48 C.F.R. § 36.203 (2026)

36.203 Government estimate of construction costs.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1997 1citing case
At a glance

Courts have cited this section in 1 opinion since 1997.

(a) An independent Government estimate of construction costs shall be prepared and furnished to the contracting officer at the earliest practicable time for each proposed contract and for each contract modification anticipated to exceed the simplified acquisition threshold. The contracting officer may require an estimate when the cost of required work is not anticipated to exceed the simplified acquisition threshold. The estimate shall be prepared in as much detail as though the Government were competing for award.

(b) When two-step sealed bidding is used, the independent Government estimate shall be prepared when the contract requirements are definitized.

(c) Access to information concerning the Government estimate shall be limited to Government personnel whose official duties require knowledge of the estimate. An exception to this rule may be made during contract negotiations to allow the contracting officer to identify a specialized task and disclose the associated cost breakdown figures in the Government estimate, but only to the extent deemed necessary to arrive at a fair and reasonable price. The overall amount of the Government's estimate shall not be disclosed except as permitted by agency regulations.

[48 FR 42356, Sept. 19, 1983, as amended at 50 FR 1744, Jan. 11, 1985; 50 FR 52429, Dec. 23, 1985; 62 FR 44829, Aug. 22, 1997; 71 FR 57368, Sept. 28, 2006]
The 1 case that cites 48 C.F.R. § 36.203 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENDelbert Wheeler Constr., Inc. v. United States, 39 Fed. Cl. 239 (Fed. Cl. 1997).
cites § 36.203 2×cited by 35 cases
Where it cites § 36.203
“See 48 C.F.R. § 36.203 (1996). The cost estimate is used to compare the offeror’s cost estimate to the government’s estimate in determining which proposal provides the best value to the government.”
The case’s holding
A true competitor during evaluation remains an interested party with standing even if statutory price limits later bar award, and agency evaluations are upheld absent arbitrary or capricious conduct.
Later courts cite it for
“a likelihood of success on the merits” · 2 citing courts

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.