C.F.R. homeSearch C.F.R.
C.F.R.Title 48Chapter 1—Federal Acquisition RegulationSubchapter H—Clauses and FormsPart 52—Solicitation Provisions and Contract ClausesSubpart 52.2—Text of Provisions and Clauses

48 C.F.R. § 52.249-10 (2026)

52.249-10 Default (Fixed-Price Construction).

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1993–2025 35citing cases
At a glance

Courts have cited this section in 35 opinions since 1993, 5 of them in the last five years. The most litigated part is subsection (a) (3 cases).

As prescribed in 49.504(c)(1), insert the following clause:

Default (Fixed-Price Construction) (APR 1984)

(a) If the Contractor refuses or fails to prosecute the work or any separable part, with the diligence that will insure its completion within the time specified in this contract including any extension, or fails to complete the work within this time, the Government may, by written notice to the Contractor, terminate the right to proceed with the work (or the separable part of the work) that has been delayed. In this event, the Government may take over the work and complete it by contract or otherwise, and may take possession of and use any materials, appliances, and plant on the work site necessary for completing the work. The Contractor and its sureties shall be liable for any damage to the Government resulting from the Contractor's refusal or failure to complete the work within the specified time, whether or not the Contractor's right to proceed with the work is terminated. This liability includes any increased costs incurred by the Government in completing the work.

(b) The Contractor's right to proceed shall not be terminated nor the Contractor charged with damages under this clause, if—

(1) The delay in completing the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor. Examples of such causes include (i) acts of God or of the public enemy, (ii) acts of the Government in either its sovereign or contractual capacity, (iii) acts of another Contractor in the performance of a contract with the Government, (iv) fires, (v) floods, (vi) epidemics, (vii) quarantine restrictions, (viii) strikes, (ix) freight embargoes, (x) unusually severe weather, or (xi) delays of subcontractors or suppliers at any tier arising from unforeseeable causes beyond the control and without the fault or negligence of both the Contractor and the subcontractors or suppliers; and

(2) The Contractor, within 10 days from the beginning of any delay (unless extended by the Contracting Officer), notifies the Contracting Officer in writing of the causes of delay. The Contracting Officer shall ascertain the facts and the extent of delay. If, in the judgment of the Contracting Officer, the findings of fact warrant such action, the time for completing the work shall be extended. The findings of the Contracting Officer shall be final and conclusive on the parties, but subject to appeal under the Disputes clause.

(c) If, after termination of the Contractor's right to proceed, it is determined that the Contractor was not in default, or that the delay was excusable, the rights and obligations of the parties will be the same as if the termination had been issued for the convenience of the Government.

(d) The rights and remedies of the Government in this clause are in addition to any other rights and remedies provided by law or under this contract.

(End of clause)

Alternate I (APR 1984). If the contract is for dismantling, demolition, or removal of improvements, substitute the following paragraph (a) for paragraph (a) of the basic clause:

(a)(1) If the Contractor refuses or fails to prosecute the work, or any separable part, with the diligence that will insure its completion within the time specified in this contract, including any extension, or fails to complete the work within this time, the Government may, by written notice to the Contractor, terminate the right to proceed with the work or the part of the work that has been delayed. In this event, the Government may take over the work and complete it by contract or otherwise, and may take possession of and use any materials, appliances, and plant on the work site necessary for completing the work.

(2) If title to property is vested in the Contractor under this contract, it shall revest in the Government regardless of any other clause of this contract, except for property that the Contractor has disposed of by bona fide sale or removed from the site.

(3) The Contractor and its sureties shall be liable for any damage to the Government resulting from the Contractor's refusal or failure to complete the work within the specified time, whether or not the Contractor's right to proceed with the work is terminated. This liability includes any increased costs incurred by the Government in completing the work.

Alternate II (APR 1984). If the contract is to be awarded during a period of national emergency, subparagraph (b)(1) below may be substituted for subparagraph (b)(1) of the basic clause:

(1) The delay in completing the work arises from causes other than normal weather beyond the control and without the fault or negligence of the Contractor. Examples of such causes include (i) acts of God or of the public enemy, (ii) acts of the Government in either its sovereign or contractual capacity, (iii) acts of another Contractor in the performance of a contract with the Government, (iv) fires, (v) floods, (vi) epidemics, (vii) quarantine restrictions, (viii) strikes, (ix) freight embargoes, (x) unusually severe weather, or (xi) delays of subcontractors or suppliers at any tier arising from causes other than normal weather beyond the control and without the fault or negligence of both the Contractor and the subcontractors or suppliers; and

