C.F.R. homeSearch C.F.R.
C.F.R.Title 48Chapter 1—Federal Acquisition RegulationSubchapter H—Clauses and FormsPart 52—Solicitation Provisions and Contract ClausesSubpart 52.2—Text of Provisions and Clauses

48 C.F.R. § 52.243-1 (2026)

52.243-1 Changes—Fixed-Price.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1993–2024 22citing cases
At a glance

Courts have cited this section in 22 opinions since 1993, 1 of them in the last five years.

As prescribed in 43.205(a)(1), insert the following clause. The 30-day period may be varied according to agency procedures.

Changes—Fixed-Price (AUG 1987)

(a) The Contracting Officer may at any time, by written order, and without notice to the sureties, if any, make changes within the general scope of this contract in any one or more of the following:

(2) Drawings, designs, or specifications when the supplies to be furnished are to be specially manufactured for the Government in accordance with the drawings, designs, or specifications.

(2) Method of shipment or packing.

(3) Place of delivery.

(b) If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of the work under this contract, whether or not changed by the order, the Contracting Officer shall make an equitable adjustment in the contract price, the delivery schedule, or both, and shall modify the contract.

(c) The Contractor must assert its right to an adjustment under this clause within 30 days from the date of receipt of the written order. However, if the Contracting Officer decides that the facts justify it, the Contracting Officer may receive and act upon a proposal submitted before final payment of the contract.

(d) If the Contractor's proposal includes the cost of property made obsolete or excess by the change, the Contracting Officer shall have the right to prescribe the manner of the disposition of the property.

(e) Failure to agree to any adjustment shall be a dispute under the Disputes clause. However, nothing in this clause shall excuse the Contractor from proceeding with the contract as changed.

(End of clause)

Alternate I (APR 1984). If the requirement is for services, other than architect-engineer or other professional services, and no supplies are to be furnished, substitute the following paragraph (a) for paragraph (a) of the basic clause:

(a) The Contracting Officer may at any time, by written order, and without notice to the sureties, if any, make changes within the general scope of this contract in any one or more of the following:

(1) Description of services to be performed.

(2) Time of performance (i.e., hours of the day, days of the week, etc.).

(3) Place of performance of the services.

Alternate II (APR 1984). If the requirement is for services (other than architect-engineer services, transportation, or research and development) and supplies are to be furnished, substitute the following paragraph (a) for paragraph (a) of the basic clause:

(a) The Contracting Officer may at any time, by written order, and without notice to the sureties, if any, make changes within the general scope of this contract in any one or more of the following:

(1) Description of services to be performed.

(2) Time of performance (i.e., hours of the day, days of the week, etc.).

(3) Place of performance of the services.

(4) Drawings, designs, or specifications when the supplies to be furnished are to be specially manufactured for the Government in accordance with the drawings, designs, or specifications.

(5) Method of shipment or packing of supplies.

(6) Place of delivery.

Alternate III (APR 1984). If the requirement is for architect-engineer or other professional services, substitute the following paragraph (a) for paragraph (a) of the basic clause and add the following paragraph (f):

(a) The Contracting Officer may at any time, by written order, and without notice to the sureties, if any, make changes within the general scope of this contract in the services to be performed.

(f) No services for which an additional cost or fee will be charged by the Contractor shall be furnished without the prior written authorization of the Contracting Officer.

Alternate IV (APR 1984). If the requirement is for transportation services, substitute the following paragraph (a) for paragraph (a) of the basic clause:

(a) The Contracting Officer may at any time, by written order, and without notice to the sureties, if any, make changes within the general scope of this contract in any one or more of the following:

(1) Specifications.

(2) Work or services.

(3) Place of origin.

(4) Place of delivery.

(5) Tonnage to be shipped.

(6) Amount of Government-furnished property.

Alternate V (APR 1984). If the requirement is for research and development and it is desired to include the clause, substitute the following subparagraphs (a)(1) and (a)(3) and paragraph (b) for subparagraphs (a)(1) and (a)(3) and paragraph (b) of the basic clause:

(a)(1) Drawings, designs, or specifications.

(3) Place of inspection, delivery, or acceptance.

(b) If any such change causes an increase or decrease in the cost of, or time required for, performing this contract, whether or not changed by the order, the Contracting Officer shall make an equitable adjustment in (1) the contract price, the time of performance, or both; and (2) other affected terms of the contract, and shall modify the contract accordingly.

