Idaho Code homeSearch Idaho

Idaho Code § 45-512 (2026)

Judgment to declare priority. 

Edition and currency
text as last checked Oct. 2026 (this copy records no edition or section history). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTtext as last checked Oct. 2026 (this copy records no edition or section history) cited 1972–2005 5citing cases
At a glance

Courts have cited this section in 5 opinions since 1972.

Judgment to declare priority. 

In every case in which different liens are asserted against any property, the court in the judgment must declare the rank of each lien or class of liens which shall be in the following order:

1.  All laborers, other than contractors or subcontractors.
2.  All materialmen including persons furnishing, renting or leasing equipment, materials or fixtures as defined in section 28-12-309, Idaho Code, other than contractors or subcontractors.
3.  Subcontractors.
4.  The original contractor.
5.  All professional engineers and licensed surveyors.
And in case the proceeds of sale under this chapter shall be insufficient to pay all lienholders under it:
1.  The liens of all laborers, other than the original contractor and subcontractor, shall first be paid in full, or pro rata if the proceeds be insufficient to pay them in full.
2.  The lien of materialmen including persons furnishing, renting or leasing equipment, materials or fixtures as defined in section 28-12-309, Idaho Code, other than the original contractor or subcontractor, shall be paid in full, or pro rata if the proceeds be insufficient to pay them in full.
3.  Out of the remainder, if any, the subcontractors shall be paid in full, or pro rata if the remainder be insufficient to pay them in full, and the remainder, if any, shall be paid pro rata to the original contractor and the professional engineers and licensed surveyors; and each claimant shall be entitled to execution for any balance due him after such distribution; such execution to be issued by the clerk of the court upon demand, at the return of the sheriff or other officer making the sale, showing such balance due.
The 5 cases that cite Idaho Code § 45-512 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENBouten Constr. Co. v. H.F. Magnuson Co., 992 P.2d 751 (Idaho 1999).
cites § 45-512 14×cited by 64 cases
Where it cites § 45-512
“Thus, following remand, the district court had a statutory duty to establish both the mechanics lien priorities and the mortgage lien priorities.”
The case’s holding
Prejudgment interest is unavailable when damages are not readily ascertainable prior to the proceedings on remand.
Later courts cite it for
“when damages are not readily 'ascertainable prior to the proceedings on remand,' they are not liquidated.” · 1 citing court
2
GREENPierson v. Sewell, 539 P.2d 590 (Idaho 1975).
cites § 45-512 20×cited by 49 cases
Where it cites § 45-512
“Eastern Idaho Packing Corporation, [18] the relevant provisions of I.C. § 45-512 [19] were interpreted as allowing a lien claimant to treat that portion of the claim which remains unsatisfied after distribution of the proceeds of the foreclosure sale as a personal judgment…”
The case’s holding
Mechanic's lien statutes operate in rem and do not create a personal charge against a property owner in the absence of a direct contractual relationship.
Later courts cite it for
“the purpose of these statutes is to compensate persons who perform labor upon or furnish material to be used in the construction, alteration or repair of a building or structure.” · 2 citing courts
3
GREENUltrawall, Inc. v. Washington Mut. Bank, 25 P.3d 855 (Idaho 2001).
cites § 45-512 8×cited by 8 cases
Where it cites § 45-512
“Then, if the value of the project is insufficient to pay all the lien claimants, those claimants are paid according to their rank under I.C. § 45-512. 2 Thus, either all of the lien claimants are paid ahead of the construction lender, or none are, depending on whether the…”
Later courts cite it for
“the court must assume that when the statute was amended, the legislature had full knowledge of the existing judicial decisions and caselaw of the state.” · 2 citing courts
4
YELLOWWeber v. E. Idaho Packing Corp., 496 P.2d 693 (Idaho 1972).
cites § 45-512 2×cited by 14 cases
Overruled by Pierson v. Sewell on other grounds: 2 citing opinions limit it to other grounds.
Where it cites § 45-512
“Out of the remainder, if any, the subcontractors shall be paid in full, or pro rata if the remainder be insufficient to pay them in full, and the remainder, if any, shall be paid to the original contractor ; and each claimant shall be entitled to execution for any balance due…”
5
GREENIn re Thames, 349 B.R. 659 (Bankr. D. Idaho 2005).
cites § 45-512 4×cited by 1 case
Where it cites § 45-512
“The determination of the lien’s priority is required in a mechanic's lien foreclosure action by Idaho Code § 45-512 . Where differ *667 ent liens for the recovery of labor and materials are asserted against real property, the judgment must declare the rank of each lien, with the…”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
197219882005

One bar per year. Tallest: 1 case in 1972. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Idaho4Bankr. D. Idaho1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: text as last checked Oct. 2026 (this copy records no edition or section history). Syfert holds no earlier or later version of this section.

Idaho Code Home  |  Search Idaho  |  Search cases for this section  |  syfert.com