 (2006)). Moreover, Airtronic contends that, even if it could request a reformation, an exercise of that right would provide no relief to PHT.”
- The case’s holding
- A procurement award need not discuss unstated factors: agencies must award based solely on solicitation factors but may weigh past performance by currency, relevance, source, context, and trends.
- Later courts cite it for
- “this federal statute provides that, in negotiated procurements, agencies 'shall evaluate ... competitive proposals and make an award based solely on the factors specified in the solicitation.” · 2 citing courts
- Where it cites § 16.202-1
- “at 26 (quot- ing 48 C.F.R. § 16.202-1 ; then citing ITT Fed.”
- Later courts cite it for
- “is not available for an 'errant bid' caused by a bidder's 'gross negligence in failing to read and consider the specifications thoroughly.” · 1 citing court
- Where it cites § 16.202-1
- “” 48 C.F.R. § 16.202-1 (2008). Firm-fixed-priee contracts assign the “risk to the contractor that the actual cost of performance will be higher than the price of the contract.”
- Where it cites § 16.202-1
- “48 C.F.R. § 16.202-1 (2004). . Before awarding a contract, the contracting officer must make an affirmative determination that the winning offeror is responsible, 48 C.”
- Later courts cite it for
- “an agency has virtually a carte blanche right to decide the amount of funding it will spend on a given project.” · 2 citing courts
- Where it cites § 16.202-1
- “” 48 C.F.R. § 16.202-1 (2006). This type of contract "is suitable for acquiring commercial items .”
- Later courts cite it for
- “present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.” · 1 citing court
- Where it cites § 16.202-1
- “” 48 C.F.R. § 16.202-1 (2008). It is "suitable for acquiring commercial items .”
- Where it cites § 16.202-1
- “48 C.F.R. § 16.202-1 (1997). Given the nature of the contract, plaintiff assuredly would have been responsible for those costs exceeding its expectations or calculations.”
- Where it cites § 16.202-1
- “” 48 C.F.R. § 16.202-1 . This type of task order places upon the contractor maximum risk and full responsibility for all costs and resulting profit or loses.”
- Where it cites § 16.202-1
- “See FAR 16.202-1, 48 C.F.R. § 16.202-1 . Athough ITT argues that after fifteen years it and its employees expected the contract to continue, the fact that the contract expired was not an abnormal event.”
- Later courts cite it for
- “assumes maximum risk and full responsibility for all such costs that may be incurred"); see also 48 c.f.r. 16.202-1 (placing upon the contractor” · 1 citing court
Show all 30 citing cases (list view) →
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per year. Tallest: 3 cases in 2010. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.