C.F.R. homeSearch C.F.R.
C.F.R.Title 48Chapter 1—Federal Acquisition RegulationSubchapter G—Contract ManagementPart 49—Termination of ContractsSubpart 49.1—General Principles

48 C.F.R. § 49.112-2 (2026)

49.112-2 Final payment.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1996–2008 4citing cases
At a glance

Courts have cited this section in 4 opinions since 1996.

(a) Negotiated settlement. After execution of a settlement agreement, the contractor shall submit a voucher or invoice showing the amount agreed upon, less any portion previously paid. The TCO shall attach a copy of the settlement agreement to the voucher or invoice and forward the documents to the disbursing officer for payment.

(b) Settlement by determination. If the settlement is by determination and—

(1) There is no appeal within the allowed time, the contractor shall submit a voucher or invoice showing the amount determined due, less any portion previously paid; or

(2) There is an appeal, the contractor shall submit a voucher or invoice showing the amount finally determined due on the appeal, less any portion previously paid. Pending determination of any appeal, the contractor may submit vouchers or invoices for charges that are not directly involved with the portion being appealed, without prejudice to the rights of either party on the appeal.

(c) Construction contracts. In the case of construction contracts, before forwarding the final payment voucher, the contracting officer shall ascertain whether there are any outstanding labor violations. If so, the contracting officer shall determine the amount to be withheld from the final payment (see subpart 22.4).

(d) Interest. The Government shall not pay interest on the amount due under a settlement agreement or a settlement by determination. The Government may, however, pay interest on a successful contractor appeal from a contracting officer's determination under the Disputes clause at 52.233-1.

The 4 cases that cite 48 C.F.R. § 49.112-2 most heavily, weighted by court and treatment. RelevanceNewestTreatment
cites § 49.112-2 2×cited by 39 cases
Where it cites § 49.112-2
“” 48 C.F.R. § 49.112-2 (d). MK argues the retrial of this lawsuit constitutes a “settlement by determination” and therefore precludes the assessment of prejudgment interest.”
The case’s holding
A district court possesses discretion in awarding prejudgment interest, though such awards must comply with stipulations regarding the accrual of damages.
Later courts cite it for
“an award of prejudgment interest is within the district court's discretion.” · 4 citing courts
2
GREENJames M. Ellett Constr. Co. v. United States, 93 F.3d 1537 (Fed. Cir. 1996).
cites § 49.112-2 1×cited by 235 cases
Where it cites § 49.112-2
“48 C.F.R. § 49.112-2 (a)-(b) (1995). Relying on a dictionary, the government argues that a termination settlement proposal is a routine request for payment because the FAR and the contract establish procedures for submitting one.”
The case’s holding
Jurisdiction under the Contract Disputes Act requires both a valid claim and a contracting officer's final decision on that claim.
Later courts cite it for
“there are three requirements a nonroutine submission must meet to be a 'claim.' it must be: (1) a written demand or assertion, (2) seeking as a matter of right, (3) the payment of money in a sum certain.” · 8 citing courts
3
GREENMedina Constr., Ltd. v. United States, 43 Fed. Cl. 537 (Fed. Cl. 1999).
cites § 49.112-2 1×cited by 40 cases
Where it cites § 49.112-2
“§ 611 (allowing interest to contractors commencing from date claim is submitted); see 48 C.F.R. § 49.112-2 (d) (precluding government from paying interest upon amount due pursuant to a settlement but permitting interest from date claim is submitted).”
The case’s holding
A certified termination settlement proposal may ripen into a Contract Disputes Act claim without negotiations where fraud allegations make settlement futile and a final decision is requested.
Later courts cite it for
“the documents before the court do not demonstrate a meeting of the minds of the parties which is inferred from the parties' conduct such that a tacit understanding and agreement was reached as would demonstrate an implied-in-fact contract.” · 2 citing courts
4
GREENRex Sys., Inc. v. William S. Cohen, 224 F.3d 1367 (Fed. Cir. 2000).
cites § 49.112-2 1×cited by 34 cases
Where it cites § 49.112-2
“See 48 C.F.R. § 49.112-2 (d) (1995). Here, RSI asks the court to hold that it is entitled to interest on its negotiated termination settlement amount because, RSI asserts, the negotiations over the amount had broken down, or reached an “impasse,” thus converting its termination…”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199620022008

One bar per year. Tallest: 1 case in 1996. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Fed. Cir.210th Cir.1Fed. Cl.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com