Electric company plan for meeting requirements; commission review; rules

Edition and currency
laws through the 2025 session (checked Sept. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2025 session (checked Sept. 2026) ACTIVE · 1 IN 5Y cited 2026 1citing case
At a glance

Courts have cited this section in 1 opinion since 2026, 1 of them in the last five years. The most litigated part is subsection (1) (1 case).

      469A.075 Electric company plan for meeting requirements; commission review; rules. (1) An electric company that is subject to a renewable portfolio standard shall describe the electric company’s plan for meeting the requirements of the renewable portfolio standard as part of the electric company’s integrated resource plan filed with the Public Utility Commission.

      (2) At a minimum, a plan for meeting the requirements of the renewable portfolio standard must contain:

      (a) Annual targets for acquisition and use of qualifying electricity; and

      (b) The estimated cost of meeting the annual targets, including the cost of transmission, the cost of firming, shaping and integrating qualifying electricity, the cost of alternative compliance payments and the cost of acquiring renewable energy certificates.

      (3) The commission shall review a plan for meeting the requirements of the renewable portfolio standard and take appropriate action as part of the procedure for acknowledgment of an electric company’s integrated resource plan.

      (4) The commission shall adopt rules:

      (a) Establishing requirements for the content of plans for meeting the requirements of the renewable portfolio standard;

      (b) Providing for the least-cost, least-risk acquisition of resources; and

      (c) Providing for the evaluation of competitive bidding processes that allow for diverse ownership of renewable energy sources that generate qualifying electricity.

      (5) A plan for meeting the requirements of the renewable portfolio standard may include procedures that will be used by the electric company to determine whether the costs of constructing a facility that generates electricity from a renewable energy source, or the costs of acquiring bundled or unbundled renewable energy certificates, are consistent with the renewable portfolio standards of the commission relating to least-cost, least-risk planning for acquisition of resources. [2007 c.301 §11; 2016 c.28 §6; 2023 c.54 §1]

 

(Cost Limitation)

The 1 case that cites Or. Rev. Stat. § 469A.075 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
NEUTRALNewSun Energy LLC v. PUC, 348 Or. App. 293 (Or. Ct. App. 2026).
cites § 469A.075 3×subsections: (1) (3) (4)(c)
Where it cites § 469A.075
“ORS 469A.075(1), (2). The PUC must now “review a plan for meeting the requirements of the renewable portfolio standard and take appropriate action as part of the procedure for acknowledgment of an electric company’s integrated resource plan.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

By subsection
(1)1 case
NewSun Energy LLC v. PUC, 348 Or. App. 293 (Or. Ct. App. 2026).“ORS 469A.075(1), (2). The PUC must now “review a plan for meeting the requirements of the renewable portfolio standard and take appropriate action as part of the procedure for acknowledgment of an electric company’s integrated resource plan.”
(3)1 case
NewSun Energy LLC v. PUC, 348 Or. App. 293 (Or. Ct. App. 2026).
(4)(c)1 case
NewSun Energy LLC v. PUC, 348 Or. App. 293 (Or. Ct. App. 2026).
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.