Alternate III (APR 1984). If the contract is for dismantling, demolition, or removal of improvements and is to be awarded during a period of national emergency, substitute the following paragraph (a) for paragraph (a) of the basic clause. The following subparagraph (b)(1) may be substituted for subparagraph (b)(1) of the basic clause:

(a)(1) If the Contractor refuses or fails to prosecute the work, or any separable part, with the diligence that will insure its completion within the time specified in this contract, including any extension, or fails to complete the work within this time, the Government may, by written notice to the Contractor, terminate the right to proceed with the work or the part of the work that has been delayed. In this event, the Government may take over the work and complete it by contract or otherwise, and may take possession of and use any materials, appliances, and plant on the work site necessary for completing the work.

(2) If title to property is vested in the Contractor under this contract, it shall revest in the Government regardless of any other clause of this contract, except for property that the Contractor has disposed of by bona fide sale or removed from the site.

(3) The Contractor and its sureties shall be liable for any damage to the Government resulting from the Contractor's refusal or failure to complete the work within the specified time, whether or not the Contractor's right to proceed with the work is terminated. This liability includes any increased costs incurred by the Government in completing the work.

(b) The Contractor's right to proceed shall not be terminated nor the Contractor charged with damages under this this clause, if—

(1) The delay in completing the work arises from causes other than normal weather beyond the control and without the fault or negligence of the Contractor. Examples of such causes include (i) acts of God or of the public enemy, (ii) acts of the Government in either its sovereign or contractual capacity, (iii) acts of another Contractor in the performance of a contract with the Government, (iv) fires, (v) floods, (vi) epidemics, (vii) quarantine restrictions, (viii) strikes, (ix) freight embargoes, (x) unusually severe weather, or (xi) delays of subcontractors or suppliers at any tier arising from causes other than normal weather beyond the control and without the fault or negligence of both the Contractor and the subcontractors or suppliers; and

