Skip to main content

Ariz. Rev. Stat. § 34-223 (2026)

Payment bond provisions

Edition and currency
text as last checked Oct. 2026 (this copy records no edition or section history). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTtext as last checked Oct. 2026 (this copy records no edition or section history) cited 1977–2016 24citing cases
At a glance

Courts have cited this section in 24 opinions since 1977. The most litigated part is subsection (A) (14 cases).

A. Every claimant who has furnished labor or material in the prosecution of the work provided for in a contract for which a payment bond is furnished under section 34-222, and who has not been paid in full for the labor or material for the work before the expiration of a period of ninety days after the day on which the last of the labor was done or performed by the claimant or material was furnished or supplied by the claimant for which the claim is made, shall have the right to sue on the payment bond for the amount, or the balance of the amount, unpaid at the time of institution of the suit and to prosecute the action to final judgment for the sum or sums justly due the claimant, and have execution thereon, provided however that any claimant who has a direct contractual relationship with a subcontractor of the contractor furnishing the payment bond but not a contractual relationship express or implied with the contractor has a right of action on the payment bond on giving the contractor the following notices:

1. A written preliminary twenty-day notice, as provided for in section 33-992.01, subsection C, paragraphs 1, 2, 3 and 4 and subsections E, F and H.

2. A written ninety-day notice given within ninety days after the date on which the claimant performed the last of the labor or furnished or supplied the last of the material for which the claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was done or performed. The ninety-day notice shall be given by any means that provides written, third-party verification of delivery to the contractor at any place the contractor maintains an office or conducts business, or at the contractor's residence.

B. Every suit instituted under this section shall be brought in the name of the claimant but no such suit shall be commenced after the expiration of one year after the date on which the last of the labor was performed or materials were supplied by the person bringing this suit.

C. On written application, the contracting body and the agent in charge of its office shall furnish to any person that states the person has supplied labor or materials for the work, and payment for the labor or materials for the work has not been made, or is being sued on the bond, or is the surety on the bond, a certified copy of the bond and the contract for which the bond was given.  The copy is prima facie evidence of the contents, execution and delivery of the original. Applicants shall pay for the certified copies and the reasonable fees that the contracting body or the agent in charge of its office fixes to cover the actual cost of preparation of the certified copies.

 

