Skip to main content
U.S. CodeTitle 28Part VI— Particular ProceedingsChapter 165— United States Court of Federal Claims Procedure

28 U.S.C. § 2516 (2026)

Interest on claims and judgments

Edition and currency
U.S. Code current through Pub. L. 119-102 (OLRC release point). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTU.S. Code current through Pub. L. 119-102 (OLRC release point) cited 1954–2025 230citing cases
At a glance

Courts have cited this section in 230 opinions since 1954, 3 of them in the last five years. The most litigated part is subsection (a) (4 cases).

(a) Interest on a claim against the United States shall be allowed in a judgment of the United States Court of Federal Claims only under a contract or Act of Congress expressly providing for payment thereof.(b) Interest on a judgment against the United States affirmed by the Supreme Court after review on petition of the United States is paid at a rate equal to the weekly average 1-year constant maturity Treasury yield, as published by the Board of Governors of the Federal Reserve System, for the calendar week preceding the date of the judgment.(June 25, 1948, ch. 646, 62 Stat. 978; Sept. 3, 1954, ch. 1263, § 57, 68 Stat. 1248; Pub. L. 97–164, title I, § 139(j)(2), title III, § 302(d), Apr. 2, 1982, 96 Stat. 43, 56; Pub. L. 97–258, § 2(g)(5), (m)(3), Sept. 13, 1982, 96 Stat. 1061, 1062; Pub. L. 102–572, title IX, § 902(a)(1), Oct. 29, 1992, 106 Stat. 4516; Pub. L. 106–554, § 1(a)(7) [title III, § 307(d)(2)], Dec. 21, 2000, 114 Stat. 2763, 2763A–636.)Historical and Revision Notes1948 Act

Based on title 28, U.S.C., 1940 ed., § 284 and section 226 of title 31, U.S.C., 1940 ed., Money and Finance (Sept. 30, 1890, ch. 1126, § 1, 26 Stat. 537; Mar. 3, 1911, ch. 231, § 177, 36 Stat. 1141; Nov. 23, 1921, ch. 136, § 1324(b), 42 Stat. 316; June 2, 1924, ch. 234, § 1020, 43 Stat. 346; Feb. 13, 1925, ch. 229, § 3(c), 43 Stat. 939; Feb. 26, 1926, ch. 27, §§ 1117, 1200, 44 Stat. 119, 125; May 29, 1928, ch. 852, § 615(a), 45 Stat. 877; June 22, 1936, ch. 690, § 808, 49 Stat. 1746).

Subdivision (b) of section 284 of title 28, U.S.C., 1940 ed., was omitted as covered by section 3771 of title 26, U.S.C., 1940 ed., Internal Revenue Code. Such omission required the exception in subdivision (a) of such section 284, reading: “except as provided in subdivision (b)”, to be changed to read: “or Act of Congress expressly providing for payment thereof.”

Subsection (b) of this section is based on the last sentence of section 226 of title 31, U.S.C., 1940 ed., Money and Finance.

Changes were made in phraseology.

1982 Act

Revised Section

Source (U.S. Code)

Source (Statutes at Large)

28:2516(b)

28:2516(b)(1st sentence words before “from the date”).

Section 2(g)(5) of the bill restates 28:2516(b) because the provisions in 28:2516(b) on the periods for computing interest were superseded by the source provisions restated in section 1304 of the revised title 31.

Editorial NotesAmendments

2000—Subsec. (b). Pub. L. 106–554 substituted “the weekly average 1-year constant maturity Treasury yield, as published by the Board of Governors of the Federal Reserve System, for the calendar week preceding” for “the coupon issue yield equivalent (as determined by the Secretary of the Treasury) of the average accepted auction price for the last auction of fifty-two week United States Treasury bills settled immediately before”.

1992—Subsec. (a). Pub. L. 102–572 substituted “United States Court of Federal Claims” for “United States Claims Court”.

