42 U.S.C. § 10162 (2026)
Authorization of monitored retrievable storage
Edition and currency
Other sources
Courts have cited this section in 9 opinions since 2003.
The proposal of the Secretary (EC–1022, 100th Congress) to locate a monitored retrievable storage facility at a site on the Clinch River in the Roane County portion of Oak Ridge, Tennessee, with alternative sites on the Oak Ridge Reservation of the Department of Energy and on the former site of a proposed nuclear powerplant in Hartsville, Tennessee, is annulled and revoked. In carrying out the provisions of sections 10164 and 10165 of this title, the Secretary shall make no presumption or preference to such sites by reason of their previous selection.
The Secretary is authorized to site, construct, and operate one monitored retrievable storage facility subject to the conditions described in sections 10163 through 10169 of this title.
Pub. L. 100–202 and Pub. L. 100–203 added identical sections.
- Where it cites § 10162
- “Defendant concedes that “DOE has never constructed a MRS [] authorized pursuant to 42 U.S.C. § 10162 (b), subject to the licensing and construction requirements of 42 U.”
- The case’s holding
- The concept of a taking has limited application when the parties' rights are voluntarily created by contract and interference with those rights generally gives rise to a breach of contract claim.
- Later courts cite it for
- “although plaintiff may have real property interests that are separate from its interests under the standard contract, plaintiff does not have a takings claim absent the rights and obligations granted to the parties by the standard contract.” · 2 citing courts
- Where it cites § 10162
- “42 U.S.C. § 10162 (b). However, DOE could not begin construction of this secondary storage facility until it had obtained a license for a permanent facility.”
- The case’s holding
- A government agency breaches the implied covenant of good faith and fair dealing by failing to act on contractually mandated schedules, allowing for recovery of mitigation costs.
- Later courts cite it for
- “doe's failure to perform under the standard contract thus has led to the very thing the nwpa and the standard contract were designed to forestall, i.e., the construction of dry storage facilities for spent nuclear fuel at nuclear power electricity generating plants throughout the united states.” · 2 citing courts
- Where it cites § 10162
- “1330 -227, 1330-232 (codified at 42 U.S.C. § 10162 (b)). The statutory conditions on the MRS took the form of three principal “linkages” between the DOE’s authority to proceed with a MRS and progress by the DOE on the permanent repository.”
- The case’s holding
- The government must demonstrate with reasonable certainty that claimed benefits exist to offset costs, as speculative claims are insufficient (establishing the standard for offsetting benefits).
- Later courts cite it for
- “any 'benefits' the government seeks to offset must be shown to a reasonable certainty, or they must be denied as too speculative to meet the standards set forth by the federal circuit in indiana michigan.” · 2 citing courts
- Where it cites § 10162
- “The Amendments Act also authorized DOE to site, construct, and operate a single MRS facility, 42 U.S.C. § 10162 (b), provided that DOE not select a site for the MRS facility “until the Secretary recommends to the President the approval of a site for development as a repository,”…”
- The case’s holding
- A party's duty to mitigate partial breach arises once it has reason to know performance will not be forthcoming, and recoverable mitigation costs must be foreseeable, caused by the breach, and reasonable.
- Where it cites § 10162
- “1330 -227, 1330-232 (codified at 42 U.S.C. § 10162 (b)). The conditions took the form of linkages between DOE’s authority to proceed with a MRS and progress by DOE on a permanent repository.”
- Later courts cite it for
- “a court may grant such a motion when the movant shows '(1) that an intervening change in the controlling law has occurred; (2) that previously unavailable evidence is now available; or (3) that the motion is necessary to prevent manifest injustice.” · 9 citing courts
- Where it cites § 10162
- “1330 -232 (current version at 42 U.S.C. § 10162 (b) (2006)), which made timely performance of *266 the contract extremely difficult.”
- The case’s holding
- Overhead costs are recoverable if a utility demonstrates that the costs were incurred and are properly attributable to mitigation projects and activities.
- Later courts cite it for
- “overhead costs are recoverable as long as a utility can demonstrate that 'overhead costs were incurred and are properly attributable to mitigation projects and activities.” · 4 citing courts
- Where it cites § 10162
- “1330 -227, 1330-232 (codified at 42 U.S.C. § 10162 (b)). Congress, however, prohibited the MRS from storing more than 10,000 MTU and also limited DOE’s ability to construct the interim facility until the permanent repository had been licensed for construction.”
- The case’s holding
- Mitigation costs resulting from a breach of a spent-fuel contract are recoverable if causally linked and foreseeable, but interest-like cost of capital claims are barred.
- Later courts cite it for
- “envy's accounting practices follow generally accepted accounting principles gaap and ferc guide- lines.” · 1 citing court
- Where it cites § 10162
- “at 32-33; 42 U.S.C. §§ 10162 (b), 10168(d)(1), (3).”
- Where it cites § 10162
- “42 U.S.C. § 10162 (b). The conditions included the requirement that a permanent repository be licensed first.”
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per year. Tallest: 3 cases in 2007. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.
Edition shown: U.S. Code current through Pub. L. 119-102 (OLRC release point). Syfert holds no earlier or later version of this section.