Your Trusted Partner in Personal Injury & Workers' Compensation
Call Now: 904-383-7448
(Code 1981, §10-7-31, enacted by Ga. L. 1994, p. 870, § 1.)
- For survey article on construction law, see 59 Mercer L. Rev. 55 (2007).
- Construing the pleadings in a light most favorable to showing a question of fact in an action in which: (1) the pleadings did not disclose with certainty that a supplier would not be entitled to relief in the supplier's action against a general contractor and the contractor's surety; and (2) the appeals court did not consider the supplier's averments that the supplier's "Notice to Owner/Contractor" complied with O.C.G.A. §§ 10-7-31 and44-14-361.5 or its admission that it received a copy of the notice of commencement to establish that the general contractor's notice of commencement was otherwise proper and timely filed as required by the statutes, the general contractor and the contractor's surety were not entitled to judgment on the pleadings. Consol. Pipe & Supply Co. v. Genoa Constr. Servs., Inc., 279 Ga. App. 894, 633 S.E.2d 59 (2006).
- In the general contractor's action against the materials provider relating to the provider's request for payment under a payment bond, the trial court erred by declaring that the payment bond obtained and recorded by the general contractor served as substituted collateral for the construction project and in discharging the materialmen's lien filed by the provider; O.C.G.A. § 10-7-31 was silent on the issue of how or whether the bond affected materialmen's liens, and, under O.C.G.A. § 44-14-364(a), the bond did not satisfy the essential requirements of a lien release bond since the bond was obtained before the provider filed its lien claim and there was nothing indicating that the bond was issued with good security approved by the clerk. Sierra Craft, Inc. v. T. D. Farrell Constr., Inc., 282 Ga. App. 377, 638 S.E.2d 815 (2006), cert. denied, No. S07C0460, 2007 Ga. LEXIS 145 (Ga. 2007).
- In the general contractor's action against the materials provider relating to the provider's request for payment under a payment bond, the general contractor's notice of commencement and the provider's notice to contractor complied with O.C.G.A. § 10-7-31; although the notice of commencement stated that the notice was pursuant to O.C.G.A. § 44-14-361.5 and the notice to contractor stated that the notice was sent under O.C.G.A. § 44-14-361, O.C.G.A. § 10-7-31 did not require that either of the notices be expressly labeled as being provided under the statute, the notices contained the pertinent information contemplated by O.C.G.A. § 10-7-31, including that the general contractor had provided a payment bond and that the provider had provided materials for the project through improvements made by the subcontractor, and the notice of commencement was not misfiled under O.C.G.A. § 10-7-31(d) because it was labeled as provided under O.C.G.A. § 44-14-361.5 as the indexing requirements of both statutes were substantially identical. Sierra Craft, Inc. v. T. D. Farrell Constr., Inc., 282 Ga. App. 377, 638 S.E.2d 815 (2006), cert. denied, No. S07C0460, 2007 Ga. LEXIS 145 (Ga. 2007).
- Trial court did not err in granting a general contractor and its surety summary judgment in a supplier's action to recover under a payment bond and a lien discharge bond for monies a subcontractor owed it for materials it supplied to a construction project because the supplier's notice to contractor failed to comply with O.C.G.A. §§ 10-7-31(a) and44-14-361.5(c) because the notice wholly omitted required information; although the supplier's notice to contractor set forth the subcontractor's name, it failed to provide any address for the subcontractor as required under §§ 10-7-31(a)(2) and44-14-361.5(c)(2), and although the notice set forth the name of the project, it failed to state the location of the construction project pursuant to §§ 10-7-31(a)(3) and44-14-361.5(c)(3). Consol. Pipe & Supply Co. v. Genoa Constr. Servs., 302 Ga. App. 255, 690 S.E.2d 894 (2010).
- Although the materials provider, in seeking payment under a payment bond, incorrectly stated in the notice to contractor that the contract price for its provision of materials was $20,000, it was not limited to recovery of that amount. O.C.G.A. § 10-7-31(a)(4), dictating the contents of a notice to contractor, did not limit the future claims of a notifying supplier. Sierra Craft, Inc. v. T. D. Farrell Constr., Inc., 282 Ga. App. 377, 638 S.E.2d 815 (2006), cert. denied, No. S07C0460, 2007 Ga. LEXIS 145 (Ga. 2007).
No results found for Georgia Code 10-7-31.