48 C.F.R. § 49.401 (2026)
49.401 General.
Edition and currency
Other sources
Courts have cited this section in 8 opinions since 1986.
(a) Termination for default is generally the exercise of the Government's contractual right to completely or partially terminate a contract because of the contractor's actual or anticipated failure to perform its contractual obligations.
(b) If the contractor can establish, or it is otherwise determined that the contractor was not in default or that the failure to perform is excusable; i.e., arose out of causes beyond the control and without the fault or negligence of the contractor, the default clauses prescribed in 49.503 and located at 52.249 provide that a termination for default will be considered to have been a termination for the convenience of the Government, and the rights and obligations of the parties governed accordingly.
(c) The Government may, in appropriate cases, exercise termination or cancellation rights in addition to those in the contract clauses (see for example, paragraph (h) of the Default clause at 52.249-8).
(d) For default terminations of orders under Federal Supply Schedule contracts, see subpart 8.4.
(e) Notwithstanding the provisions of this 49.401, the contracting officer may, with the written consent of the contractor, reinstate the terminated contract by amending the notice of termination, after a written determination is made that the supplies or services are still required and reinstatement is advantageous to the Government.
- Where it cites § 49.401
- “48 C.F.R. § 49.401 (b) (1998). Linan-Faye suggests, therefore, that because no such regulations exist in grant situations 10 such as this, there is an expressed intent that such a conversion not be allowed.”
- The case’s holding
- State law governs contract disputes between private contractors and public housing authorities rather than federal common law.
- Later courts cite it for
- “the high-water mark of courts' permissiveness in allowing the government to terminate for convenience.” · 2 citing courts
- Where it cites § 49.401
- “48 C.F.R. § 49.401 (a). The Government has the right to terminate a fixed-price contract for default if the contractor fails to deliver the supplies or to perform the services within the time specified in the contract.”
- The case’s holding
- A contractor terminated for default cannot recover the difference between the unpaid contract balance and the cost of completing the unfinished work.
- Later courts cite it for
- “a clear understanding of the basis for the decision.” · 4 citing courts
- Where it cites § 49.401
- “Pursuant to the Federal Acquisition Regulation (FAR), 48 C.F.R. § 49.401 (e) (1990), the DPSC agreed to consider such a reinstatement after Sac & Fox submitted a viable and satisfactory business plan.”
- Later courts cite it for
- “the price a willing lessee would pay to a willing lessor, for the period of the temporary taking.” · 4 citing courts
- Summary
- No passage or summary on file for this case yet.
- Where it cites § 49.401
- “48 C.F.R. § 49.401 (e) (1997). It requires amendment of the notice of termination and a written determination that the supplies are still required and that reinstatement is advantageous to the government.”
- Where it cites § 49.401
- “48 C.F.R. §§ 49.401 (a)-(b). . FAR 14.407-3(a) provides: If a bidder requests permission to correct a mistake and clear and convincing evidence establishes both the existence of the mistake and the bid actually intended, the agency head may make a determination permitting the…”
- Where it cites § 49.401
- “48 C.F.R. § 49.401 (a). The Government has the right to terminate a fixed-price contract for default if the contractor fails to deliver the supplies or to perform the services within the time specified in the contract.”
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per year. Tallest: 3 cases in 1998. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.