C.F.R. homeSearch C.F.R.
C.F.R.Title 48Chapter 1—Federal Acquisition RegulationSubchapter H—Clauses and FormsPart 52—Solicitation Provisions and Contract ClausesSubpart 52.2—Text of Provisions and Clauses

48 C.F.R. § 52.236-3 (2026)

52.236-3 Site Investigation and Conditions Affecting the Work.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1988–2024 15citing cases
At a glance

Courts have cited this section in 15 opinions since 1988, 3 of them in the last five years. The most litigated part is subsection (a) (1 case).

As prescribed in 36.503, insert the following clause:

Site Investigation and Conditions Affecting the Work (APR 1984)

(a) The Contractor acknowledges that it has taken steps reasonably necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost, including but not limited to (1) conditions bearing upon transportation, disposal, handling, and storage of materials; (2) the availability of labor, water, electric power, and roads; (3) uncertainties of weather, river stages, tides, or similar physical conditions at the site; (4) the conformation and conditions of the ground; and (5) the character of equipment and facilities needed preliminary to and during work performance. The Contractor also acknowledges that it has satisfied itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, including all exploratory work done by the Government, as well as from the drawings and specifications made a part of this contract. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.

(b) The Government assumes no responsibility for any conclusions or interpretations made by the Contractor based on the information made available by the Government. Nor does the Government assume responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of its officers or agents before the execution of this contract, unless that understanding or representation is expressly stated in this contract.

