C.F.R. homeSearch C.F.R.
C.F.R.Title 48Chapter 1—Federal Acquisition RegulationSubchapter H—Clauses and FormsPart 52—Solicitation Provisions and Contract ClausesSubpart 52.2—Text of Provisions and Clauses

48 C.F.R. § 52.236-2 (2026)

52.236-2 Differing Site Conditions.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1988–2024 38citing cases
At a glance

Courts have cited this section in 38 opinions since 1988, 3 of them in the last five years. The most litigated part is subsection (a) (1 case).

As prescribed in 36.502, insert the following clause:

Differing Site Conditions (APR 1984)

(a) The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the Contracting Officer of (1) subsurface or latent physical conditions at the site which differ materially from those indicated in this contract, or (2) unknown physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract.

(b) The Contracting Officer shall investigate the site conditions promptly after receiving the notice. If the conditions do materially so differ and cause an increase or decrease in the Contractor's cost of, or the time required for, performing any part of the work under this contract, whether or not changed as a result of the conditions, an equitable adjustment shall be made under this clause and the contract modified in writing accordingly.

(c) No request by the Contractor for an equitable adjustment to the contract under this clause shall be allowed, unless the Contractor has given the written notice required; provided, that the time prescribed in (a) above for giving written notice may be extended by the Contracting Officer.

(d) No request by the Contractor for an equitable adjustment to the contract for differing site conditions shall be allowed if made after final payment under this contract.

