48 C.F.R. § 52.211-12
52.211-12 Liquidated Damages—Construction.
As prescribed in 11.503(b), insert the following clause in solicitations and contracts:
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of __ [Contracting Officer insert amount] for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
Notes of Decisions
Cited in 5
cases (1 in the last 5 years), 2008–2021 · leading case: M. Maropakis Carpentry, Inc. v. United States
M. Maropakis Carpentry, Inc. v. United States (2010)
“The contract also included a liquidated damages clause, in the form of 48 C.F.R. § 52.211-12 , which provided that Maropakis would be liable to the government for $650 per day for each day of delay beyond the contract completion date.”
Mw Builders, Inc. v. United States (2017)
“§§ 3729-3733 ; Federal Acquisition Regulation, 48 C.F.R. §§ 52.211-12 (Liquidated Damages), 52.”
Rda Construction Corp. v. United States (2017)
“DX 1 at 17, 586 (incorporating 48 C.F.R. § 52.211-12 ), Although FAR 52.”
M. Maropakis Carpentry, Inc. v. United States (2008)
“67; 48 C.F.R. § 52.211-12 (Liquidated Damages—Construction).”
Sauer Incorporated (2021)
“” 48 C.F.R. § 52.211-12 (emphasis supplied).”
Annotations are extracted automatically from the opinions in the
Syfert caselaw corpus and ranked by authority, recency, and
treatment. Dots show Syfertize treatment of the citing case itself.