The 20 cases that cite Ariz. Rev. Stat. § 34-223 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENCemex Constr. Materials South, LLC v. Falcone Bros. & Assocs., 349 P.3d 210 (Ariz. Ct. App. 2015).
cites § 34-223 45×subsections: (A) 43× (B)cited by 3 cases
Where it cites § 34-223
“To maintain an action on the bond, a claimant must comply with the notice requirements of § 34-223(A), which provides in pertinent part: [A]ny such claimant having a direct contractual relationship with a subcontractor of the contractor furnishing such payment bond but no…”
2
GREENHartford Accident & Indem. Co. v. Fed. Ins., 834 P.2d 827 (Ariz. Ct. App. 1992).
cites § 34-223 17×subsections: (B) 14× (A) 2×cited by 12 cases
Where it cites § 34-223
“The bond shall be conditioned in accordance with the provisions of § 34-223, subsections A and B. The contract recorded with the bond shall contain a legal description of the land on which the work is being or is to be performed.”
3
GREENWestburne Supply, Inc. v. Diversified Design & Constr., Inc., 826 P.2d 1224 (Ariz. Ct. App. 1992).
cites § 34-223 27×subsections: (A) 25× (B) 2×cited by 5 cases
Where it cites § 34-223
“Westburne properly served a preliminary twenty day notice to Diversified as required by A.R.S. § 34-223(A). The notice estimated that the cost of the materials supplied would be $1,500.”
Later courts cite it for
“what a statute necessarily implies is as much a part of the statute as what it makes explicit.” · 1 citing court
4
GREENS & S Paving & Constr., Inc. v. Berkley Reg'l Ins., 372 P.3d 1036 (Ariz. Ct. App. 2016).
cites § 34-223 8×subsections: (A) 4× (B) 4×cited by 7 cases
Where it cites § 34-223
“” A.R.S. § 34-223(A). “The purpose behind both of the Miller Acts is to provide security for those who supply materials or labor in the construction of public projects.”
5
GREENW. Asbestos Co. v. TGK Const. Co., 590 P.2d 927 (Ariz. 1979).
cites § 34-223 10×subsections: (A) 8×cited by 17 cases
Where it cites § 34-223
“Construction, and the invoices thereto attached * * * do not constitute notice as required by A.R.S. § 34-223; and “2. That there was not, and is not, any contractual relationship existing between the Plaintiff [Western Asbestos Co.”
The case’s holding
Written notice to a prime contractor need not be sent by registered mail if receipt is proven, and it suffices if it states the amount and implies reliance on the contractor.
6
GREENHoneywell, Inc. v. Arnold Const. Co., 654 P.2d 301 (Ariz. Ct. App. 1982).
cites § 34-223 8×subsections: (C) 2×cited by 18 cases
Where it cites § 34-223
“A.R.S. § 34-223. The right of action contains, however, two significant limitation periods.”
The case’s holding
A corporation's veil may be pierced to reach an individual's property only if the corporation is shown to be the alter ego of that individual.
Later courts cite it for
“in order for a corporate 'veil' to be pierced, the corporation must be considered the alter ego of the individual whose property is sought.” · 1 citing court
7
GREENGreaig v. Park West Constr. Co., 637 P.2d 1079 (Ariz. Ct. App. 1981).
cites § 34-223 19×cited by 3 cases
Where it cites § 34-223
“A.R.S. § 34-223 in pertinent part provides that: [A]ny such claimant having a direct contractual relationship with a subcontractor of the contractor furnishing such payment bond but no contractual relationship express or implied with such contractor shall have a right of action…”
8
GREENAdvance Leasing & Crane Co. v. Del E. Webb Corp., 573 P.2d 525 (Ariz. Ct. App. 1977).
cites § 34-223 4×cited by 27 cases
Where it cites § 34-223
“Having reached this conclusion, we hold that Advance has no claim under A.R.S. § 34-223 as a supplier of a materialman.”
The case’s holding
A party who confers a benefit as performance of a contract with a third person is not entitled to restitution from the beneficiary merely because that third person failed to perform.
Later courts cite it for
“a person who has conferred a benefit upon another as the performance of a contract with a third person is not entitled to restitution from the other merely because of the failure of performance by the third person.” · 3 citing courts
9
GREENCoast to Coast Mfg. v. Carnes Constr., Inc., 700 P.2d 499 (Ariz. Ct. App. 1985).
cites § 34-223 7×subsections: (A) 7×cited by 5 cases
Where it cites § 34-223
“The statute states: “Every claimant who has furnished labor or material in the prosecution of the work provided for in such contract in respect of which a payment bond is furnished under the provisions of § 34-222, and who has not been paid in full therefor before the expiration…”
