Skip to main content
C.F.R.Title 48Chapter 1—Federal Acquisition RegulationSubchapter G—Contract ManagementPart 49—Termination of ContractsSubpart 49.2—Additional Principles for Fixed-Price Contracts Terminated for Convenience

48 C.F.R. § 49.201 (2026)

49.201 General.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1994–2011 8citing cases
At a glance

Courts have cited this section in 8 opinions since 1994.

(a) A settlement should compensate the contractor fairly for the work done and the preparations made for the terminated portions of the contract, including a reasonable allowance for profit. Fair compensation is a matter of judgment and cannot be measured exactly. In a given case, various methods may be equally appropriate for arriving at fair compensation. The use of business judgment, as distinguished from strict accounting principles, is the heart of a settlement.

(b) The primary objective is to negotiate a settlement by agreement. The parties may agree upon a total amount to be paid the contractor without agreeing on or segregating the particular elements of costs or profit comprising this amount.

(c) Cost and accounting data may provide guides, but are not rigid measures, for ascertaining fair compensation. In appropriate cases, costs may be estimated, differences compromised, and doubtful questions settled by agreement. Other types of data, criteria, or standards may furnish equally reliable guides to fair compensation. The amount of recordkeeping, reporting, and accounting related to the settlement of terminated contracts should be kept to a minimum compatible with the reasonable protection of the public interest.

The 8 cases that cite 48 C.F.R. § 49.201 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENNicon, Inc. v. United States, 331 F.3d 878 (Fed. Cir. 2003).
cites § 49.201 4×cited by 43 cases
The case’s holding
A contractor may recover unabsorbed overhead in a termination for convenience settlement if a reasonable allocation method is available and all necessary prerequisites are met.
Later courts cite it for
“the overall purpose of a termination for convenience settlement is to fairly compensate the contractor and to make the contractor whole for the costs incurred in connection with the terminated work.” · 5 citing courts
2
GREENMorrison Knudsen Corp. v. Fireman's Fund Ins., 175 F.3d 1221 (10th Cir. 1999).
cites § 49.201 2×cited by 104 cases
Where it cites § 49.201
“See 48 C.F.R. §§ 49.201 & .303 — 5(d) 40 ; see also id.”
The case’s holding
An appellant's failure to provide a necessary transcript to demonstrate prejudice from an instructional error requires affirmance of the judgment below.
Later courts cite it for
“our concern is to ensure that our review does not leave us with substantial doubt whether the instructions, considered as a whole, properly guided the jury in its deliberations.” · 7 citing courts
3
GREENCentury Marine Inc. v. United States, 153 F.3d 225 (5th Cir. 1998).
cites § 49.201 2×cited by 62 cases
Where it cites § 49.201
“In contrast, under a fixed-price contract terminated for the convenience of the Government, a settlement should compensate the contractor fairly for the work actually done and for the preparations made for the terminated portions of the contract, including a reasonable allowance…”
The case’s holding
A contractor terminated for default cannot recover the difference between the unpaid contract balance and the cost of completing the unfinished work.
Later courts cite it for
“a clear understanding of the basis for the decision.” · 4 citing courts
4
GREENInt'l Data Prods. Corp. v. United States, 492 F.3d 1317 (Fed. Cir. 2007).
cites § 49.201 1×cited by 92 cases
Where it cites § 49.201
“48 C.F.R. §§ 49.201 et seq.; 48 C.F.R. §§ 49.301 et seq.”
The case’s holding
A termination for convenience does not extinguish a contractor's obligation to provide warranties or software upgrades specified in the contract.
Later courts cite it for
“a constructive change occurs where a contractor performs work beyond the contract requirements without a formal order, either by an informal order or due to the fault of the government.” · 13 citing courts
5
GREENEngineered Maint. Servs., Inc. v. United States, 55 Fed. Cl. 637 (Fed. Cl. 2003).
cites § 49.201 1×cited by 5 cases
Later courts cite it for
“mere notice or knowledge that the contractor encountered a 'condition' falls short of the contractual requirement that the contractor notify the government that it considered the condition to constitute a 'differing site condition.” · 2 citing courts
6
GREENRed River Holdings, LLC v. United States, 802 F. Supp. 2d 648 (D. Md. 2011).
cites § 49.201 1×cited by 5 cases
Summary
No passage or summary on file for this case yet.
7
GREENUnited States v. Frequency Elec., 862 F. Supp. 834 (E.D.N.Y. 1994).
cites § 49.201 1×cited by 8 cases
Where it cites § 49.201
“See 48 C.F.R. § 49.201 (c). 1 With respect to the FOX contracts, the government knew that FEI did not keep accurate records of time spent on each project and thus had to estimate and often transfer costs from one project to another when asked to account for outlays pursuant to a…”
8
NO FLAGCentury Marine Inc v. United States, No. 03-20991 (5th Cir. Aug. 27, 1998).
cites § 49.201 1×
Where it cites § 49.201
“48 C.F.R. §§ 49.201 , 49.202. Anticipatory profits and consequential damages shall not be allowed under either a termination for convenience or a termination for default of a fixed-price contract.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199420022011

One bar per year. Tallest: 2 cases in 1998. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
5th Cir.2Fed. Cir.210th Cir.1D. Md.1E.D.N.Y1Fed. Cl.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.