C.F.R. homeSearch C.F.R.
C.F.R.Title 48Chapter 1—Federal Acquisition RegulationSubchapter H—Clauses and FormsPart 52—Solicitation Provisions and Contract ClausesSubpart 52.2—Text of Provisions and Clauses

48 C.F.R. § 52.236-13 (2026)

52.236-13 Accident Prevention.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1992–2021 13citing cases
At a glance

Courts have cited this section in 13 opinions since 1992, 1 of them in the last five years. The most litigated part is subsection (b) (1 case).

As prescribed in 36.513, insert the following clause:

Accident Prevention (NOV 1991)

(a) The Contractor shall provide and maintain work environments and procedures which will (1) safeguard the public and Government personnel, property, materials, supplies, and equipment exposed to Contractor operations and activities; (2) avoid interruptions of Government operations and delays in project completion dates; and (3) control costs in the performance of this contract.

(b) For these purposes on contracts for construction or dismantling, demolition, or removal of improvements, the Contractor shall—

(1) Provide appropriate safety barricades, signs, and signal lights;

(2) Comply with the standards issued by the Secretary of Labor at 29 CFR part 1926 and 29 CFR part 1910; and

(3) Ensure that any additional measures the Contracting Officer determines to be reasonably necessary for the purposes are taken.

(c) If this contract is for construction or dismantling, demolition or removal of improvements with any Department of Defense agency or component, the Contractor shall comply with all pertinent provisions of the latest version of U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, in effect on the date of the solicitation.

(d) Whenever the Contracting Officer becomes aware of any noncompliance with these requirements or any condition which poses a serious or imminent danger to the health or safety of the public or Government personnel, the Contracting Officer shall notify the Contractor orally, with written confirmation, and request immediate initiation of corrective action. This notice, when delivered to the Contractor or the Contractor's representative at the work site, shall be deemed sufficient notice of the noncompliance and that corrective action is required. After receiving the notice, the Contractor shall immediately take corrective action. If the Contractor fails or refuses to promptly take corrective action, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. The Contractor shall not be entitled to any equitable adjustment of the contract price or extension of the performance schedule on any stop work order issued under this clause.

(e) The Contractor shall insert this clause, including this paragraph (e), with appropriate changes in the designation of the parties, in subcontracts.

(End of clause)

Alternate I (NOV 1991). If the contract will involve (a) work of a long duration or hazardous nature, or (b) performance on a Government facility that on the advice of technical representatives involves hazardous materials or operations that might endanger the safety of the public and/or Government personnel or property, add the following paragraph (f) to the basic clause:

(f) Before commencing the work, the Contractor shall—

(1) Submit a written proposed plan for implementing this clause. The plan shall include an analysis of the significant hazards to life, limb, and property inherent in contract work performance and a plan for controlling these hazards; and

(2) Meet with representatives of the Contracting Officer to discuss and develop a mutual understanding relative to administration of the overall safety program.