(End of clause) [48 FR 42478, Sept. 19, 1983, as amended at 60 FR 34761, July 3, 1995]
The 20 cases that cite 48 C.F.R. § 52.236-2 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENGeorge Sollitt Constr. Co. v. United States, 64 Fed. Cl. 229 (Fed. Cl. 2005).
cites § 52.236-2 5×cited by 47 cases
Where it cites § 52.236-2
“See 48 C.F.R. § 52.236-2 (a), (c) (1994) (“No request by the Contractor for an equitable adjustment to the contract under this clause shall be allowed, unless the Contractor has given the written notice required [before the conditions are disturbed] ----”).”
The case’s holding
Disputed contract payment amounts are subject to Contract Disputes Act interest rather than Prompt Payment Act interest.
Later courts cite it for
“extended field office overhead also may sometimes be recovered as delay damages.” · 4 citing courts
2
GREENRanda/madison Jt. Venture III v. Gregory Robert Dahlberg, 239 F.3d 1264 (Fed. Cir. 2001).
cites § 52.236-2 3×cited by 37 cases
Where it cites § 52.236-2
“48 C.F.R. § 52.236-2 (a) (2000) (FAR 52.236-2(a)).”
The case’s holding
A contractor is charged with notice of information explicitly made available for inspection and must prove by a preponderance of the evidence that actual conditions differ materially from those indicated.
Later courts cite it for
“this court has previously explained that 'in order to establish entitlement to an equitable adjustment by reason of a type i differing site condition, ... the contractor must prove, by a preponderance of the evidence, that the conditions indicated in the contract differ materially from those it encounters during performance.” · 5 citing courts
3
GREENRda Constr. Corp. v. United States, 132 Fed. Cl. 732 (Fed. Cl. 2017).
cites § 52.236-2 3×subsections: (a)cited by 10 cases
Where it cites § 52.236-2
“48 C.F.R. § 52.236-2 (a)-(b). 11 . Modifications 1-3 made administrative changes to the October 13, 2009 Contract.”
Later courts cite it for
“gave in to pressure from other government officials to abdicate his responsibility to be impartial and agreed to support contract interpretations made by officials, who were openly contemptuous of the contractor.” · 2 citing courts
4
GREENL.W. Matteson, Inc. v. United States, 61 Fed. Cl. 296 (Fed. Cl. 2004).
cites § 52.236-2 4×cited by 13 cases
Where it cites § 52.236-2
“In this case, the only provision in the contract dealing with differing site conditions is Paragraph 60, Section 00700, which incorporates 48 C.F.R. § 52.236-2 . In Olympus Corp. v.”
Later courts cite it for
“is settled law that where an agreement contains general and specific provisions that conflict, 'the provision directed to a particular matter controls over the provision which is general in its terms.” · 2 citing courts
5
GREENMetcalf Constr. Co. v. United States, 102 Fed. Cl. 334 (Fed. Cl. 2011).
cites § 52.236-2 5×cited by 9 cases
Later courts cite it for
“a breach of the duty of good faith and fair dealing claim against the government can only be established by a showing that it 'specifically designed to reappropriate the benefits that the other party expected to obtain from the transaction, thereby abrogating the government's obligations under the contract.” · 2 citing courts
6
GREENGreat Lakes Dredge & Dock Co. v. United States, 60 Fed. Cl. 350 (Fed. Cl. 2004).
cites § 52.236-2 2×cited by 32 cases
Where it cites § 52.236-2
“See 48 C.F.R. § 52.236-2 . Thus, the issues regarding improper risk shifting were resolved prior to bid submission, and do not constitute a proper basis for cancelling the solicitation.”
Later courts cite it for
“the agency has not considered all relevant factors and articulated a rational connection between the facts found and the choice made.” · 3 citing courts
7
GREENMetcalf Constr. Co. v. United States, 742 F.3d 984 (Fed. Cir. 2014).
cites § 52.236-2 1×cited by 170 cases
Where it cites § 52.236-2
“48 C.F.R. § 52.236-2 . The RFP and pre-bid documents set out an understanding of how that provision would be applied to soil conditions.”
The case’s holding
A claim for breach of the implied duty of good faith and fair dealing requires consideration of the specific terms and risk allocations of the contract at issue.
Later courts cite it for
“prevents a party's acts or omissions that, though not proscribed by the contract expressly, are inconsistent with the contract's purpose and deprive the other party of the contemplated value.” · 20 citing courts
8
GREENMeridian Eng'g Co. v. United States, 122 Fed. Cl. 381 (Fed. Cl. 2015).
cites § 52.236-2 4×subsections: (b)cited by 7 cases
Where it cites § 52.236-2
“48 C.F.R. § 52.236-2 . 32 . In this case, the contract incorporates a "differing site conditions” clause, FAR 52.”
The case’s holding
Water flowing in natural washes throughout a construction site is a foreseeable condition that may not constitute a compensable differing site condition.
Later courts cite it for
“water in varying quantities may be flowing in natural washes throughout the length of the project,” · 1 citing court
9
GREENExtreme Coatings, Inc. v. United States, 109 Fed. Cl. 450 (Fed. Cl. 2013).
cites § 52.236-2 2×cited by 20 cases
Where it cites § 52.236-2
“The Federal Circuit also noted that to prevail on a Type I differing site conditions claim, “‘the contractor must prove, by a preponderance of the evidence, that the conditions indicated in the contract differ materially from those it encounters during performance.”
Later courts cite it for
“a complaint must contain sufficient factual matter, accepted as true, to state a claim to relief that is plausible on its face.” · 7 citing courts
10
GREENComtrol, Inc. v. United States, 294 F.3d 1357 (Fed. Cir. 2002).
cites § 52.236-2 1×cited by 79 cases
Where it cites § 52.236-2
“Soil Conditions The Solicitation included the standard Federal Acquisition Regulation (“FAR”) *1360 clauses for differing site conditions and site investigations, 48 C.F.R. §§ 52.236-2 and 52.236-3 (1994), and the standard changes clause, 48 C.”
The case’s holding
Reasonable reliance cannot exist where a contractor bids without reviewing the contract documents on which it seeks to rely.
Later courts cite it for
