C.F.R. homeSearch C.F.R.
C.F.R.Title 48Chapter 1—Federal Acquisition RegulationSubchapter H—Clauses and FormsPart 52—Solicitation Provisions and Contract ClausesSubpart 52.2—Text of Provisions and Clauses

48 C.F.R. § 52.243-4 (2026)

52.243-4 Changes.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1992–2025 43citing cases
At a glance

Courts have cited this section in 43 opinions since 1992, 3 of them in the last five years. The most litigated part is subsection (d) (1 case).

As prescribed in 43.205(d), insert the following clause. The 30-day period may be varied according to agency procedures.

Changes (JUN 2007)

(a) The Contracting Officer may, at any time, without notice to the sureties, if any, by written order designated or indicated to be a change order, make changes in the work within the general scope of the contract, including changes—

(1) In the specifications (including drawings and designs);

(2) In the method or manner of performance of the work;

(3) In the Government-furnished property or services; or

(4) Directing acceleration in the performance of the work.

(b) Any other written or oral order (which, as used in this paragraph (b), includes direction, instruction, interpretation, or determination) from the Contracting Officer that causes a change shall be treated as a change order under this clause; provided, that the Contractor gives the Contracting Officer written notice stating (1) the date, circumstances, and source of the order and (2) that the Contractor regards the order as a change order.

(c) Except as provided in this clause, no order, statement, or conduct of the Contracting Officer shall be treated as a change under this clause or entitle the Contractor to an equitable adjustment.

(d) If any change under this clause causes an increase or decrease in the Contractor's cost of, or the time required for, the performance of any part of the work under this contract, whether or not changed by any such order, the Contracting Officer shall make an equitable adjustment and modify the contract in writing. However, except for an adjustment based on defective specifications, no adjustment for any change under paragraph (b) of this clause shall be made for any costs incurred more than 20 days before the Contractor gives written notice as required. In the case of defective specifications for which the Government is responsible, the equitable adjustment shall include any increased cost reasonably incurred by the Contractor in attempting to comply with the defective specifications.

(e) The Contractor must assert its right to an adjustment under this clause within 30 days after (1) receipt of a written change order under paragraph (a) of this clause or (2) the furnishing of a written notice under paragraph (b) of this clause, by submitting to the Contracting Officer a written statement describing the general nature and amount of proposal, unless this period is extended by the Government. The statement of proposal for adjustment may be included in the notice under paragraph (b) above.

(f) No proposal by the Contractor for an equitable adjustment shall be allowed if asserted after final payment under this contract.

