CONTRACTOR'S BOND FOR PUBLIC BUILDINGS OR WORKS
Act 213 of 1963
129.203 Payment bond; amount; purpose.
Sec. 3.
The payment bond shall be in an amount fixed by the governmental unit but not less than 25% of the contract amount solely for the protection of claimants, as defined in section 6, supplying labor or materials to the principal contractor or his subcontractors in the prosecution of the work provided for in the contract.
History: 1963, Act 213, Eff. Sept. 6, 1963 ;-- Am. 1972, Act 351, Imd. Eff. Jan. 9, 1973
Notes of Decisions
Wyandotte Elec. Supply Co. v. Elec. Tech. Sys., Inc., 881 N.W.2d 95 (Mich. 2016).
· cites it 16× “MCL 129.203. The principal contractor who obtains the bond, as well as the principal’s surety if applicable, is liable to compensate suppliers of labor or materials.”
Morris Pumps v. Centerline Piping, Inc., 729 N.W.2d 898 (Mich. Ct. App. 2007).
· cites it 2× “MCL 129.203; MCL 129.206; see also W T Andrew Co, Inc v Mid-State Surety Corp, 450 Mich 655 , 659; 545 NW2d 351 (1996).”
WT ANDREW Co. v. Mid-State Sur. Corp., 545 N.W.2d 351 (Mich. 1996).
· cites it 2× “2321(2) and MCL 129.203; MSA 5.2321(3) go on to enumerate the purpose behind the performance and payment bonds: The performance bond shall be in an amount *659 fixed by the governmental unit but not less than 25% of the contract amount, conditioned upon the faithful performance…”
Thomas Indus., Inc v. C & L Elec., Inc, 550 N.W.2d 558 (Mich. Ct. App. 1996).
· cites it 2× “Pursuant to the requirements of MCL 129.203; MSA 5.2321(3), C & L furnished a payment bond, issued by defendant USF&G as surety, for the protection of certain claimants supplying labor or materials for the project.”
Barnes & Sweeney Enter., Inc v. City of Hazel Park, 425 N.W.2d 572 (Mich. Ct. App. 1988).
“MCL 129.203; MSA 5.2321(3) provides that the governmental unit shall specify the amount the payment bond shall be for, but not less than twenty-five percent of the contract amount, and MCL 129.”
Leonard C. Carnaghi, Inc. v. Amwest Sur. Ins. Co., 617 N.W.2d 49 (Mich. Ct. App. 2000).
· cites it 2× “MCL 129.203; MSA 5.2321(3). “Claimant” is statutorily defined as “a person having furnished labor, material, or both, used or reasonably required for use in the performance of the contract.”
W. T. Andrew Co. v. Mid-State Sur. Corp., 611 N.W.2d 305 (Mich. 2000).
“2321(3)], and who has not been paid in full therefor before the expiration of a period of 90 days after the day on which the last of the labor was done or performed by him or material was furnished or supplied by him for which claim is made, may sue on the payment bond for the…”
WT Andrew Co. v. Mid-State Sur. Corp., 450 Mich. 655 (1996).
· cites it 2× “2321(2) and MCL 129.203; MSA 5.2321(3) go on to enumerate the purpose behind the performance and payment bonds: The performance bond shall be in an amount *659 fixed by the governmental unit but not less than 25% of the contract amount, conditioned upon the faithful performance…”
Annotations are extracted automatically from the opinions in the
Syfert caselaw corpus and ranked by authority, recency, and
treatment. Dots show Syfertize treatment of the citing case itself.