[48 FR 42478, Sept. 19, 1983, as amended at 60 FR 34762, July 3, 1995]
The 20 cases that cite 48 C.F.R. § 52.249-10 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENZafer Taahhut Insaat Ve Ticaret A.S. v. United States, 833 F.3d 1356 (Fed. Cir. 2016).
cites § 52.249-10 2×cited by 39 cases
Where it cites § 52.249-10
“48 C.F.R. § 52.249-10 (b) (2007). In June 2011, Zafer received a notice to proceed with the contract, with a contract completion date in November 2012.”
The case’s holding
A constructive acceleration claim requires a timely extension request that the government denies, and the government is not liable for the sovereign acts of a foreign nation.
Later courts cite it for
“constructive acceleration often occurs when the government demands compliance with an original contract deadline, despite excusable delay by the contractor.” · 3 citing courts
2
GREENUnified Contractor, Inc. v. Albuquerque Hous. Auth., 2017-NMCA-060, 400 P.3d 290.
cites § 52.249-10 2×subsections: (a)cited by 25 cases
Where it cites § 52.249-10
“2000) (holding that federal acquisition requirement (FAR) 48 C.F.R. Section 52.249-10 “does not require that a contractor be afforded a period in which to cure defects before a contract is terminated for default”);4 Bruner & O’Connor, supra at § 18:37 (“[T]he absence of an…”
3
GREENAllen Eng'g Contractor Inc. v. United States, 123 Fed. Cl. 701 (Fed. Cir. 2015).
cites § 52.249-10 6×cited by 9 casesunpublished
Where it cites § 52.249-10
“This was a material breach of AECI’s agreement with the Navy, and the Navy appropriately terminated the contracts under 48 C.F.R. § 52.249-10 (a). A contractor on a construction project worth more than $150,000 is required to *704 post and maintain performance and payment bonds…”
Later courts cite it for
“as a general matter, government contracting officers have 'broad discretion to determine whether to terminate a contract for default.” · 4 citing courts
4
GREENRda Constr. Corp. v. United States, 132 Fed. Cl. 732 (Fed. Cl. 2017).
cites § 52.249-10 3×cited by 10 cases
Where it cites § 52.249-10
“” DX 1 at 15 (incorporating 48 C.F.R. § 52.249-10 (e)), Therefore, if the Contractor was not in default, or the default was excusable, the Government cannot recover liquidated damages under FAR 52.”
Later courts cite it for
“gave in to pressure from other government officials to abdicate his responsibility to be impartial and agreed to support contract interpretations made by officials, who were openly contemptuous of the contractor.” · 2 citing courts
cites § 52.249-10 2×cited by 39 cases
Where it cites § 52.249-10
“48 C.F.R. § 52.249-10 (a), (c). That clause is part of the Federal Acquisition Regulation System (“FAR”).”
The case’s holding
A district court possesses discretion in awarding prejudgment interest, though such awards must comply with stipulations regarding the accrual of damages.
Later courts cite it for
“an award of prejudgment interest is within the district court's discretion.” · 4 citing courts
6
GREENMorrison Knudsen Corp. v. Fireman's Fund Ins., 175 F.3d 1221 (10th Cir. 1999).
cites § 52.249-10 2×cited by 104 cases
Where it cites § 52.249-10
“See 48 C.F.R. § 52.249-10 (1997). That clause is part of the Federal Acquisition Regulation System (FAR).”
The case’s holding
An appellant's failure to provide a necessary transcript to demonstrate prejudice from an instructional error requires affirmance of the judgment below.
Later courts cite it for
“our concern is to ensure that our review does not leave us with substantial doubt whether the instructions, considered as a whole, properly guided the jury in its deliberations.” · 7 citing courts
7
GREENAllen Eng'g Contractor, Inc. v. United States, 115 Fed. Cl. 457 (Fed. Cl. 2014).
cites § 52.249-10 4×subsections: (a)cited by 10 cases
Where it cites § 52.249-10
“, ¶¶ 24 and 27; (5) the Navy improperly terminated the contract because 48 C.F.R. § 52.249-10 does not permit termination for failure to provide replacement bonds, see id.”
8
GREENEnron Fed. Solutions, Inc. v. United States, 80 Fed. Cl. 382 (Fed. Cl. 2008).
cites § 52.249-10 2×cited by 27 cases
Where it cites § 52.249-10
“249-8 ) also allegedly incorporated into the Contract; and (3) by operation of the FAR construction provisions, including the Default Clause ( 48 C.F.R. § 52.249-10 ), which EFSI claims must be incorporated into the Contract through invocation of the Christian doctrine.”
The case’s holding
Courts interpret a government contract by starting with its plain text, read as a whole in context, and a provision is not ambiguous merely because the parties disagree about it.
Later courts cite it for
“context defines a contract and the issues deriving thereof.” · 10 citing courts
9
GREENPCL Constr. Servs., Inc. v. United States, 47 Fed. Cl. 745 (Fed. Cl. 2000).
cites § 52.249-10 2×cited by 43 cases
The case’s holding
A cardinal change claim requires evidence that government-directed work exceeds both the general scope of the contract and the scope of the contract's changes clause.
Later courts cite it for
“courts must look beyond simple arithmetic when assessing a cardinal change claim.” · 2 citing courts
10
GREENR.P. Wallace, Inc. v. United States, 63 Fed. Cl. 402 (Fed. Cl. 2004).
cites § 52.249-10 2×cited by 15 cases
Where it cites § 52.249-10
“” 48 C.F.R. § 52.249-10 (b)(1). These salvific provisions, however, are triggered only if “[t]he Contractor, within 10 days from the beginning of any delay (unless extended by the Contracting Officer), notifies the Contracting Officer in writing of the causes of delay.”
11
GREENTransfair Int'l, Inc. v. United States, 54 Fed. Cl. 78 (Fed. Cl. 2002).
cites § 52.249-10 2×cited by 9 cases
Where it cites § 52.249-10
