Skip to main content
C.F.R.Title 48Chapter 1—Federal Acquisition RegulationSubchapter H—Clauses and FormsPart 52—Solicitation Provisions and Contract ClausesSubpart 52.2—Text of Provisions and Clauses

48 C.F.R. § 52.246-12 (2026)

52.246-12 Inspection of Construction.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1993–2009 12citing cases
At a glance

Courts have cited this section in 12 opinions since 1993.

As prescribed in 46.312, insert the following clause:

Inspection of Construction (AUG 1996)

(a) Definition. Work includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.

(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.

(c) Government inspections and tests are for the sole benefit of the Government and do not—

(1) Relieve the Contractor of responsibility for providing adequate quality control measures;

(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;

(3) Constitute or imply acceptance; or

(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) below.

(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer's written authorization.

(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.

(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.

(g) If the Contractor does not promptly replace or correct rejected work, the Government may (1) by contract or otherwise, replace or correct the work and charge the cost to the Contractor or (2) terminate for default the Contractor's right to proceed.

(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.

(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.

(End of clause) [48 FR 42478, Sept. 19, 1983, as amended at 51 FR 27120, July 29, 1986; 60 FR 34762, July 3, 1995; 61 FR 31665, June 20, 1996]
The 11 cases that cite 48 C.F.R. § 52.246-12 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENBlinderman Constr. Co. v. United States, 39 Fed. Cl. 529 (Fed. Cl. 1997).
cites § 52.246-12 5×cited by 23 cases
Later courts cite it for
“the only way to accurately assess the effect of the delays alleged ... on the ... project's progress is to contrast updated cpm schedules prepared immediately before and immediately after each purported delay.” · 2 citing courts
2
GREENNeal & Co. v. United States, 36 Fed. Cl. 600 (Fed. Cl. 1996).
cites § 52.246-12 1×cited by 32 cases
The case’s holding
A contractor's unreasonable-bid or bad-faith claim fails unless the agency's conduct rises to bad faith, and claims are judged by information available to bidders at bidding time.
Later courts cite it for
“inappropriate and unprofessional” · 2 citing courts
3
GREENTravelers Cas. & Sur. of Am. v. United States, 74 Fed. Cl. 75 (Fed. Cl. 2006).
cites § 52.246-12 2×cited by 4 cases
Where it cites § 52.246-12
“Among the clauses incorporated by reference into the contract was the “Inspection of Construction” clause of the FAR, 48 C.F.R. § 52.246-12 . See Ex. 2 (Solicitation § E.”
4
GREENUnited States Fire Ins. v. United States, 78 Fed. Cl. 308 (Fed. Cl. 2007).
cites § 52.246-12 2×cited by 4 cases
Where it cites § 52.246-12
“” 48 C.F.R. § 52.246-12 (b) (Oct. 1,1995). FAR provision 52.236-6 (April 1984), titled “Superintendence by the Contractor,” also required TriGems to have a supervisor on the work site at all times to “superintend the work.””
5
GREENS. Comfort Builders, Inc. v. United States, 67 Fed. Cl. 124 (Fed. Cl. 2005).
cites § 52.246-12 1×cited by 9 cases
Where it cites § 52.246-12
“48 C.F.R. § 52.246-12 . The court concludes from the evidence provided, and as admitted to by SCBI’s project superintendent, Curtis Reed, that SCBI failed to adhere to the contract requirements when it provided the AHUs without the required belt guards or interlock switches,…”
6
GREENM.A. DeAtley Constr., Inc. v. United States, 71 Fed. Cl. 370 (Fed. Cl. 2006).
cites § 52.246-12 1×cited by 7 cases
Where it cites § 52.246-12
“(citing the Federal Acquisition Regulation at 48 C.F.R. § 52.246-12 ). In its response, Plaintiff asserts that the Government’s reliance on the Federal Acquisition Regulation is misplaced because that provision applies to corrective work that is necessitated by the contractor’s…”
7
GREENCom. Contractors, Inc. v. United States, 29 Fed. Cl. 654 (Fed. Cl. 1993).
cites § 52.246-12 1×cited by 9 cases
Where it cites § 52.246-12
“The contract documents incorporate FAR 52.246-12 ( 48 C.F.R. § 52.246-12 ) which requires a contractor to maintain an adequate inspection system and to perform such inspections as will insure the work conforms to contract requirements.”
8
GREENKandarge v. United States Dept. of Navy, 849 F. Supp. 304 (D.N.J. 1994).
cites § 52.246-12 1×cited by 4 cases
Where it cites § 52.246-12
“48 C.F.R. § 52.246-12 (c) and (d), incorporated into the contract by reference, provided that Government inspections were solely for its benefit and “the presence or absence of a Government inspector does not relieve the Contractor from any contract requirement .”
9
NO FLAGM.A. Mortenson Co. v. United States, 40 Fed. Cl. 389 (Fed. Cl. 1998).
cites § 52.246-12 2×
Where it cites § 52.246-12
“” 48 C.F.R. § 52.246-12 (a). This clause also provides for replacement or correction, at the contractor’s expense, of work found not to conform to the contract requirements.”
10
NO FLAGBarr ex rel. Barr v. United States, 628 F. Supp. 2d 800 (N.D. Ill. 2009).
cites § 52.246-12 1×
Where it cites § 52.246-12
“48 C.F.R. § 52.246-12 relating to inspection of construction provides that inspections performed by contracting officers are for the government’s own benefit and do not relieve the contractor of responsibility for providing adequate quality control measures.”
11
NO FLAGFleming Steel Co. v. W.M. Schlosser Co., 345 F. App'x 752 (3d Cir. 2009).
cites § 52.246-12 1×unpublished
Where it cites § 52.246-12
“Moreover, the subcontract incorporated 48 C.F.R. § 52.246-12 (Aug.1996), a clause of the Federal Acquisition Regulation governing the inspection of construction, which provides that “Government inspections and tests are for the sole benefit of the Government and do not .”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199320012009

One bar per year. Tallest: 3 cases in 2009. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Fed. Cl.83rd Cir.2N.D. Ill.1D.N.J.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.