(End of clause) [48 FR 42478, Sept. 19, 1983, as amended at 52 FR 30079, Aug. 12, 1987; 72 FR 27389, May 15, 2007]
The 20 cases that cite 48 C.F.R. § 52.243-4 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENbell/heery v. United States, 739 F.3d 1324 (Fed. Cir. 2014).
cites § 52.243-4 7×cited by 192 cases
Where it cites § 52.243-4
“” 48 C.F.R. § 52.243-4 (a). The Changes clause further states that, for any such ordered change that “causes an increase or decrease in the Contractor’s cost of, or the time required for, the performance of any part of the work under [the] contract,” the Contracting Officer…”
The case’s holding
A breach of contract claim requires factual allegations supporting a breach of a specific contractual duty identified in the agreement.
Later courts cite it for
“performed work beyond the contract requirements, and ... that the additional work was ordered, expressly or impliedly, by the government.” · 20 citing courts
2
GREENBell Bci Co. v. United States, 570 F.3d 1337 (Fed. Cir. 2009).
cites § 52.243-4 3×cited by 57 cases
Where it cites § 52.243-4
“The contract included language from the Federal Acquisition Regulations (“FAR”), 48 C.F.R. § 52.243-4 (d), which expressly allows for equitable adjustment: If any change under this clause causes an increase or decrease in the Contractor’s cost of, or the time required for, the…”
The case’s holding
A contractual release is interpreted according to standard contract principles and extrinsic evidence is admissible only if the release language is ambiguous.
Later courts cite it for
“because a release is contractual in nature, it is interpreted in the same manner as any other contract term or provision.” · 10 citing courts
3
GREENK-Con Bldg. Sys., Inc. v. United States, 778 F.3d 1000 (Fed. Cir. 2015).
cites § 52.243-4 2×cited by 145 cases
The case’s holding
Jurisdiction under the Contract Disputes Act requires that a claim meeting specific requirements be submitted to the contracting officer and that the officer issue a final decision on that claim.
Later courts cite it for
“should treat requests as involving separate claims if they either request different remedies (whether monetary or non-monetary) or assert grounds that are materially different from each other factually or legally.” · 13 citing courts
4
GREENGeorge Sollitt Constr. Co. v. United States, 64 Fed. Cl. 229 (Fed. Cl. 2005).
cites § 52.243-4 3×cited by 47 cases
Where it cites § 52.243-4
“243-4 (d) (1994), the government is liable when changes to contract work increased the contractor’s costs: If any change under this clause causes an increase or decrease in the Contractor’s cost of, or the time required for, the performance of any part of the work under this…”
The case’s holding
Disputed contract payment amounts are subject to Contract Disputes Act interest rather than Prompt Payment Act interest.
Later courts cite it for
“extended field office overhead also may sometimes be recovered as delay damages.” · 4 citing courts
5
GREENComtrol, Inc. v. United States, 294 F.3d 1357 (Fed. Cir. 2002).
cites § 52.243-4 1×cited by 79 cases
Where it cites § 52.243-4
“236-3 (1994), and the standard changes clause, 48 C.F.R. § 52.243-4 (1994). Paragraph 1.”
The case’s holding
Reasonable reliance cannot exist where a contractor bids without reviewing the contract documents on which it seeks to rely.
Later courts cite it for
“where the differing site conditions claim and the defective specifications claim are so intertwined as to constitute a single claim, that claim will be governed by the specific differing site conditions clause and the cases under that clause.” · 6 citing courts
cites § 52.243-4 1×cited by 66 cases
Where it cites § 52.243-4
“During the course of construction, Odebrecht requested and received a number of “equitable adjustments” to the contract price. Equitable adjustments are used to keep a contractor whole when the Government modifies the contract or, under some Government contracts, for changed…”
The case’s holding
Claims submitted under a contract procured by fraud are actionable under the False Claims Act even if the claims themselves are not fraudulent.
Later courts cite it for
“for each claim submitted to the government under a contract which was procured by fraud, even in the absence of evidence that the claims were fraudulent in themselves.” · 19 citing courts
7
GREENMeridian Eng'g Co. v. United States, 122 Fed. Cl. 381 (Fed. Cl. 2015).
cites § 52.243-4 3×cited by 7 cases
Where it cites § 52.243-4
“at 75 (citing 48 C.F.R. § 52.243-4 (d) 36 and 48 C.F.R.”
The case’s holding
Water flowing in natural washes throughout a construction site is a foreseeable condition that may not constitute a compensable differing site condition.
Later courts cite it for
“water in varying quantities may be flowing in natural washes throughout the length of the project,” · 1 citing court
8
GREENLakeshore Eng'g Servs., Inc. v. United States, 748 F.3d 1341 (Fed. Cir. 2014).
cites § 52.243-4 1×cited by 44 cases
Where it cites § 52.243-4
“2007); see 48 C.F.R. §§ 52.243-4 , 252.243-7002. Lake-shore’s claim is not based on any such government modification; the claim that prices rose during the term of the contract does not entitle Lakeshore to equitable adjustment under the FAR provision.”
The case’s holding
In a firm fixed-price contract, the contractor assumes the risk of unexpected costs including pricing inaccuracies and inflation.
Later courts cite it for
“the essence of a firm fixed-price contract is that the contractor, not the government, assumes the risk of unexpected costs.” · 9 citing courts
cites § 52.243-4 1×cited by 39 cases
Where it cites § 52.243-4
“See 48 C.F.R. § 52.243-4 . The clause provides that a "written or oral order .”
The case’s holding
A district court possesses discretion in awarding prejudgment interest, though such awards must comply with stipulations regarding the accrual of damages.
Later courts cite it for
“an award of prejudgment interest is within the district court's discretion.” · 4 citing courts
10
GREENMorrison Knudsen Corp. v. Fireman's Fund Ins., 175 F.3d 1221 (10th Cir. 1999).
cites § 52.243-4 1×cited by 104 cases
Where it cites § 52.243-4
“See 48 C.F.R. § 52.243-4 . The clause provides that MK may, "by written order designated .”