[48 FR 42478, Sept. 19, 1983, as amended at 52 FR 30079, Aug. 12, 1987; 54 FR 48995, Nov. 28, 1989; 83 FR 42576, Aug. 22, 2018]
The 20 cases that cite 48 C.F.R. § 52.243-1 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENElec. Boat Corp. v. Sec'y of the Navy, 958 F.3d 1372 (Fed. Cir. 2020).
cites § 52.243-1 2×cited by 23 cases
Where it cites § 52.243-1
“The Contract incorporates by reference the standard Changes Clause under 48 C.F.R. §§ 52.243-1 , -2. J.A. 335, 344.”
The case’s holding
A Contract Disputes Act claim accrues under the Federal Acquisition Regulation, the contract language, and the facts, when the right to relief becomes fixed rather than upon later refusal.
Later courts cite it for
“interpretation of a government contract is a question of law, which we also review de novo.” · 2 citing courts
2
GREENBgt Holdings LLC v. United States, 984 F.3d 1003 (Fed. Cir. 2020).
cites § 52.243-1 2×cited by 13 cases
Where it cites § 52.243-1
“The contract incorporates the standard FAR changes clause for fixed-price contracts, 48 C.F.R. § 52.243-1 . The fixed-price changes clause covers the Navy’s modifications to the method of shipment, the method of packing, the place of delivery, and the “[d]rawings, designs, or…”
Later courts cite it for
“the contract unquestionably gives the navy the right to decrease or withdraw gfe, bgt cannot use the doctrine of good faith and fair dealing to complain of the very conduct that the contract expressly permits.” · 3 citing courts
3
GREENJames M. Ellett Constr. Co. v. United States, 93 F.3d 1537 (Fed. Cir. 1996).
cites § 52.243-1 1×cited by 235 cases
Where it cites § 52.243-1
“43081 , 93-1 BCA ¶ 25,512 at 127,054, 1992 WL 302847 (1992); see also 48 C.F.R. § 52.243-1 (1995) (“Changes-Fixed Price” clause).”
The case’s holding
Jurisdiction under the Contract Disputes Act requires both a valid claim and a contracting officer's final decision on that claim.
Later courts cite it for
“there are three requirements a nonroutine submission must meet to be a 'claim.' it must be: (1) a written demand or assertion, (2) seeking as a matter of right, (3) the payment of money in a sum certain.” · 8 citing courts
4
GREENNorthrop Grumman Corp. v. United States, 50 Fed. Cl. 443 (Fed. Cl. 2001).
cites § 52.243-1 1×cited by 38 cases
Where it cites § 52.243-1
“48 C.F.R. § 52.243-1 (2000) (Changes — Fixed Price); 48 C.”
The case’s holding
A contractor's failure to meet proposal assertions constitutes material misrepresentation only if the errors are willful and egregious.
Later courts cite it for
“it is quite common for proposals to fall short of their assertions; it is not something to be punished unless the errors were willful and egregious.” · 2 citing courts
5
GREENBecho, Inc. v. United States, 47 Fed. Cl. 595 (Fed. Cl. 2000).
cites § 52.243-1 1×cited by 85 cases
Where it cites § 52.243-1
“” 48 C.F.R. § 52.243-1 . On January 31, 1997, Fernando Aguilar, a civil engineer with the Walla Walla District of the Corps, was designated COR on the subject contract.”
The case’s holding
A contract modification constitutes a cardinal change if it fundamentally alters the original undertaking or if the cost greatly exceeds the original contract cost.
Later courts cite it for
“contemplated by the original contract.” · 2 citing courts
6
GREENSufi Network Servs., Inc. v. United States, 755 F.3d 1305 (Fed. Cir. 2014).
cites § 52.243-1 1×cited by 16 cases
Where it cites § 52.243-1
“243-1 provision, 48 C.F.R. § 52.243-1 , but only overhead (not profits) for work that was compensable as damages for breach.”
The case’s holding
A plaintiff seeking lost profits must prove causation and reasonably certain damages by a preponderance, and a non-breach impediment to profit does not shift that burden to the defendant.
Later courts cite it for
“we remand to the court of federal claims, with instructions to remand to the board for further factual findings consistent with this opinion.” · 2 citing courts
7
GREENStarflight Boats v. United States, 48 Fed. Cl. 592 (Fed. Cl. 2001).
cites § 52.243-1 1×cited by 15 cases
Where it cites § 52.243-1
“” 48 C.F.R. § 52.243-1 (emphasis added). Plaintiff has not offered any evidence that Mr.”
Later courts cite it for
“government employees hold express actual authority to bind the government in contract only when the constitution, a statute, or a regulation grants them such authority in unambiguous terms.” · 4 citing courts
8
GREENUnited States v. Hirani Eng'g & Land Surveying, P.C., 345 F. Supp. 3d 11 (D.C. Cir. 2018).
cites § 52.243-1 1×cited by 6 cases
Later courts cite it for
“hirani breached the subcontract by refusing to pay acc for the work that it performed.” · 1 citing court
9
GREENDonald H. Rumsfeld v. Applied Companies, Inc., 318 F.3d 1317 (Fed. Cir. 2002).