Later courts cite it for
“designed to relieve a prime contractor of liability to sub-subcontractors or material-men (who have no contractual relation to the prime contractor) after ninety days so that the prime contractor may safely pay his subcontractor without the fear of being subject to 'double payments' to sub-subcontractors.” · 2 citing courts
10
GREENBrown Wholesale Elec. Co. v. Safeco Ins. Co. of Am., 659 P.2d 1299 (Ariz. Ct. App. 1982).
cites § 34-223 2×cited by 30 cases
Where it cites § 34-223
“See A.R.S. § 34-223. If these three statutes are to be read together, as appellant claims, a claimant would be faced with two differing notice provisions.”
The case’s holding
A materials supplier suing on a contractor's license bond need not satisfy the lien statute's preliminary twenty-day notice requirement.
11
GREENGen. Acrylics v. United States Fid. & Guar. Co., 623 P.2d 839 (Ariz. Ct. App. 1980).
cites § 34-223 4×subsections: (C) 4×cited by 8 cases
Where it cites § 34-223
“See A.R.S. § 34-223(C). In the interpleader action, USF&G, as the assignee and subrogee of All American, moved for summary judgment, claiming it was entitled to all the sums interpleaded by Tuba City.”
12
NO FLAGR.E. Monks Constr. Co. v. Aetna Cas. & Sur. Co., 944 P.2d 517 (Ariz. Ct. App. 1997).
cites § 34-223 12×subsections: (B) 8× (A) 2×cited by 6 cases
Where it cites § 34-223
“This court has previously held that the limitations period under A.R.S. § 34-223 does not begin to run until completion of all work performed in direct furtherance of the construction contract.”
13
GREENAmfac Elec. Supply Co. v. Rainer Constr. Co., 600 P.2d 26 (Ariz. 1979).
cites § 34-223 4×subsections: (C) 4×cited by 6 cases
Where it cites § 34-223
“Due to this confusion as to the true claimant, appellees moved to dismiss on the additional ground that A.R.S. § 34-223(C) mandates that suit be brought in the name of the claimant.”
14
GREENArizona Laborers v. New Pueblo Constructors, Inc., 640 P.2d 209 (Ariz. Ct. App. 1982).
cites § 34-223 6×cited by 3 cases
Where it cites § 34-223
“This is an appeal from a summary judgment in favor of the plaintiff trust funds on their claim to a general contractor’s payment bond, pursuant to A.R.S. § 34-223. Defendant New Pueblo Constructors contracted with the Arizona Department of Transportation to work on the…”
15
GREENCertainteed Corp. v. United Pac. Ins., 762 P.2d 560 (Ariz. Ct. App. 1988).
cites § 34-223 2×cited by 11 cases
Where it cites § 34-223
“See A.R.S. § 34-223. Certainteed periodically sent invoices to C & D which made partial payments.”
16
GREENRogers v. Speros Const. Co., 580 P.2d 750 (Ariz. Ct. App. 1978).
cites § 34-223 4×cited by 4 cases
Where it cites § 34-223
“Their claim was asserted in one count under A.R.S. § 34-223 2 and in a second count as third-party beneficiaries under the construction contract, which states in part: .”
17
GREENTrio Forest Prods., Inc. v. FNF Constr., Inc., 893 P.2d 1 (Ariz. Ct. App. 1994).
cites § 34-223 4×subsections: (A) 4×cited by 4 cases
Where it cites § 34-223
“, provided however that any such claimant *2 having a direct contractual relationship with a subcontractor of the contractor furnishing such payment bond but no contractual relationship express or implied with such contractor shall have a right of action upon such payment bond…”
Later courts cite it for
“provide protection comparable to that afforded by state mechanic's lien laws on private contracts.” · 2 citing courts
18
GREENSCA Constr. Supply v. Aetna Cas. & Sur. Co., 754 P.2d 1339 (Ariz. 1987).
cites § 34-223 2×subsections: (A) 2×cited by 9 cases
Where it cites § 34-223
“shall have the right to sue on such payment bond____ A.R.S. § 34-223(A) (emphasis added) The purpose behind both of the Miller Acts is to provide security for those who supply materials or labor in the construction of public projects.”
Later courts cite it for
“the purpose behind both of the miller acts is to provide security for those who supply materials or labor in the construction of public projects.” · 2 citing courts
19
GREENNorman S. Wright & Co. v. Slaysman, 604 P.2d 261 (Ariz. Ct. App. 1979).
cites § 34-223 4×subsections: (A) 4×cited by 2 cases
Where it cites § 34-223
“The first is whether appellant gave sufficient notice to the general contractor under the requirements of A.R.S. § 34-223(A) of the Little Miller Act.”
20
GREENMaricopa Turf, Inc. v. Sunmaster, Inc., 842 P.2d 1370 (Ariz. Ct. App. 1992).
cites § 34-223 2×subsections: (A)cited by 3 cases
Where it cites § 34-223
“Section 34-223 provides that the preliminary twenty-day notice must be in the form prescribed by A.”