The case’s holding
An appellant's failure to provide a necessary transcript to demonstrate prejudice from an instructional error requires affirmance of the judgment below.
Later courts cite it for
“our concern is to ensure that our review does not leave us with substantial doubt whether the instructions, considered as a whole, properly guided the jury in its deliberations.” · 7 citing courts
11
GREENSauer Inc. v. Richard J. Danzig, 224 F.3d 1340 (Fed. Cir. 2000).
cites § 52.243-4 1×cited by 75 cases
Where it cites § 52.243-4
“The changes clause in the RIF Contract provides for an equitable adjustment if any change “causes an increase or decrease in the Contractor’s cost of, or the time required for, the performance of any part of the work under this contract, whether or not changed.”
The case’s holding
A party asserting that liquidated damages were improperly assessed bears the burden of proving the extent of the excusable delay caused by unforeseeable factors beyond its control.
Later courts cite it for
“as a general rule, a party asserting that liquidated damages were improperly assessed bears the burden of showing the extent of the excusable delay to which it is entitled.” · 10 citing courts
12
GREENKentucky Bridge & Dam, Inc. v. United States, 42 Fed. Cl. 501 (Fed. Cl. 1998).
cites § 52.243-4 2×cited by 16 cases
Where it cites § 52.243-4
“F-66, 48 C.F.R. § 52.243-4 , titled “Changes,” which states: CHANGES (AUG 1987) (a) The Contracting Officer may, at any time, without notice to the sureties, if any, by written order designated or indicated to be a change order, make changes in the work within the general scope…”
13
GREENMeridian Eng'g Co. v. United States, 130 Fed. Cl. 147 (Fed. Cl. 2016).
cites § 52.243-4 2×subsections: (d) 2×cited by 3 cases
Where it cites § 52.243-4
“See 48 CF.R. 52.243-4(d). Adjustments under the Suspension Clause, however, exclude profit.”
14
GREENT. Brown Constructors, Inc. v. Federico Pena, 132 F.3d 724 (Fed. Cir. 1998).
cites § 52.243-4 1×cited by 45 cases
Where it cites § 52.243-4
“See 48 C.F.R. § 52.243-4 (1996). The disputed work, according to Brown, is work specified by the contract.”
The case’s holding
A contractor prevails on a misrepresentation claim by proving the government made an erroneous representation of a material fact that the contractor honestly and reasonably relied upon to its detriment.
Later courts cite it for
“a misrepresentation is material if it would be likely to induce a reasonable person to manifest his assent, or if the maker knows that it would be likely to induce the recipient to do so.” · 7 citing courts
15
GREENSNC-Lavalin Am., Inc. v. Alliant Techsystems, Inc., 858 F. Supp. 2d 620 (W.D. Va. 2012).
cites § 52.243-4 8×cited by 1 case
Where it cites § 52.243-4
“As noted in several of the more recent constructive acceleration cases involving claims against the federal government, including Fraser, such claims against the United States are brought pursuant to the standard changes clause, which is required for most federal construction…”
16
GREENTriax-Pac. v. Michael P.W. Stone, 958 F.2d 351 (Fed. Cir. 1992).
cites § 52.243-4 1×cited by 37 cases
Where it cites § 52.243-4
“48 C.F.R. § 52.243-4 (1990). The Suspension of Work clause provides that If the performance of all or any part of the work is, for an unreasonable period of time .”
The case’s holding
A contractor cannot recover suspension-clause delay costs where its own late performance on a prior contract concurrently caused the delay, because the government must be the sole proximate cause.
Later courts cite it for
“contingencies contemplated by various contract clauses are remediable under those clauses of the contract, not as a breach of the contract.” · 3 citing courts
17
GREENSab Constr., Inc. v. United States, 66 Fed. Cl. 77 (Fed. Cl. 2005).
cites § 52.243-4 1×cited by 15 cases
Where it cites § 52.243-4
“” 48 C.F.R. § 52.243-4 (Aug.1987). The plaintiffs contract contained a clause stating “[wjhen costs are a factor in any price adjustment under this contract, the contract cost principles and procedures in FAR Part 31 and [Department of Defense Federal Acquisition Regulation…”
Later courts cite it for
“prove that the government somehow delayed, accelerated, augmented, or complicated the work, and thereby caused plaintiff to incur specific additional costs, and that those costs were reasonable, allowable, and allocable to the contract.” · 2 citing courts
18
GREENAAB Jt. Venture v. United States, 75 Fed. Cl. 414 (Fed. Cl. 2007).
cites § 52.243-4 1×cited by 15 cases
Summary
No passage or summary on file for this case yet.
19
GREENWilliam O'Hara v. NIKA Tech., Inc., 878 F.3d 470 (4th Cir. 2017).
cites § 52.243-4 1×cited by 6 cases
Where it cites § 52.243-4
“” 48 C.F.R. §§ 52.243-4 (a)(l)-(2). When the government requires a contractor to perform additional work under an existing contract, the contractor may submit a “change order proposal,” requesting that the government increase the contractor’s compensation to reflect the extra…”
Later courts cite it for
“courts are not free to read into the language of a statute what is not there.” · 3 citing courts
20
GREENUnited States v. Hirani Eng'g & Land Surveying, P.C., 345 F. Supp. 3d 11 (D.C. Cir. 2018).
cites § 52.243-4 1×cited by 6 cases
Where it cites § 52.243-4
“" *45 48 C.F.R. § 52.243-4 (e). The references in the regulation to "Contractor," "Contracting Officer," and "Government" make clear that the Changes Clause concerns a change to the prime contract, that is, the agreement the between the prime contractor and the United States.”
Later courts cite it for
“hirani breached the subcontract by refusing to pay acc for the work that it performed.” · 1 citing court

Show all 43 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199220082025

One bar per year. Tallest: 5 cases in 2003. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Fed. Cl.21Fed. Cir.10A.S.B.C.A.310th Cir.2D.C. Cir.24th Cir.1D.D.C.1D. Md.1

The 8 courts with the most citing cases, of 10 courts in all.

By subsection
(d)1 case
Meridian Eng'g Co. v. United States, 130 Fed. Cl. 147 (Fed. Cl. 2016).“See 48 CF.R. 52.243-4(d). Adjustments under the Suspension Clause, however, exclude profit.”

Show all 43 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com