cites § 52.243-1 1×cited by 9 cases
Where it cites § 52.243-1
“243-l(b), 48 C.F.R. § 52.243-1 (b), or to the recovery of the costs it had incurred plus a reasonable profit, as contemplated by the Termination for Convenience Clause, see FAR 52.”
10
GREENOrlando Helicopter Airways v. United States, 75 F.3d 622 (11th Cir. 1996).
cites § 52.243-1 1×cited by 17 cases
Where it cites § 52.243-1
“48 C.F.R. §§ 52.243-1 , 52.243-7 (1994). 3 .”
Later courts cite it for
“section 2675(a) is satisfied if the claimant (1) gave the appropriate agency written notice of the tort claim to enable the agency to investigate; and (2) stated a sum certain as to the value of the claim.” · 3 citing courts
11
GREENLB&B Assocs. Inc. v. United States, 91 Fed. Cl. 142 (Fed. Cl. 2010).
cites § 52.243-1 1×cited by 7 cases
Where it cites § 52.243-1
“48 C.F.R. § 52.243-1 (2009). A constructive change requires that the contractor undertake extra work not previously contemplated under a contract; work that cannot be characterized as additional work does not constitute a constructive change.”
12
GREENGreen Mgmt. Corp. v. United States, 42 Fed. Cl. 411 (Fed. Cl. 1998).
cites § 52.243-1 1×cited by 13 cases
Where it cites § 52.243-1
“The changes clause in the contract between the instant parties, “Changes — Fixed-Price (August 1987), Alternate I,” 48 C.F.R. § 52.243-1 (1987), provides that the contracting officer may make changes within the general scope of the contract.”
13
GREENNorthrop Grumman Corp. v. United States, 42 Fed. Cl. 1 (Fed. Cl. 1998).
cites § 52.243-1 1×cited by 9 cases
Where it cites § 52.243-1
“243-1, 48 C.F.R. § 52.243-1 (1997) (as modified by Alternate II (Apr.”
14
GREENECC Int'l Corp. v. United States, 43 Fed. Cl. 359 (Fed. Cl. 1999).
cites § 52.243-1 1×cited by 9 cases
Where it cites § 52.243-1
“On or about September 5, 1995, the Air Force unilaterally executed Modification P00048 pursuant to its authority under the Changes clause, see 48 C.F.R. § 52.243-1 (1998), increasing the contract amount for CLIN 0006 by $166,822.”
15
GREENEnv't Tectonics Corp. v. United States, 72 Fed. Cl. 290 (Fed. Cl. 2006).
cites § 52.243-1 1×cited by 3 cases
Where it cites § 52.243-1
“2d 975, 984 (1968) (determining that a contractor was allowed to recover interest on actual borrowings based on government changes to the contract pursuant to an Army Procurement Procedure analogous to 48 C.F.R. § 52.243-1 ). In both circumstances, however, the contractor must…”
16
GREENUMC Elec. Co. v. United States, 45 Fed. Cl. 507 (Fed. Cl. 1999).
cites § 52.243-1 1×cited by 4 cases
Where it cites § 52.243-1
“See 48 C.F.R. § 52.243-1 (1988). The government, however, states in its post-hearing submission on the accounting of costs in the above-captioned cases that, at the fraud trial, “The government chose to keep its ease simple and rely on a comparison of UMC’s claimed costs versus…”
17
GREENExec. Bus. Media, Inc. v. U.S. Dep't of Def., 3 F.3d 759 (4th Cir. 1993).
cites § 52.243-1 1×cited by 15 cases
Where it cites § 52.243-1
“It was based on the terms of the Changes Clause in government contracts, 48 C.F.R. § 52.243-1 (a) ("The Contracting Officer may .”
Later courts cite it for
“essentially the same performance.” · 3 citing courts
18
GREENN. States Power Co. v. United States, 43 Fed. Cl. 374 (Fed. Cl. 1999).
cites § 52.243-1 1×cited by 3 cases
Where it cites § 52.243-1
“” 48 C.F.R. § 52.243-1 (1998). . We add, by way of footnote, that while a twelve-year postponement in the commencement of the Government’s promised performance would seem to stretch the concept of "delay” to the breaking point, it is worth keeping in mind that, by the terms of…”
Later courts cite it for
“is obliged by the terms of its contract with doe to pursue its demand for monetary relief at the agency level, i.e., through a claim for equitable adjustment submitted in accordance with the contract's disputes clause.” · 3 citing courts
19
GREENNorthrop Grumman Corp. v. United States, 41 Fed. Cl. 645 (Fed. Cl. 1998).
cites § 52.243-1 1×cited by 1 case
Where it cites § 52.243-1
“243-1, 48 C.F.R. § 52.243-1 (1997) ("Changes-Fixed-Price”), with FAR § 52.”
20
NO FLAGAm. Civil Constr., LLC v. Hirani Eng'g & Land Surveying, Pc, No. 2014-0745 (D.D.C. Nov. 28, 2018).
cites § 52.243-1 1×cited by 0 cases
Summary
No passage or summary on file for this case yet.

Show all 22 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199320082024

One bar per year. Tallest: 3 cases in 1998. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Fed. Cl.12Fed. Cir.5A.S.B.C.A.111th Cir.14th Cir.1D.C. Cir.1D.D.C.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Show all 22 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com