[56 FR 55376, Oct. 25, 1991]
The 13 cases that cite 48 C.F.R. § 52.236-13 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENSlavoljub Damnjanovic v. United States, 9 F.3d 1270 (7th Cir. 1993).
cites § 52.236-13 2×cited by 22 cases
Where it cites § 52.236-13
“One of these regulations, 48 C.F.R. § 52.236-13 , deals specifically with accident prevention.”
Later courts cite it for
“depends upon the surrounding circumstances and the role the party assumed on the work-site.” · 2 citing courts
2
GREENHills Materials Co. v. Donald B. Rice, 982 F.2d 514 (Fed. Cir. 1992).
cites § 52.236-13 1×cited by 100 cases
The case’s holding
Specific contract terms relating to a particular matter control over general language when the two are in conflict.
Later courts cite it for
“where specific and general terms in a contract are in conflict, those which relate to a particular matter control over the more general language.” · 8 citing courts
3
GREENFraser v. United States, 490 F. Supp. 2d 302 (E.D.N.Y. 2007).
cites § 52.236-13 2×cited by 8 cases
Where it cites § 52.236-13
“With regards to the safety of the Premises, the Contract incorporated 48 C.F.R. 52.236-13, which requires the contractor to “provide and maintain work environments and procedures which will .”
Later courts cite it for
“courts look to the terms of the contract to determine whether the government controlled the detailed physical performance of the contractor or whether the government supervised the day-to-day operations of the contractor.” · 2 citing courts
4
GREENRda Constr. Corp. v. United States, 132 Fed. Cl. 732 (Fed. Cl. 2017).
cites § 52.236-13 1×cited by 10 cases
Later courts cite it for
“gave in to pressure from other government officials to abdicate his responsibility to be impartial and agreed to support contract interpretations made by officials, who were openly contemptuous of the contractor.” · 2 citing courts
5
GREENSteven Paul Phillips v. United States, 956 F.2d 1071 (11th Cir. 1992).
cites § 52.236-13 1×cited by 36 cases
Where it cites § 52.236-13
“See Federal Acquisitions Regulations System, Solicitation Provisions and Contract Clauses, 48 C.F.R. § 52.236-13 (1991). The court found that the Army Corps was required to insure that the means of anchorage of suspended scaffolds was inspected; furthermore, the judge found that…”
The case’s holding
The discretionary function exception does not shield the government from liability for the negligent discharge of mandatory responsibilities imposed by its own regulations.
Later courts cite it for
“perform 'field safety inspections every time they visit a construction site.” · 1 citing court
6
GREENDoud v. United States, 797 F. Supp. 138 (N.D.N.Y. 1992).
cites § 52.236-13 3×cited by 5 cases
Where it cites § 52.236-13
“As to plaintiff’s claim that the United States violated its non-delegable duty to provide plaintiff with a safe working environment under New York Labor Law sections 240 and 241(6), the court holds that these statutes are pre-empted by 48 C.F.R. § 52.236-13 to the extent that…”
7
GREENRyan v. United States, 233 F. Supp. 2d 668 (D.N.J. 2002).
cites § 52.236-13 1×cited by 4 cases
Where it cites § 52.236-13
“236-13 10 and 48 C.F.R. § 52.236-13 11 and several courts have found that it validly delegates safety inspections to the contractor, and leaves further government inspections to the discretion of the.”
8
GREENKandarge v. United States Dept. of Navy, 849 F. Supp. 304 (D.N.J. 1994).
cites § 52.236-13 1×cited by 4 cases
Where it cites § 52.236-13
“-12); and (3) an accident prevention clause ( 48 C.F.R. § 52.236-13 ). The accident prevention clause, referred to in § 52.”
9
GREENHVAC Constr. Co. v. United States, 28 Fed. Cl. 690 (Fed. Cl. 1993).
cites § 52.236-13 1×cited by 4 cases
Where it cites § 52.236-13
“236-7 (1989); 48 C.F.R. § 52.236-13 (1989). 6 The court finds that removal of the barrier was a reasonable precaution taken pursuant to the fire regulations governing the project.”
10
GREENMcDaniel v. United States, 53 F. App'x 8 (10th Cir. 2002).
cites § 52.236-13 1×cited by 2 casesunpublished
Where it cites § 52.236-13
“at 240; see 48 C.F.R. § 52.236-13 . However, [t]he fact that the contract may have reserved to the United States the right to inspect the work and facilities of the independent contractor, and the right to stop the work, does not in itself override or alter the general rule of…”
11
GREENSchmoldt v. WADCO Indus., Inc., 941 F. Supp. 905 (D. Ariz. 1996).
cites § 52.236-13 2×cited by 1 case
Where it cites § 52.236-13
“48 C.F.R. § 52.236-13 . In support of its assertion that any decision regarding the safety of the channel form is discretionary, the United States relies heavily upon Clark v.”
12
GREENHencely v. Fluor Corp., 554 F. Supp. 3d 770 (D.S.C. 2021).
cites § 52.236-13 2×cited by 0 casesunknown
Where it cites § 52.236-13
“113 at 12 (quoting 48 C.F.R. § 52.236-13 ).) Plaintiff reasons that, based on this clause, “it would absolutely be reasonable for Plaintiff to rely on that promise as manifesting Fluor and the government’s intent to confer a right on him.”
13
NO FLAGIron Hawk v. United States, No. 5:19-cv-05080 (D.S.D. Aug. 24, 2020).
cites § 52.236-13 2×subsections: (b)cited by 0 casesunknown
Where it cites § 52.236-13
“Similarly, 48 C.F.R. 52.236-13 is not relevant to this case.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199220062021

One bar per year. Tallest: 3 cases in 1992. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
D.N.J.2Fed. Cl.2D. Ariz.110th Cir.111th Cir.17th Cir.1Fed. Cir.1E.D.N.Y1

The 8 courts with the most citing cases, of 11 courts in all.

By subsection
(b)1 case
Iron Hawk v. United States, No. 5:19-cv-05080 (D.S.D. Aug. 24, 2020).“Similarly, 48 C.F.R. 52.236-13 is not relevant to this case.”
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com