C.F.R. homeSearch C.F.R.
C.F.R.Title 48Chapter 1—Federal Acquisition RegulationSubchapter H—Clauses and FormsPart 52—Solicitation Provisions and Contract ClausesSubpart 52.2—Text of Provisions and Clauses

48 C.F.R. § 52.236-11 (2026)

52.236-11 Use and Possession Prior to Completion.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 ACTIVE · 1 IN 5Y cited 1997–2023 3citing cases
At a glance

Courts have cited this section in 3 opinions since 1997, 1 of them in the last five years. The most litigated part is subsection (a) (1 case).

As prescribed in 36.511, insert the following clause:

Use and Possession Prior to Completion (APR 1984)

(a) The Government shall have the right to take possession of or use any completed or partially completed part of the work. Before taking possession of or using any work, the Contracting Officer shall furnish the Contractor a list of items of work remaining to be performed or corrected on those portions of the work that the Government intends to take possession of or use. However, failure of the Contracting Officer to list any item of work shall not relieve the Contractor of responsibility for complying with the terms of the contract. The Government's possession or use shall not be deemed an acceptance of any work under the contract.

(b) While the Government has such possession or use, the Contractor shall be relieved of the responsibility for the loss of or damage to the work resulting from the Government's possession or use, notwithstanding the terms of the clause in this contract entitled Permits and Responsibilities. If prior possession or use by the Government delays the progress of the work or causes additional expense to the Contractor, an equitable adjustment shall be made in the contract price or the time of completion, and the contract shall be modified in writing accordingly.

(End of clause) [48 FR 42478, Sept. 19, 1983, as amended at 60 FR 34761, July 3, 1995]
The 3 cases that cite 48 C.F.R. § 52.236-11 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENMeridian Eng'g Co. v. United States, 122 Fed. Cl. 381 (Fed. Cl. 2015).
cites § 52.236-11 2×subsections: (a)cited by 7 cases
Where it cites § 52.236-11
“” 48 C.F.R. § 52.236-11 (a). Although no clear legal test addresses whether a nominally “excessive” Punchlist constitutes a breach of contract in this case, the court will attempt to evaluate the alleged number, timing, and nature of the contested Punchlist items under the…”
The case’s holding
Water flowing in natural washes throughout a construction site is a foreseeable condition that may not constitute a compensable differing site condition.
Later courts cite it for
“water in varying quantities may be flowing in natural washes throughout the length of the project,” · 1 citing court
2
GREENBlinderman Constr. Co. v. United States, 39 Fed. Cl. 529 (Fed. Cl. 1997).
cites § 52.236-11 1×cited by 23 cases
Where it cites § 52.236-11
“See 48 C.F.R. § 52.236-11 (1989), Use and Possession Prior to Completion, which provides, inter alia: "The Government’s possession or use [of the property that is the subject matter of the contract] shall not be deemed an acceptance of any work under the contract.”
Later courts cite it for
“the only way to accurately assess the effect of the delays alleged ... on the ... project's progress is to contrast updated cpm schedules prepared immediately before and immediately after each purported delay.” · 2 citing courts
3
NO FLAGBetance Enter., Inc., ASBCA No. 63076, 63077, 63078, 63079 (A.S.B.C.A. Jan. 25, 2023).
cites § 52.236-11 1×cited by 0 cases
Where it cites § 52.236-11
“48 C.F.R. § 52.236-11 . 8. In July 2017, the government issued Solicitation No.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199720102023

One bar per year. Tallest: 1 case in 1997. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Fed. Cl.2A.S.B.C.A.1
By subsection
(a)1 case
Meridian Eng'g Co. v. United States, 122 Fed. Cl. 381 (Fed. Cl. 2015).“” 48 C.F.R. § 52.236-11 (a). Although no clear legal test addresses whether a nominally “excessive” Punchlist constitutes a breach of contract in this case, the court will attempt to evaluate the alleged number, timing, and nature of the contested Punchlist items under the…”
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com