1982—Subsec. (a). Pub. L. 97–164, § 139(j)(2), substituted “United States Claims Court” for “Court of Claims”.

Subsec. (b). Pub. L. 97–258 substituted provisions that interest on a judgment against the United States is paid at a rate equal to the coupon issue yield equivalent of the average accepted auction price for the last auction of fifty-two week United States Treasury bills settled immediately before the date of judgment for provisions that such interest would be paid at the rate of four percent per annum from the date of the filing of the transcript of the judgment in the Treasury Department to the date of mandate of affirmance by the Supreme Court and that the interest would not be allowed for any period after the term of the Supreme Court at which the judgment was affirmed, and repealed the amendment made by Pub. L. 97–164, § 302(d), eff. Oct. 1, 1982. See, also, section 1304(b) of Title 31, Money and Finance.

Pub. L. 97–164, §§ 302(d), 402, eff. Oct. 1, 1982, struck out “at the rate of four percent per annum” and all that follows through “affirmance” and inserted in lieu thereof “, from the date of the filing of the transcript of the judgment in the General Accounting Office to the date of the mandate of the affirmance, at a rate of interest equal to the coupon issue yield equivalent (as determined by the Secretary of the Treasury) of the average accepted auction price for the last auction of fifty-two week United States Treasury bills settled immediately prior to the date of the judgment”.

1954—Subsec. (b). Act Sept. 3, 1954, inserted “for any period” after “allowed” in last sentence.

Statutory Notes and Related SubsidiariesEffective Date of 1992 Amendment

Amendment by Pub. L. 102–572 effective Oct. 29, 1992, see section 911 of Pub. L. 102–572, set out as a note under section 171 of this title.

Effective Date of 1982 Amendment

Pub. L. 97–258, § 2(g)(5), Sept. 13, 1982, 96 Stat. 1061, provided that the amendment made by that section is effective Oct. 1, 1982.

Repeals

Pub. L. 97–164, title III, § 302(d), Apr. 2, 1982, 96 Stat. 56, cited as a credit to this section, was repealed by Pub. L. 97–258, § 2(m)(3), Sept. 13, 1982, 96 Stat. 1062, eff. Oct. 1, 1982.

