Massachusetts General Laws homeSearch Massachusetts
Mass. Gen. LawsPart III Title IV Chapter 254

Mass. Gen. Laws ch. 254, § 8 (2026)

Statement of amount due; time for filing; dissolution of lien

Edition and currency
text as last checked Sept. 2026 (this copy records no edition or section history). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTtext as last checked Sept. 2026 (this copy records no edition or section history) cited 1928–2018 39citing cases
At a glance

Courts have cited this section in 39 opinions since 1928. The most litigated part is subsection (iii) (1 case).

Section 8. Liens under sections two and four shall be dissolved unless the contractor, subcontractor, or some person claiming by, through or under them, shall, not later than the earliest of: (i) ninety days after the filing or recording of the notice of substantial completion under section two A; (ii) one hundred and twenty days after the filing or recording of the notice of termination under section two B; or (iii) one hundred and twenty days after the last day a person, entitled to enforce a lien under section two or anyone claiming by, through or under him, performed or furnished labor or material or both labor and materials or furnished rental equipment, appliances or tools, file or record in the registry of deeds in the county or district where the land lies a statement, giving a just and true account of the amount due or to become due him, with all just credits, a brief description of the property, and the names of the owners set forth in the notice of contract. Liens under sections 2C and 2D shall be dissolved unless a like statement is filed or recorded at the appropriate registry of deeds within 30 days after the last day that a notice of contract may be filed or recorded under the applicable section. A lien under section one shall be dissolved unless a like statement, giving the names of the owner of record at the time the work was performed or at the time of filing the statement, is filed or recorded in the appropriate registry of deeds within the ninety days provided in said section. Nothing in this section shall prohibit the filing or recording of a statement under this section prior to the filing or recording of the notices under section two A or two B.