Show all 24 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
197719962016

One bar per year. Tallest: 4 cases in 1979. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Ariz. Ct. App.20Ariz.4
By subsection
(A)14 cases
Cemex Constr. Materials South, LLC v. Falcone Bros. & Assocs., 349 P.3d 210 (Ariz. Ct. App. 2015).“To maintain an action on the bond, a claimant must comply with the notice requirements of § 34-223(A), which provides in pertinent part: [A]ny such claimant having a direct contractual relationship with a subcontractor of the contractor furnishing such payment bond but no…”
Westburne Supply, Inc. v. Diversified Design & Constr., Inc., 826 P.2d 1224 (Ariz. Ct. App. 1992).“Westburne properly served a preliminary twenty day notice to Diversified as required by A.R.S. § 34-223(A). The notice estimated that the cost of the materials supplied would be $1,500.”
W. Asbestos Co. v. TGK Const. Co., 590 P.2d 927 (Ariz. 1979).“Construction, and the invoices thereto attached * * * do not constitute notice as required by A.R.S. § 34-223; and “2. That there was not, and is not, any contractual relationship existing between the Plaintiff [Western Asbestos Co.”
S & S Paving & Constr., Inc. v. Berkley Reg'l Ins., 372 P.3d 1036 (Ariz. Ct. App. 2016).“” A.R.S. § 34-223(A). “The purpose behind both of the Miller Acts is to provide security for those who supply materials or labor in the construction of public projects.”
Coast to Coast Mfg. v. Carnes Constr., Inc., 700 P.2d 499 (Ariz. Ct. App. 1985).“The statute states: “Every claimant who has furnished labor or material in the prosecution of the work provided for in such contract in respect of which a payment bond is furnished under the provisions of § 34-222, and who has not been paid in full therefor before the expiration…”
Showing the top 5 of 14. More in the list view →
(B)6 cases
Hartford Accident & Indem. Co. v. Fed. Ins., 834 P.2d 827 (Ariz. Ct. App. 1992).“The bond shall be conditioned in accordance with the provisions of § 34-223, subsections A and B. The contract recorded with the bond shall contain a legal description of the land on which the work is being or is to be performed.”
S & S Paving & Constr., Inc. v. Berkley Reg'l Ins., 372 P.3d 1036 (Ariz. Ct. App. 2016).
R.E. Monks Constr. Co. v. Aetna Cas. & Sur. Co., 944 P.2d 517 (Ariz. Ct. App. 1997).“This court has previously held that the limitations period under A.R.S. § 34-223 does not begin to run until completion of all work performed in direct furtherance of the construction contract.”
Showing the top 5 of 6. More in the list view →
(C)3 cases
Gen. Acrylics v. United States Fid. & Guar. Co., 623 P.2d 839 (Ariz. Ct. App. 1980).“See A.R.S. § 34-223(C). In the interpleader action, USF&G, as the assignee and subrogee of All American, moved for summary judgment, claiming it was entitled to all the sums interpleaded by Tuba City.”
Amfac Elec. Supply Co. v. Rainer Constr. Co., 600 P.2d 26 (Ariz. 1979).“Due to this confusion as to the true claimant, appellees moved to dismiss on the additional ground that A.R.S. § 34-223(C) mandates that suit be brought in the name of the claimant.”
Honeywell, Inc. v. Arnold Const. Co., 654 P.2d 301 (Ariz. Ct. App. 1982).“A.R.S. § 34-223. The right of action contains, however, two significant limitation periods.”

Show all 24 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: text as last checked Oct. 2026 (this copy records no edition or section history). Syfert holds no earlier or later version of this section.