C.F.R. homeSearch C.F.R.
C.F.R.Title 48Chapter 1—Federal Acquisition RegulationSubchapter H—Clauses and FormsPart 52—Solicitation Provisions and Contract ClausesSubpart 52.2—Text of Provisions and Clauses

48 C.F.R. § 52.236-9 (2026)

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 ACTIVE · 2 IN 5Y cited 1998–2024 6citing cases
At a glance

Courts have cited this section in 6 opinions since 1998, 2 of them in the last five years.

As prescribed in 36.509, insert the following clause:

Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (APR 1984)

(a) The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

(b) The Contractor shall protect from damage all existing improvements and utilities (1) at or near the work site and (2) on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

(End of clause) [48 FR 42478, Sept. 19, 1983, as amended at 60 FR 34761, July 3, 1995]
The 6 cases that cite 48 C.F.R. § 52.236-9 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENCom. Contractors, Inc. v. United States, 154 F.3d 1357 (Fed. Cir. 1998).
cites § 52.236-9 2×cited by 72 cases
Where it cites § 52.236-9
“236-9(b), 48 C.F.R. § 52.236-9 (b) (1987) (incorporated into the contract) (“The Contractor shall protect from damage all existing improvements and utilities (1) at or near the work site and (2) on adjacent property of a third party.”
The case’s holding
A contractor is liable under the False Claims Act if it submits claims with actual knowledge of falsity, deliberate ignorance, or reckless disregard of the truth.
Later courts cite it for
“for purposes of the fca false claims act, a contractor is deemed to have known that a claim it submitted was false if it had actual knowledge of the falsity of the claim or if it acted in deliberate ignorance or reckless disregard of the truth or falsity of the claim.” · 6 citing courts
2
GREENGeorge Sollitt Constr. Co. v. United States, 64 Fed. Cl. 229 (Fed. Cl. 2005).
cites § 52.236-9 1×cited by 47 cases
Where it cites § 52.236-9
“236-9, codified at 48 C.F.R. § 52.236-9 (1994) (“Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements”), made Sollitt responsible for the costs of damage to utilities at the construction site, Def.”
The case’s holding
Disputed contract payment amounts are subject to Contract Disputes Act interest rather than Prompt Payment Act interest.
Later courts cite it for
“extended field office overhead also may sometimes be recovered as delay damages.” · 4 citing courts
3
GREENJoseph Dureiko v. United States, 209 F.3d 1345 (Fed. Cir. 2000).
cites § 52.236-9 1×cited by 82 cases
Where it cites § 52.236-9
“” 48 C.F.R. § 52.236-9 (1999). Pine Isle also notes that the Corps’s own Quality Assurance Plan requires that a Quality Assurance Representative “[a]ssure that utility outlets and other features that must not be damaged are marked before removal operations are started.”
The case’s holding
The discretionary function exception does not bar a breach of contract claim when a federal agency voluntarily enters into a contract prescribing a mandatory course of action.
Later courts cite it for
“in the absence of sufficient factual allegations supporting the parties' mutual intent, we construe the ambiguous contract provision against the drafter, unless the ambiguity is patent.” · 3 citing courts
4
NO FLAGRLB Contracting, Inc., No. 62779 (A.S.B.C.A. June 15, 2023).
cites § 52.236-9 1×cited by 0 cases
Where it cites § 52.236-9
“” 48 C.F.R. § 52.236-9 (b). 8. The 0043 Contract specification 1.”
5
NO FLAGBCI Constr. USA, Inc., No. 62657, 62975, 63200 (A.S.B.C.A. Feb. 5, 2024).
cites § 52.236-9 1×cited by 0 cases
Where it cites § 52.236-9
“” 48 C.F.R. § 52.236-9 . 77. BCI asserts that prior to beginning construction on the upper training wall, it determined that the existing riprap at Monolith 12L and 12R exceeded the Monolith joint where concrete removal and placement was to occur (app.”
6
NO FLAGCom. Contractors, Inc. v. United States, 41 Fed. Cl. 1357 (Fed. Cir. 1998).
cites § 52.236-9 2×cited by 0 cases
Where it cites § 52.236-9
“236-9(b), 48 C.F.R. § 52.236-9 (b) (1987) (incorporated into the contract) (“The Contractor shall protect from damage all existing improvements and utilities (1) at or near the work site and (2) on adjacent property of a third party.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199820112024

One bar per year. Tallest: 2 cases in 1998. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Fed. Cir.3A.S.B.C.A.2Fed. Cl.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com