The 20 cases that cite 28 U.S.C. § 2516 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENMarathon Oil Co. v. United States, 374 F.3d 1123 (Fed. Cir. 2004).
cites § 2516 8×cited by 27 cases
Where it cites § 2516
“Furthermore, the Oil Companies contend that the interest owed on their contract judgment is unaffected by 28 U.S.C. § 2516 (b) or 31 U.S.C. § 1304 (b).”
Later courts cite it for
“a waiver of sovereign immunity 'must be unequivocally expressed,' or a court must infer that congress did not intend to create a waiver.” · 3 citing courts
2
GREENWisconsin Elec. Power Co. v. United States, 90 Fed. Cl. 714 (Fed. Cl. 2009).
cites § 2516 6×cited by 24 cases
Where it cites § 2516
“) By statute, interest on a claim against the United States may be awarded only if provided for by contract or statute. “Interest on a claim against the United States shall be allowed in a judgment of the United States Court of Federal Claims only under a eon-tract or Act of…”
The case’s holding
A party may recover reasonable mitigation costs incurred to limit damages from a partial breach, where those costs were reasonably foreseeable, substantially caused by the breach, and proven with reasonable certainty.
Later courts cite it for
“would have occurred in 1999 even if doe had begun performance in 1998.” · 5 citing courts
3
GREENSys. Fuels, Inc. v. United States, 92 Fed. Cl. 101 (Fed. Cl. 2010).
cites § 2516 6×cited by 17 cases
Where it cites § 2516
“The court’s authority to award the first type of interest as damages is governed by the Judiciary and Judicial Procedure Rules of Decision Act that provides, “[i]nterest on a claim against the United States shall be allowed in a judgment of the United States Court of Federal…”
Later courts cite it for
“determined that plaintiffs would have performed the cell recovery project even if doe accepted snf at grand gulf in 2006” · 1 citing court
4
GREENSys. Fuels, Inc. v. United States, 78 Fed. Cl. 769 (Fed. Cl. 2007).
cites § 2516 5×cited by 21 cases
Where it cites § 2516
“Plaintiffs do not contest that 28 U.S.C. § 2516 (a) is a general bar on the award of prejudgment interest, but rely on the United States Court of Appeals for the Federal Circuit decision in Wickham Contracting Co.”
The case’s holding
A private party to a government contract may recover interest on borrowed funds used to mitigate a breach if causation is established.
Later courts cite it for
“if causation is established, a private party to a government contract may recover an amount charged by a lender for borrowed funds that were obtained to mitigate a breach of contract.” · 2 citing courts
5
GREENSys. Fuels, Inc. v. United States, 666 F.3d 1306 (Fed. Cir. 2012).
cites § 2516 4×cited by 29 cases
Where it cites § 2516
“The trial court stated that its authority to award interest on a claim of damages is governed by the Judiciary and Judicial Procedure Rules of Decision Act, which states that "interest on a claim against the United States shall be allowed in a judgment of the United States Court…”
The case’s holding
The no-interest rule precludes recovery of interest costs on borrowed money, but overhead costs for mitigation work are recoverable if supported by reliable accounting records.
Later courts cite it for
“denies claims for interest and 'interest costs incurred on money borrowed as a result of the government's breach or delay in payment” · 4 citing courts
6
GREENDorothy M. Thompson v. Ralph E. Kennickell, Jr., 797 F.2d 1015 (D.C. Cir. 1986).
cites § 2516 7×cited by 20 cases
Where it cites § 2516
“§ 2411 , 28 U.S.C. § 2516 , and 31 U.S.C. § 724a. These provisions designated certain judgments against the United States on which interest would be allowed and established both the rate of interest and the time period during which such interest would be payable.”
Later courts cite it for
“for post-judgment interest only during the period that the government appealed its adverse judgment to the supreme court.” · 1 citing court
7
cites § 2516 8×cited by 14 cases
Where it cites § 2516
“See 28 U.S.C. § 2516 (a) (1982). Compare Maryland Port Administration, supra, 438 A.”
Later courts cite it for
“first step in the construction of contracts is to determine "what a reasonable person in the position of the parties would have thought the disputed language meant.” · 4 citing courts
8
GREENCalifornia Fed. Bank v. United States, 395 F.3d 1263 (Fed. Cir. 2005).
cites § 2516 2×cited by 93 cases
Where it cites § 2516
“” 28 U.S.C. § 2516 (a). This is not an action against a federal agency as such, but is an action against the United States based on a breach of contract caused by the enactment of legislation.”
The case’s holding
A plaintiff must establish a definite causal connection between a breach and lost profits, though the existence of other contributing factors does not necessarily preclude recovery.
Later courts cite it for
“the existence of other factors operating in confluence with the breach will not necessarily preclude recovery based on the breach.” · 10 citing courts
9
GREENDravo Corp. v. United States, 219 Ct. Cl. 416 (Ct. Cl. 1979).
cites § 2516 5×cited by 27 cases
Where it cites § 2516
“To begin with, it is well established in the law that interest cannot be recovered against the United States upon unpaid accounts or claims in the absence of an express provision to the contrary in a relevant statute or contract, 28 U.S.C. § 2516 (a) (1970). 2 Mar-Pak Corp.”
The case’s holding
A contractor bears the burden of proving that a change in contract terms created a clear necessity for additional borrowings (basis: clear necessity for borrowings occasioned by the change).
Later courts cite it for
“it is clear that this court still holds to the view that direct tracing to a specific loan or necessity for increased borrowing is still required to be proven in order for a contractor to recover for interest costs under an equitable adjustment theory.” · 6 citing courts
10
GREENEnergy Nw. v. United States, 91 Fed. Cl. 531 (Fed. Cl. 2010).
cites § 2516 4×cited by 15 cases