“” Any notion, however, that this language was intended to establish a broad general rule of attribution is foreclosed not only by its context, but also by the next sentence of the opinion, which, in language defendant did not trouble to quote, states that the subcontractor’s…”
12
GREENSauer Inc. v. Richard J. Danzig, 224 F.3d 1340 (Fed. Cir. 2000).
cites § 52.249-10 1×cited by 75 cases
Where it cites § 52.249-10
“To establish entitlement to an extension based on excusable delay, Sauer must show that the delay resulted from “unforeseeable causes beyond the control and without the fault or negligence of the Contractor.”
The case’s holding
A party asserting that liquidated damages were improperly assessed bears the burden of proving the extent of the excusable delay caused by unforeseeable factors beyond its control.
Later courts cite it for
“as a general rule, a party asserting that liquidated damages were improperly assessed bears the burden of showing the extent of the excusable delay to which it is entitled.” · 10 citing courts
13
GREENCJP Contractors, Inc. v. United States, 45 Fed. Cl. 343 (Fed. Cl. 1999).
cites § 52.249-10 2×cited by 17 cases
Where it cites § 52.249-10
“48 C.F.R. § 52.249-10 (1984). Although the government may charge the defaulted contractor with the excess costs of reprocurement under this *383 clause, the government must prove the reasonableness of the costs.”
Later courts cite it for
“unforeseeable causes beyond the control and without the fault or negligence of the contractor.” · 2 citing courts
14
GREENH.T. Johnson v. All-State Constr., Inc., 329 F.3d 848 (Fed. Cir. 2003).
cites § 52.249-10 1×cited by 21 cases
Where it cites § 52.249-10
“48 C.F.R. § 52.249-10 (1984). There is no regulation, however, permitting the government to withhold progress payments when the government is considering declaring a default termination.”
15
GREENDecker & Co. v. Togo D. West, 76 F.3d 1573 (Fed. Cir. 1996).
cites § 52.249-10 1×cited by 41 cases
Where it cites § 52.249-10
“ors or suppliers at any tier arising from unforeseeable causes beyond the control and without the fault or negligence of both the Contractor and the subcontractors or suppliers; and (2) The Contractor, within 10 days from the beginning of any delay (unless extended by the…”
The case’s holding
A contractor must demonstrate that incorrect appeal advice actually prejudiced its ability to prosecute a timely appeal before the limitation period is held not to have begun.
Later courts cite it for
“a contractor in decker's position must demonstrate that incorrect appeal advice actually prejudiced its ability to prosecute its timely appeal before the limitation period will be held not to have begun.” · 2 citing courts
16
GREENTransp. v. Eagle Peak Rock & Paving, Inc., 69 F.4th 1367 (Fed. Cir. 2023).
cites § 52.249-10 1×cited by 7 cases
Where it cites § 52.249-10
“249-10, 48 C.F.R. § 52.249-10 . Eagle Peak, CBCA 5692, at 3; J.”
Later courts cite it for
“when a contracting officer terminates a contract for default, and the contractor appeals that termination decision, 'the government . . . bears the burden of proof with respect to the issue of whether termination for default was justified.” · 3 citing courts
17
GREENEmiabata v. United States, 102 Fed. Cl. 787 (Fed. Cl. 2012).
cites § 52.249-10 1×cited by 4 cases
Where it cites § 52.249-10
“That clause gives the CO the right to terminate a contract for default if the contractor “refuses or fails to prosecute the work or any separable part, with the diligence that will insure its completion within the time specified in [the] contract including any extension, or…”
18
GREENRice Lake Contracting, Inc. v. United States, 33 Fed. Cl. 144 (Fed. Cl. 1995).
cites § 52.249-10 1×cited by 6 cases
Where it cites § 52.249-10
“[ 7 ] The contract also contained clause 73, “Termination for Convenience of the Government,” pursuant to 48 C.F.R. 52.249-10 (1986). *148 Under the contract, the government was to order services by means of delivery orders.”
19
GREENHVAC Constr. Co. v. United States, 28 Fed. Cl. 690 (Fed. Cl. 1993).
cites § 52.249-10 1×cited by 4 cases
Where it cites § 52.249-10
“In sum, the situation leading to the work stoppage was of plaintiff’s making, not defendant’s. Therefore, plaintiff is not entitled to an equitable adjustment for costs incurred as a consequence of the work stoppage.”
20
GREENGilbane Fed. v. United Infrastructure Projects FZCO, 275 F. Supp. 3d 1180 (N.D. Cal. 2017).
cites § 52.249-10 1×cited by 1 case
Where it cites § 52.249-10
“See 48 C.F.R. § 52.249-10 . 2. Gilbane bears the burden of proving that termination was justified by a preponderance of the evidence.”

Show all 35 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199320092025

One bar per year. Tallest: 3 cases in 2000. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Fed. Cl.16Fed. Cir.11A.S.B.C.A.210th Cir.29th Cir.1N.D. Cal.1N.M. Ct. App.1D.N.M.1
By subsection
(a)3 cases
Unified Contractor, Inc. v. Albuquerque Hous. Auth., 2017-NMCA-060, 400 P.3d 290.“2000) (holding that federal acquisition requirement (FAR) 48 C.F.R. Section 52.249-10 “does not require that a contractor be afforded a period in which to cure defects before a contract is terminated for default”);4 Bruner & O’Connor, supra at § 18:37 (“[T]he absence of an…”
Allen Eng'g Contractor, Inc. v. United States, 115 Fed. Cl. 457 (Fed. Cl. 2014).“, ¶¶ 24 and 27; (5) the Navy improperly terminated the contract because 48 C.F.R. § 52.249-10 does not permit termination for failure to provide replacement bonds, see id.”
Cumberland Cas. & Sur. Co. v. United States, 82 Fed. Cl. 500 (Fed. Cl. 2008).

Show all 35 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com