In Re Miscott Corp., 848 F.2d 1190 (11th Cir. 1988). · Go Syfert
In Re Miscott Corp., 848 F.2d 1190 (11th Cir. 1988). Cases Citing This Book View Copy Cite
29 citation events (3 in the last 25 years) across 9 distinct courts.
Strongest positive: Andrews & Kurth L.L.P. v. Family Snacks, Inc. (In Re Pro-Snax Distributors, Inc.) (ca5, 1998-10-20)
Treatment trajectory · 1988 → 2026 · click a year to view as-of
1988 2007 2026
Top citers, strongest first. 12 distinct citers. How cited ↗
discussed Cited as authority (rule) Andrews & Kurth L.L.P. v. Family Snacks, Inc. (In Re Pro-Snax Distributors, Inc.)
5th Cir. · 1998 · confidence medium
“While in some cases the calculation of attorneys’ fees may be a ministerial duty collateral to the merits of the action,” In re Miscott Corp., 848 F.2d 1190, 1193 (11th Cir.1988), a remand requiring such a calculation is not final if it necessitates further factual development or other significant judicial activity involving the exercise of considerable discretion, see Travelers, 908 F.2d at 345 , or is likely to generate a new appeal or affect the issue that the disappointed party wants to raise on appeal from the order of remand.
discussed Cited as authority (rule) In the Matter of Francisco Lopez, Debtor-Appellant
7th Cir. · 1997 · confidence medium
See In re Gould & Eberhardt Gear Machinery Corp., 852 F.2d 26 (1st Cir.1988); In re Harrington, 992 F.2d 3 (1st Cir.1993); Bowers v. Connecticut National Bank, 847 F.2d 1019, 1023-24 (2d Cir.1988); In re Prudential Lines, Inc., 59 F.3d 327, 331-32 (2d Cir.1995); In re Chateaugay Corp., 838 F.2d 59 (2d Cir.1988); United States v. Carolina Parachute Corp., 907 F.2d 1469 , 1472 n. 3 (4th Cir.1990); Capitol Credit Plan of Tennessee, Inc. v. Shaffer, 912 F.2d 749 (4th Cir.1990); In re Bowman, 821 F.2d 245 (5th Cir.1987); In re County Management, Inc., 788 F.2d 311 (5th Cir.1986); In re Vekco, 792 F…
cited Cited as authority (rule) In Re Delta Resources, Inc., Debtor. Orix Credit Alliance, Inc. v. Delta Resources, Inc.
11th Cir. · 1995 · confidence medium
Miscott Corp. v. Zaremba Walden Co. (In re Miscott), 848 F.2d 1190, 1192 (11th Cir.1988) (other citations omitted).
cited Cited as authority (rule) In Re RED CARPET CORPORATION OF PANAMA CITY BEACH, Debtor. Jimmy HATCHER, Petitioner-Appellant, v. John MILLER, Respondent-Appellee
11th Cir. · 1990 · confidence medium
“The requirement of finality is essential to avoid piecemeal review, inconvenience and unnecessary costs.” In re Miscott Corp., 848 F.2d 1190, 1193 (11th Cir.1988).
discussed Cited as authority (rule) 20 Collier bankr.cas.2d 1521, Bankr. L. Rep. P 72,874 in Re Dixie Broadcasting, Inc. And Martin Broadcasting of Alabama, Inc., Debtors. Barclays-American/business Credit, Inc., Dixie Broadcasting, Inc. And Martin Broadcasting v. Radio Wbhp, Inc.
11th Cir. · 1989 · confidence medium
The Court noted that an order including a remand may be considered final if "all that remains is the performance of a ministerial duty." 848 F.2d at 1192. (citations omitted.) However, the Court concluded that a determination of whether a bona fide settlement offer was made and rejected, entitling the offeror to an award of attorneys' fees, was more than a ministerial duty.
discussed Cited as authority (rule) Barclays-American/Business Credit, Inc. v. Radio WBHP, Inc. (In re Dixie Broadcasting, Inc.)
11th Cir. · 1989 · confidence medium
The Court noted that an order including a remand may be considered final if “all that remains is the performance of a ministerial duty.” 848 F.2d at 1192. (citations omitted.) However, the Court concluded that a determination of whether a bona fide settlement offer was made and rejected, entitling the offer- or to an award of attorneys’ fees, was more than a ministerial duty.
examined Cited as authority (rule) T & B Scottdale Contractors, Inc. v. United States (3×) also: Cited "see, e.g."
11th Cir. · 1989 · confidence medium
They emphasize that an order is not final if on remand the bankruptcy court must exercise "significant judicial activity involving considerable discretion." Miscott, 848 F.2d at 1192.
cited Cited "see" Sky Enterprises, LLC v. Seawalk Investments, LLC
11th Cir. · 2024 · signal: see · confidence high
See Miscott Corp. v. Zaremba Walden Co. (In re Mis- cott Corp.), 848 F.2d 1190 , 1193 (11th Cir. 1988).
cited Cited "see" Nitram, Inc. v. Industrial Risk
11th Cir. · 1998 · signal: see · confidence high
See Miscott Corp. v. Zaremba Walden Co., 848 F.2d 1190, 1192 (11th Cir. 1988).
cited Cited "see" Industrial Risk Insurers v. M.A.N. Gutehoffnungshutte GmbH
11th Cir. · 1998 · signal: see · confidence high
See Miscott Corp. v. Zaremba Walden Co., 848 F.2d 1190, 1192 (11th Cir. 1988).
discussed Cited "see, e.g." T & B Scottdale Contractors, Inc. v. United States
11th Cir. · 1989 · signal: see also · confidence medium
The answer turns on whether the district court’s decision constitutes a final and appealable order which “ends the litigation on the merits and leaves nothing for the court to do but execute the judgment.” In re TCL Investors, 775 F.2d 1516, 1519 (11th Cir.1985) (order directing the bankruptcy court to conduct a trial on the merits of a property claim held not a final order); see also In re Miscott Corp., 848 F.2d 1190, 1192-93 (11th Cir. 1988) (order resolving contract dispute but remanding for factual development of attorney’s fees issue held not final); In re Regency Woods Apts., 68…
Retrieving the full opinion text from the archive…
In Re Miscott Corporation F/k/a/ Miscott Construction Corp., Debtor. Miscott Corporation F/k/a Miscott Construction Corp.
v.
Zaremba Walden Co., a Florida Corporation, Walden Communities, Inc., a Florida Corporation, D/b/a/ Walden Development Co. And Safeco Insurance Co. Of America
87-5451.
Court of Appeals for the Eleventh Circuit.
Jul 8, 1988.
848 F.2d 1190
Cited by 8 opinions  |  Published

