48 C.F.R. § 52.243-6

52.243-6 Change Order Accounting.

Read at: eCFRecfr.gov CornellLII GovInfogovinfo.gov CasesGoogle Scholar

As prescribed in 43.205(f), the contracting officer may insert a clause, substantially the same as follows:

Change Order Accounting (APR 1984)

The Contracting Officer may require change order accounting whenever the estimated cost of a change or series of related changes exceeds $100,000. The Contractor, for each change or series of related changes, shall maintain separate accounts, by job order or other suitable accounting procedure, of all incurred segregable, direct costs (less allocable credits) of work, both changed and not changed, allocable to the change. The Contractor shall maintain such accounts until the parties agree to an equitable adjustment for the changes ordered by the Contracting Officer or the matter is conclusively disposed of in accordance with the Disputes clause.

(End of clause) [48 FR 42478, Sept. 19, 1983, as amended at 54 FR 29297, July 11, 1989; 56 FR 15156, Apr. 15, 1991]
Notes of Decisions
Cited in 1 case, 2016–2016 · leading case: East Coast Repair & Fabrication, LLC v. United States, 199 F. Supp. 3d 1006 (E.D. Va. 2016).
East Coast Repair & Fabrication, LLC v. United States, 199 F. Supp. 3d 1006 (E.D. Va. 2016). “243-6, available at 48 C.F.R, § 52.243-6. While such Contract clause clearly requires ECR to segregate and track costs when requested by the Government, no such request was made by the Government in this case with the exception of the implementation of the Heavy Weather Plan…”