Where it cites § 2516
“As interest on a claim, Plaintiffs recovery would be barred by operation of the “no interest” rule of 28 U.S.C. § 2516 (a), which provides: Interest on a claim against the United States shall be allowed in a judgment of the United States Court of Federal Claims only under a…”
11
GREENN. States Power Co. v. United States, 78 Fed. Cl. 449 (Fed. Cl. 2007).
cites § 2516 3×cited by 24 cases
Where it cites § 2516
“In support of its argument, defendant refers to 28 U.S.C. § 2516 (a) which provides that “[i]nterest on a claim against the United States shall be allowed in a judgment of the United States Court of Federal Claims only under a contract or Act of Congress expressly providing for…”
The case’s holding
A party's duty to mitigate partial breach arises once it has reason to know performance will not be forthcoming, and recoverable mitigation costs must be foreseeable, caused by the breach, and reasonable.
12
GREENBoston Edison Co. v. United States, 93 Fed. Cl. 105 (Fed. Cl. 2010).
cites § 2516 4×cited by 14 cases
Where it cites § 2516
“Whether Entergy may recover its claim for cost-of-capital damages turns on the application of the no-interest rule, which states that “[i]nterest on a claim against the United States shall be allowed in a judgment of the United States Court of Federal Claims only under a…”
Later courts cite it for
“by regulation, decommissioning funds may not be used for non-decommissioning related expenses, such as spent nuclear fuel storage.” · 1 citing court
13
GREENWestfed Holdings, Inc. v. United States, 52 Fed. Cl. 135 (Fed. Cl. 2002).
cites § 2516 2×cited by 48 cases
Where it cites § 2516
“Interest on a claim against the United States is precluded under 28 U.S.C. § 2516 (a) (1994) unless permitted under a contract or Act of Congress.”
The case’s holding
A shareholder has standing to sue directly for breach of a regulatory forbearance agreement that does not explicitly allocate the risk of regulatory change to the thrift.
Later courts cite it for
“from adverse consequences beyond the compass of section 563.13 of the insurance regulations.” · 2 citing courts
14
GREENTexas Clinical Labs, Inc. v. Kathleen Sebel, 612 F.3d 771 (5th Cir. 2010).
cites § 2516 2×cited by 46 cases
Where it cites § 2516
“253, 264-65 (1980): see also, 28 U.S.C. § 2516 (a) (“Interest on a claim against the United States shall be allowed in a judgment of the United States Court of Federal Claims only under a contract or Act of Congress expressly providing for payment thereof.”
The case’s holding
A court must defer to an agency's interpretation of its own ambiguous regulation unless the interpretation is plainly erroneous or inconsistent with the regulation.
Later courts cite it for
“in reviewing an agency's decision under the arbitrary and capricious standard, there is a presumption that the agency's decision is valid, and the plaintiff has the burden to overcome that presumption by showing that the decision was erroneous.” · 4 citing courts
15
GREENBull v. United States, 68 Fed. Cl. 212 (Fed. Cl. 2005).
cites § 2516 2×cited by 46 cases
Where it cites § 2516
“*229 "Interest on a claim against the United States shall be allowed in a judgment by the United States Court of Federal Claims only under a contract or Act of Congress expressly providing for payment thereof,” 28 U.”
The case’s holding
Off-duty activities constitute compensable work under the FLSA if they benefit the employer, are known to the employer, and are controlled or required by the employer.
Later courts cite it for
“opm limits the application of the de minim-is doctrine to periods of 10 minutes or less per day.” · 7 citing courts
16
GREENHealth Repub. Ins. Co. v. United States, 129 Fed. Cl. 757 (Fed. Cl. 2017).
cites § 2516 3×cited by 8 cases
Where it cites § 2516
“” Plaintiff does not allege a breach of contract or identify any federal statutes that would entitle it to prejudgment interest.”
Later courts cite it for
“a concern that insurers' costs would detrimentally exceed the premiums collected.” · 1 citing court
17
GREENS. Nuclear Operating Co. v. United States, 77 Fed. Cl. 396 (Fed. Cl. 2007).
cites § 2516 2×cited by 42 cases
Where it cites § 2516
“) Prejudgment interest on contract claims against the United States is precluded by 28 U.S.C. § 2516 (a). 46 In England, v. Contel Advanced Systems, Inc.”
The case’s holding
Mitigation costs are recoverable if the general response to a breach is foreseeable, even if the specific implementation of the mitigating decision is not.
Later courts cite it for
“while the general response to a breach must be foreseen, the particular way that a mitigating decision is implemented need not.” · 7 citing courts
18
GREENConsumers Energy Co. v. United States, 84 Fed. Cl. 670 (Fed. Cl. 2008).
cites § 2516 6×cited by 6 cases
Where it cites § 2516
“This Court holds that Consumers Energy is impermissibly seeking interest on a claim against the United States in contravention of 28 U.S.C. § 2516 (a). Additionally, this Court holds that Consumers Energy’s claim for attorney and expert fees is not permitted under binding case…”
19
GREENTennessee Valley Auth. v. United States, 69 Fed. Cl. 515 (Fed. Cl. 2006).
cites § 2516 2×cited by 40 cases
Where it cites § 2516
“(citing 28 U.S.C. § 2516 (a)) (emphasis added). Section 2516(a) of Title 28 of the U.”
The case’s holding
The government bears the burden of proving that a non-breaching party's mitigation efforts were unreasonable.
Later courts cite it for
“the government bears the burden of showing that plaintiffs mitigation efforts were unreasonable.” · 6 citing courts
cites § 2516 2×cited by 36 cases
Where it cites § 2516
“3d at 1310 -13 (citing 28 U.S.C. § 2516 (a)); see also Sys. Fuels, Inc.”
The case’s holding
A plaintiff must prove that the type of damages is foreseeable as well as the fact of damage to recover consequential damages for breach of contract.
Later courts cite it for
“a plaintiff must show that the type of damages are foreseeable as well as the fact of damage.” · 3 citing courts