848 F.2d 1190

In re MISCOTT CORPORATION f/k/a/ Miscott Construction Corp., Debtor.
MISCOTT CORPORATION f/k/a Miscott Construction Corp.,
Plaintiff-Appellant,
v.
ZAREMBA WALDEN CO., a Florida corporation, Walden
Communities, Inc., a Florida corporation, d/b/a/
Walden Development Co. and Safeco
Insurance Co. of America,
Defendants-Appellees.

No. 87-5451.

United States Court of Appeals,
Eleventh Circuit.

July 8, 1988.

Richard A. Sherman, P.A., Ft. Lauderdale, Fla., Robert Paul Keeley, Ellis, Spencer, Butler & Kisslan, Hollywood, Fla., for plaintiff-appellant.

Robert F. Plafsky, Ruden, Barnett, McClosky, Schuster, & Russell, P.A., John H. Pelzer, Ft. Lauderdale, Fla., for defendants-appellees.

Appeal from the United States District Court for the Southern District of Florida.

Before FAY and VANCE, Circuit Judges, and HOFFMAN[*], Senior District Judge.

FAY, Circuit Judge:

[*~1190]1

Miscott Corporation ("Miscott") appeals from an order of the district court that affirmed the decision of the bankruptcy court as to liability for breach of contract, but remanded the case to the bankruptcy court for further factual development concerning Zaremba Walden Co.'s ("Walden") entitlement to an award of attorneys fees. Because this court only has jurisdiction over final decisions, we must dismiss the appeal.

I. BACKGROUND

2

On June 22, 1983, Walden as owner and Miscott as general contractor, entered into a written contract for the construction of a residential condominium development in Dade County, Florida. The project consisted of eight buildings, a pool and a cabana facility. Walden divided the project into two phases. The contract provided that Miscott would build Phase II, composed of Buildings 5-8, only after receiving notice to proceed from Walden.

3

A section of the contract containing the liquidated damages clause[1] included a "bonus" provision which required Walden to pay Miscott for completing its work early. The contract stated:

4

"Owner agrees that, if Contractor completes all Work contemplated by the Contract Documents ahead of schedule, Contractor shall be entitled to the sum of FIVE HUNDRED AND 00/100 ($500.00) DOLLARS per day for each day that all of the Work contemplated by the Contract Documents is completed prior to the time required by the Contract Doucments [sic]."