The 20 cases that cite Mass. Gen. Laws ch. 254, § 8 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENMullen Lumber Co. v. Lore, 537 N.E.2d 123 (Mass. 1989).
cites § 8 4×cited by 25 cases
Where it cites § 8
“12, and the supplies provided as required by G.L.c. 254, § 8, in order to preserve the mechanic's lien on the property.”
Later courts cite it for
“the mechanic's lien statute comprises a comprehensive scheme which compels strict compliance in order to obtain relief.” · 3 citing courts
2
GREENNat'l Lumber Co. v. LeFrancois Constr. Corp., 723 N.E.2d 10 (Mass. 2000).
cites § 8 3×cited by 36 cases
Where it cites § 8
“Pursuant to G. L. c. 254, § 8, National Lumber had thirty days (until December 31, 1995) within which to file any statement of account without which its hen would dissolve.”
The case’s holding
A mechanic's lien is an encumbrance on real property, and a purchaser taking title after the lien is recorded takes subject to it, with notice of the lien.
Later courts cite it for
“massachusetts practice is more liberal than other jurisdictions in allowing amendments adding or substituting defendants after expiration of a period of limitations” · 3 citing courts
3
GREENNg Bros. Constr. v. Cranney, 766 N.E.2d 864 (Mass. 2002).
cites § 8 1×cited by 152 cases
Where it cites § 8
“Nevertheless, on January 9, 1998, the plaintiff recorded a statement of account pursuant to G. L. c. 254, § 8. 4 On January 26, 1998, the parties sought to settle some of their differences by agreeing to a partial release, and on January 29, the plaintiff filed a notice of…”
The case’s holding
A notice of substantial completion is not a prerequisite to perfecting a mechanic's lien under the applicable statute.
Later courts cite it for
“summary judgment is granted where there are no issues of genuine material fact, and the moving party is entitled to judgment as a matter of law.” · 8 citing courts
4
GREENO. Ahlborg & Sons, Inc. v. United States, 74 Fed. Cl. 178 (Fed. Cl. 2006).
cites § 8 3×cited by 12 cases
Where it cites § 8
“MHI and MAR-AD still refused to release the payment from the Escrow Fund, claiming that Ahlborg had not paid its subcontractors. Harrington Aff. 1112. On September 10, 1999, Ahlborg recorded a “statement of account on the property” for unpaid Requisition No.”
Later courts cite it for
“the third-party beneficiary exception exists to cover situations in which the subcontractor 'stands in the shoes of a party with privity.” · 5 citing courts
5
GREENGolden v. Gen. Builders Supply LLC, 807 N.E.2d 822 (Mass. 2004).
cites § 8 2×cited by 18 cases
Where it cites § 8
“59 for the materials furnished to Golden’s property, see G. L. c. 254, § 8. 1 Unable to resolve General Builders’s claim, Golden filed a complaint in the Superior Court on August 24, 2001, alleging various defects in General Builders’s ostensible mechanic’s hen, and seeking to…”
Later courts cite it for
“because a mechanic's lien is purely a creation of statute, we have consistently required exact compliance with the statute in order to create, perfect, and enforce such a lien.” · 3 citing courts
6
GREENNES Rentals v. Maine Drilling & Blasting, Inc., 992 N.E.2d 291 (Mass. 2013).
cites § 8 2×cited by 10 cases
Where it cites § 8
“*858 On April 26, 2010, NES Rentals perfected a mechanic’s lien on the Berkshire Wind property by recording a notice of its contract with McManus, as required by § 4, 3 and a sworn statement of account that claimed $89,101 as the amount due for the rental equipment, as required…”
cites § 8 1×cited by 78 cases
Where it cites § 8
“10, §§ 3253, 3255; Mass.Gen.L. ch. 254, §§ 8, 11; N.H.Rev.Stat.”
The case’s holding
A federal statute authorizing the filing of a lien on property without a pre-deprivation hearing violates the Due Process Clause of the Fifth Amendment.
Later courts cite it for
“merits of any particular removal or remedial action” · 2 citing courts
8
GREENNat'l Lumber Co. v. United Cas. & Sur. Ins., 802 N.E.2d 82 (Mass. 2004).
cites § 8 1×cited by 27 cases
Where it cites § 8
“G. L. c. 254, § 8 (recorded, sworn statement of claim must state *729 “a just and trac account of the amount due him”).”
The case’s holding
A mechanic's lien recorded under the mechanic's lien statute secures only the amount due for labor and materials, not contractual interest or reasonable attorney's fees.
Later courts cite it for
“olur inquiry is limited to whether a mechanic's lien recorded pursuant to the mechanics' lien statute, includes contractual interest and reasonable attorney's fees in addition to the amount claimed for labor and materials we conclude that it does not.” · 1 citing court
9
cites § 8 1×cited by 23 cases
Where it cites § 8
“254, § 4 (notice of contract requirement for subcontractors); G. L. c. 254, § 8 (statement of account for all mechanic’s liens).”
Later courts cite it for
“as a general matter, a lien on a leasehold is extinguished when the rights of the lessee expire” · 3 citing courts