Show all 230 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
195419892025

One bar per 2 years. Tallest: 19 cases in 2010–2011. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Ct. Cl.86Fed. Cl.83Fed. Cir.23D.D.C.5D.C. Cir.45th Cir.38th Cir.311th Cir.2

The 8 courts with the most citing cases, of 26 courts in all.

By subsection
(a)4 cases
Allen v. United States, 229 Ct. Cl. 515 (Ct. Cl. 1981).
Nez Perce Tribe of Indians v. United States, 176 Ct. Cl. 815 (Ct. Cl. 1966).
Gmo. Niehaus & Co. v. United States, 373 F.2d 944 (Ct. Cl. 1967).

Show all 230 citing cases (list view) →

Enactment and amendments
(June 25, 1948, ch. 646, 62 Stat. 978; Sept. 3, 1954, ch. 1263, § 57, 68 Stat. 1248; Pub. L. 97–164, title I, § 139(j)(2), title III, § 302(d), Apr. 2, 1982, 96 Stat. 43, 56; Pub. L. 97–258, § 2(g)(5), (m)(3), Sept. 13, 1982, 96 Stat. 1061, 1062; Pub. L. 102–572, title IX, § 902(a)(1), Oct. 29, 1992, 106 Stat. 4516; Pub. L. 106–554, § 1(a)(7) [title III, § 307(d)(2)], Dec. 21, 2000, 114 Stat. 2763, 2763A–636.)
Amendment years (notes): 2000, 1992, 1982, 1954
Versions

Edition shown: U.S. Code current through Pub. L. 119-102 (OLRC release point). Syfert holds no earlier or later version of this section.