“where the differing site conditions claim and the defective specifications claim are so intertwined as to constitute a single claim, that claim will be governed by the specific differing site conditions clause and the cases under that clause.” · 6 citing courts
11
GREENURS Grp., Inc. v. Tetra Tech FW, Inc., 181 P.3d 380 (Colo. Ct. App. 2008).
cites § 52.236-2 3×cited by 9 cases
Summary
No passage or summary on file for this case yet.
12
GREENRenda Marine, Inc. v. United States, 509 F.3d 1372 (Fed. Cir. 2007).
cites § 52.236-2 1×cited by 67 cases
Where it cites § 52.236-2
“236-2, 48 C.F.R. § 52.236-2 (a)-(b) (2006). It is distinguished from a Type II differing site condition, which arises when the conditions encountered are of an unusual nature and differ materially from those normally encountered in the kind of work contemplated by the contract.”
The case’s holding
A type I differing site condition claim requires a contractor to prove encountered conditions were not reasonably foreseeable based on all information available during bidding.
Later courts cite it for
“an abuse of discretion occurs when a court misunderstands or misapplies the relevant law or makes clearly erroneous findings of fact.” · 6 citing courts
13
GREENNeal & Co. v. United States, 36 Fed. Cl. 600 (Fed. Cl. 1996).
cites § 52.236-2 2×cited by 32 cases
Where it cites § 52.236-2
“” Title 48 C.F.R. § 52.236-2 (a)(l) (1995). A type I differing site condition requires an affirmative Government representation of some existing site condition.”
The case’s holding
A contractor's unreasonable-bid or bad-faith claim fails unless the agency's conduct rises to bad faith, and claims are judged by information available to bidders at bidding time.
Later courts cite it for
“inappropriate and unprofessional” · 2 citing courts
14
GREENH.B. Mac, Inc. v. United States, 153 F.3d 1338 (Fed. Cir. 1998).
cites § 52.236-2 1×cited by 96 cases
Where it cites § 52.236-2
“If the conditions do materially so differ and cause an increase or decrease in the Contractor’s cost of, or the time required for, performing any part of the work under this contract, whether or not changed as a result of the conditions, an equitable adjustment shall be made…”
The case’s holding
A contractor is not entitled to an equitable adjustment for a Type I differing site condition unless the contract affirmatively indicated the existence of that condition.
Later courts cite it for
“a proper technique of contract interpretation is for the court to place itself in the shoes of a reasonable and prudent contractor and decide how such a contractor would act in interpreting the contract.” · 13 citing courts
15
GREENLathan Co. v. United States, 20 Cl. Ct. 122 (Ct. Cl. 1990).
cites § 52.236-2 1×cited by 91 cases
Where it cites § 52.236-2
“If the conditions do materially so differ and cause an increase or decrease in the Contractor’s cost of, or the time required for, performing any part of the work under this contract, whether or not changed as a result of the conditions, an equitable adjustment shall be made…”
The case’s holding
Bald assertions and speculation do not create an evidentiary conflict sufficient to defeat a motion for summary judgment.
Later courts cite it for
“bald assertions and speculation do not create an evidentiary conflict sufficient to defeat a summary judgment motion.” · 4 citing courts
16
GREENNorth Slope Technical Ltd. v. United States, 14 Cl. Ct. 242 (Ct. Cl. 1988).
cites § 52.236-2 3×cited by 10 cases
Where it cites § 52.236-2
“236-2, 48 C.F.R. § 52.236-2 (1986). The phone call was contemporaneous with a letter providing the same notice.”
17
GREENTrafalgar House Constr., Inc. v. United States, 73 Fed. Cl. 675 (Fed. Cl. 2006).
cites § 52.236-2 2×cited by 8 cases
Where it cites § 52.236-2
“48 C.F.R. § 52.236-2 . The Contract also incorporated FAR 52.”
Later courts cite it for
“the primary purpose of this certification is to prevent the submission of fraudulent claims.” · 2 citing courts
18
GREENKentucky Bridge & Dam, Inc. v. United States, 42 Fed. Cl. 501 (Fed. Cl. 1998).
cites § 52.236-2 2×cited by 16 cases
Where it cites § 52.236-2
“F-50, 48 C.F.R. § 52.236-2 , titled in the contract “Differing Site Conditions (All over $25 K),” which states: DIFFERING SITE CONDITIONS (APR 1984) (a) The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the Contracting Officer of…”
19
GREENOlympus Corp. v. United States, 98 F.3d 1314 (Fed. Cir. 1996).
cites § 52.236-2 1×cited by 44 cases
Where it cites § 52.236-2
“Federal Acquisition Regulation (FAR), 48 C.F.R. § 52.236-2 (1995). On April, 18, Olympus received a Notice to Proceed from the Contracting Officer.”
The case’s holding
The differing site conditions clause applies only to physical conditions existing at the time of contracting and does not cover conditions arising during performance.
Later courts cite it for
“been to shift the risk of adverse subsurface or latent physical conditions from the contractor, who normally bears such risk under a fixed-price contract, to the government.” · 5 citing courts
20
GREENACE Constructors, Inc. v. United States, 81 Fed. Cl. 161 (Fed. Cl. 2008).
cites § 52.236-2 1×cited by 17 cases
Where it cites § 52.236-2
“at 258 , and ACE was a qualified small business at the time of its bid and the award. . A Type I differing site condition is a "latent physical condition[] at the site which differ[s] materially from th[at] indicated in th[e] contract.”

Show all 38 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
198820062024

One bar per year. Tallest: 4 cases in 1998. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Fed. Cl.24Fed. Cir.9Ct. Cl.2A.S.B.C.A.1D. Colo.1Colo. Ct. App.1
By subsection
(a)1 case
Rda Constr. Corp. v. United States, 132 Fed. Cl. 732 (Fed. Cl. 2017).“48 C.F.R. § 52.236-2 (a)-(b). 11 . Modifications 1-3 made administrative changes to the October 13, 2009 Contract.”
(b)1 case
Meridian Eng'g Co. v. United States, 122 Fed. Cl. 381 (Fed. Cl. 2015).“48 C.F.R. § 52.236-2 . 32 . In this case, the contract incorporates a "differing site conditions” clause, FAR 52.”

Show all 38 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com