cites § 8 5×cited by 2 cases
Where it cites § 8
“” G.L.c. 254, §8 (footnote added). The Plaintiffs were the proper parties to file the Lien as the Union is the agent of the workers who performed the labor, and the Trustees are the workers’ third-party beneficiaries to whom B&M was to pay amounts for allocation to certain…”
11
cites § 8 1×cited by 20 cases
Where it cites § 8
“G. L. c. 254, § 8. That statement of account must be filed within ninety days of the fifing of a notice of substantial completion; within 120 days of the fifing of a notice of termination; or within 120 days after the contractor last performed or furnished labor, materials, *681…”
Later courts cite it for
“has a statutory right to ... a lien- ... the lien itself does not exist until the contractor does something to assert that right.” · 2 citing courts
12
GREENEast Coast Steel Erectors, Inc. v. Ciolfi, 632 N.E.2d 397 (Mass. 1994).
cites § 8 1×cited by 18 cases
Where it cites § 8
“The judge ruled that the lien dissolved under G. L. c. 254, § 8, because East Coast had failed to file its statement of account within thirty days of the completion date specified in its notice of contract.”
Later courts cite it for
“by strict compliance with the statutory specifications” · 2 citing courts
13
GREENJohn Marini Mgmt. Co. v. Butler, 873 N.E.2d 1150 (Mass. App. Ct. 2007).
cites § 8 2×cited by 3 cases
Where it cites § 8
“Unless an enforcement action is brought in the Superior Court within ninety days after the filing of the statement of amount required by G. L. c. 254, § 8, the lien is dissolved.”
14
GREENVolpe Constr. Co. v. First Nat'l Bank, 567 N.E.2d 1244 (Mass. App. Ct. 1991).
cites § 8 1×cited by 15 cases
Where it cites § 8
“Thus the “statement of account,” to be filed within thirty days after the *255 completion date, see G. L. c. 254, § 8, was not in fact filed until September 17, 1986, well beyond the measuring period of thirty days from June 2, 1986.”
Later courts cite it for
“it is plain that, 'if two contracting parties expressly provide that some third party who will be benefited by performance shall have no legally enforceable right, the courts should effectuate the expressed intent by denying the party any direct remedy” · 5 citing courts
15
GREENBlount Bros. Corp. v. Lafayette Place Assocs., 506 N.E.2d 499 (Mass. 1987).
cites § 8 1×cited by 15 cases
Where it cites § 8
“” 3 On April 19, 1985, Blount filed a statement of account, pursuant to G. L. c. 254, § 8, in which it claimed a total lien in the amount of $15,329,379.”
Later courts cite it for
“shall be dissolved unless the sub-contractor . . . files a statement of account within thirty days after the date on which the contract of said sub-contractor is to be performed.” · 1 citing court
cites § 8 1×cited by 5 cases
Where it cites § 8
“Mass. Gen. Laws ch. 254, § 8 provides in pertinent part Liens under sections two and four shall be dissolved unless the contractor, subcontractor, or some person claiming by, through or under them, shall, not later than the earliest of: (i) ninety days after the filing or…”
cites § 8 1×cited by 8 cases
Where it cites § 8
“Contrast G. L. c. 254, § 8 (mechanics’ lien statement to be filed within thirty days after the date on which the contract “is to be performed”).”
18
GREENBlount Bros. v. Mondev Mass., Inc., 491 N.E.2d 640 (Mass. App. Ct. 1986).
cites § 8 2×cited by 3 cases
Where it cites § 8
“” G. L. c. 254, § 8. The lien is dissolved unless a timely statement of account is filed.”
19
GREENInterstate Elec. Servs. Corp. v. Cummings Props., LLC, 825 N.E.2d 1059 (Mass. App. Ct. 2005).
cites § 8 1×cited by 3 cases
Where it cites § 8
“Insofar as the October 20 contract is concerned, there is no dispute that, as of December 31, 1999, Interstate had installed the contractually required 1,200-amp circuit breaker, the combination cabinet, the conduit, the ground rods, and the copper wire necessary to supply power…”
20
GREENOueliet v. Armstrong, 18 Mass. L. Rptr. 100 (Mass. Super. Ct. 2004).
cites § 8 2×cited by 1 case
Where it cites § 8
“Moreover, pursuant to G.L.c. 254, §8, a subcontractor is required to record a “statement, giving a just and true account of the amount due .”

Show all 39 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
192819732018

One bar per 2 years. Tallest: 6 cases in 2006–2007. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Mass.12Mass. Super. Ct.9Mass. App. Ct.8Mass. Dist. Ct., App. Div.61st Cir.1Bankr. D. Mass.1D. Mass.1Fed. Cl.1
By subsection
(iii)1 case
NG Bros. Constr. v. Cranney, 12 Mass. L. Rptr. 556 (Mass. Super. Ct. 2000).

Show all 39 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: text as last checked Sept. 2026 (this copy records no edition or section history). Syfert holds no earlier or later version of this section.

Massachusetts General Laws Home  |  Search Massachusetts  |  Search cases for this section  |  syfert.com