(End of clause) [48 FR 42478, Sept. 19, 1983, as amended at 60 FR 34761, July 3, 1995]
The 15 cases that cite 48 C.F.R. § 52.236-3 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENRda Constr. Corp. v. United States, 132 Fed. Cl. 732 (Fed. Cl. 2017).
cites § 52.236-3 6×subsections: (a) (b)cited by 10 cases
Where it cites § 52.236-3
“DX 1 at 34 (incorporating 48 C.F.R. § 52.236-3 (a)). 15 RDA justifies the failure to conduct an independent inspection, explaining that most of the deterioration affecting the wharf could not be observed from the deck’s surface.”
Later courts cite it for
“gave in to pressure from other government officials to abdicate his responsibility to be impartial and agreed to support contract interpretations made by officials, who were openly contemptuous of the contractor.” · 2 citing courts
2
GREENOman-Fischbach Int'l (Jv) v. Robert Pirie, 276 F.3d 1380 (Fed. Cir. 2002).
cites § 52.236-3 2×cited by 27 cases
Where it cites § 52.236-3
“The Navy points out that the contract does not identify the particular haul route to be used in getting to the contract’s identified waste disposal sites.”
The case’s holding
A contracting officer's denial of a contractor's equitable adjustment request is treated as a denied claim, and absent an express warranty the government is not liable for third-party-caused cost increases.
Later courts cite it for
“the contracting officer issued a final decision denying the contractor's claim for an equitable adjustment but reaffirmed the amount awarded in unilateral modification p00053.” · 2 citing courts
3
GREENRanda/madison Jt. Venture III v. Gregory Robert Dahlberg, 239 F.3d 1264 (Fed. Cir. 2001).
cites § 52.236-3 1×cited by 37 cases
Where it cites § 52.236-3
“at 2 (emphasis added); see also 48 C.F.R. § 52.236-3 (a) (2000) (FAR 52.236-2(a)).”
The case’s holding
A contractor is charged with notice of information explicitly made available for inspection and must prove by a preponderance of the evidence that actual conditions differ materially from those indicated.
Later courts cite it for
“this court has previously explained that 'in order to establish entitlement to an equitable adjustment by reason of a type i differing site condition, ... the contractor must prove, by a preponderance of the evidence, that the conditions indicated in the contract differ materially from those it encounters during performance.” · 5 citing courts
4
GREENH.B. Mac, Inc. v. United States, 153 F.3d 1338 (Fed. Cir. 1998).
cites § 52.236-3 1×cited by 96 cases
Where it cites § 52.236-3
“See 48 C.F.R. § 52.236-3 (1997). That clause provides in pertinent part as follows: (a) The Contractor acknowledges that it has taken steps reasonably necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general…”
The case’s holding
A contractor is not entitled to an equitable adjustment for a Type I differing site condition unless the contract affirmatively indicated the existence of that condition.
Later courts cite it for
“a proper technique of contract interpretation is for the court to place itself in the shoes of a reasonable and prudent contractor and decide how such a contractor would act in interpreting the contract.” · 13 citing courts
5
GREENS. Comfort Builders, Inc. v. United States, 67 Fed. Cl. 124 (Fed. Cl. 2005).
cites § 52.236-3 2×cited by 9 cases
Where it cites § 52.236-3
“Specifically, the clause at 48 C.F.R. § 52.236-3 (Apr.1984) (incorporated by reference into the contract through 48 C.”
6
GREENTrafalgar House Constr., Inc. v. United States, 73 Fed. Cl. 675 (Fed. Cl. 2006).
cites § 52.236-3 2×cited by 8 cases
Where it cites § 52.236-3
“48 C.F.R. § 52.236-3 . 3. The Contract Incorporated Contract Drawings And The Project Manual.”
Later courts cite it for
“the primary purpose of this certification is to prevent the submission of fraudulent claims.” · 2 citing courts
7
GREENManuel Bros. v. United States, 55 Fed. Cl. 8 (Fed. Cl. 2002).
cites § 52.236-3 1×cited by 8 cases
Where it cites § 52.236-3
“” 48 C.F.R. § 52.236-3 (a). The plaintiffs expert confirmed that if a contractor does not inform itself of the soil conditions at a project site, they assume the risk of the type of soil a contractor will encounter.”
Later courts cite it for
“oral explanations or instructions given before the award of the contract are not binding.” · 1 citing court
8
GREENHoffman Constr. Co. v. United States, 40 Fed. Cl. 184 (Fed. Cl. 1998).
cites § 52.236-3 2×cited by 5 cases
Where it cites § 52.236-3
“” JX 2 at 81; 48 C.F.R. § 52.236-3 (a). Bidders were also informed that GSA would be conducting two guided building tours on specified dates but that “[inspection of the existing building plans as noted elsewhere is to be coordinated separately.”
9
GREENNorth Slope Technical Ltd. v. United States, 14 Cl. Ct. 242 (Ct. Cl. 1988).
cites § 52.236-3 1×cited by 10 cases
Where it cites § 52.236-3
“236-3, 48 C.F.R. § 52.236-3 (1986); 25 (2) North Slope should *253 have obtained additional data on subsurface conditions from the Office of the Alaska District Engineer in Anchorage (the availability of which was pointed out in the bidding documents); (3) North Slope lacked an…”
10
GREENHahnenkamm, LLC v. United States, 104 F.4th 1333 (Fed. Cir. 2024).
cites § 52.236-3 1×cited by 0 cases
Where it cites § 52.236-3
“48 C.F.R. § 52.236-3 . Those provisions also re- lieve the Government from responsibility of conclusions made by the contractor and clarify the Government is not responsible for “any understanding reached or representa- tion made concerning conditions .”
11
GREENRma Eng'g S.A.R.L v. United States, 140 Fed. Cl. 191 (Fed. Cl. 2018).
cites § 52.236-3 1×cited by 0 cases
Where it cites § 52.236-3
“48 C.F.R. § 52.236-3 . 5 In addition, the Contract incorporated a number of other standard Federal Acquisition Regulation (“FAR”) provisions, including FAR 52.”
12
NO FLAGNorth Am. Landscaping Constr. & Dredge Co. v. United States, No. 17-903 (Fed. Cl. Mar. 15, 2019).
cites § 52.236-3 1×cited by 0 cases
Where it cites § 52.236-3
“Among the standard contract clauses included in the solicitation was the Site Investigation and Conditions Affecting the Work clause, 48 C.F.R. § 52.236-3 (2017). ECF No. 12-1 at 88.”
13
NO FLAGLinda Rugina Co. D/B/A Ruginas Afrikan Vill., ASBCA No. 62207, 62334 (A.S.B.C.A. Apr. 7, 2020).
cites § 52.236-3 1×cited by 0 cases
Where it cites § 52.236-3
“48 C.F.R. § 52.236-3 (emphasis added). Appellant did not attend a September 2018 site visit before it submitted its proposal; had it done so, it presumably would have seen and been able to measure the specific work that it ultimately contracted to perform (see R4, tabs 3-4, 14,…”
14
NO FLAGBCI Constr. USA, Inc., No. 62657, 62975, 63200 (A.S.B.C.A. Feb. 5, 2024).
cites § 52.236-3 1×cited by 0 cases
Where it cites § 52.236-3
“” 48 C.F.R. § 52.236-3 . FAR 52.236-9(b) states that “[t]he Contractor shall protect from damage all existing improvements and utilities (1) at or near the work site and (2) on adjacent property of a 19 third party, the locations of which are made known to or should be known by…”
15
GREENHahnenkamm, LLC v. United States, No. 22-2018 (Fed. Cir. June 21, 2024).
cites § 52.236-3 1×cited by 0 cases
Where it cites § 52.236-3
“48 C.F.R. § 52.236-3 . Those provisions also re- lieve the Government from responsibility of conclusions made by the contractor and clarify the Government is not responsible for “any understanding reached or representa- tion made concerning conditions .”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
198820062024

One bar per year. Tallest: 3 cases in 2024. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Fed. Cl.7Fed. Cir.5A.S.B.C.A.2Ct. Cl.1
By subsection
(a)1 case
Rda Constr. Corp. v. United States, 132 Fed. Cl. 732 (Fed. Cl. 2017).“DX 1 at 34 (incorporating 48 C.F.R. § 52.236-3 (a)). 15 RDA justifies the failure to conduct an independent inspection, explaining that most of the deterioration affecting the wharf could not be observed from the deck’s surface.”
(b)1 case
Rda Constr. Corp. v. United States, 132 Fed. Cl. 732 (Fed. Cl. 2017).
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com