5

Miscott completed each building at least seventy days ahead of schedule,[2] thus earning a "bonus" payment for early completion. The parties, however, dispute the amount of the bonus.

6

On July 3, 1984, Miscott filed for bankruptcy under Chapter 11 of the United States Bankruptcy Code. 11 U.S.C. Secs. 1101-1174 (1982 Supp. IV 1988). Miscott then initiated an adversary proceeding against Walden to foreclose a mechanic's lien under Chapter 713, Florida Statutes (1985). Miscott also sought damages for breach of contract caused by Walden's alleged failure to make the final contract payment and its failure to pay a bonus for early completion of the project.[3] Walden counterclaimed against Miscott for costs incurred due to posting surety bonds that transferred the subcontractors' mechanic's liens to bond, plus attorneys' fees incurred in defending lawsuits initiated by certain subcontractors to foreclose their mechanics' liens.

7

At trial, Miscott contended it was due a bonus payment of $291,000.00. Miscott calculated this amount by multiplying $500.00 per day times the number of days it completed each building ahead of schedule. Walden contended that Miscott was entitled to a bonus of only $38,500.00, calculated at the rate of $500.00 per day for each day the final building of the project was completed ahead of schedule. Walden also sought $17,472.50 in damages resulting from Miscott's failure to pay its subcontractors. The bankruptcy court awarded Miscott only $38,500.00 as its bonus, and awarded Walden $17,472.50 in damages plus attorneys' fees to be determined at a later date. 49 B.R. 893.

8

Pursuant to 28 U.S.C. Sec. 158(a) (Supp. III 1985), Miscott appealed the bankruptcy court's final judgment. The district court affirmed the bankruptcy court, but remanded the question of Walden's entitlement to attorneys' fees under Fla.Stat. Sec. 713.29 (1985). On appeal, this Court raised sua sponte an issue of jurisdiction concerning whether the district court's order is final and thus appealable.

II. DISCUSSION

[*~1191]9

We must examine the question of jurisdiction even when neither party raises the issue. In re Downtown Properties, Ltd., 794 F.2d 647, 650 (11th Cir.1986). In bankruptcy cases, 28 U.S.C.A. Sec. 158(d) (West Supp.1987) governs the jurisdiction of this court. This provision allows for the appeal of all district court decisions, judgments and orders that are final. Under section 158(d) a decision is not final if on remand the bankruptcy court is required to exercise significant judicial activity involving considerable discretion. In re TCL Investors, 775 F.2d 1516, 1518 (11th Cir.1985) (holding as not "final" a district court's order reversing and remanding case to the bankruptcy court for further proceedings); cf. In re Regency Woods Apartments, Ltd., 686 F.2d 899, 901 (11th Cir.1982) (per curiam) (interlocutory appeals not permitted under the Bankruptcy Code). On the other hand, a district court ruling which includes a remand may be a "final decision" if all that remains is the performance of a ministerial duty. Gulf Refining Co. v. United States, 269 U.S. 125, 136, 46 S.Ct. 52, 53, 70 L.Ed. 195 (1925) (rendering judgment for the exact sums set forth in stipulations was ministerial duty); Turner v. Orr, 759 F.2d 817, 820 (11th Cir.1985) (calculation of back pay and seniority of Air Force civilian employee was purely ministerial), cert. denied, 478 U.S. 1020, 106 S.Ct. 3332, 92 L.Ed.2d 738 (1986); Matter of Fox, 762 F.2d 54, 55 (7th Cir.1985) ("[a]n order upholding liability but leaving damages for subsequent determination is not a final order").

10

In this instance, enough remains for the bankruptcy court that the decision cannot be considered final. The district court, relying upon the Supreme Court of Florida's recent decision in C.U. Associates v. R.B. Grove, Inc., 472 So.2d 1177 (Fla.1985), remanded with instructions for the bankruptcy court to determine Walden's entitlement to attorneys' fees. On remand, the bankruptcy court is required to do more than simply determine the amount of attorneys' fees. Under Fla.Stat. Sec. 713.29 (1985), the bankruptcy court must decide whether Walden made a bona fide settlement offer and whether Miscott unequivocally refused that offer. See C.U. Associates, 72 So.2d at 1179. Further, the court must consider whether, in the light of the underlying issues, the offer was made in good faith. This requires an evidentiary hearing, consideration of factual issues and the entry of findings of fact. To determine the appropriate amount of attorneys' fees to be awarded, the bankruptcy court will need to weigh the evidence, examine the credibility of the various witnesses, and ultimately use its best judgment.

11

While in some cases the calculation of attorneys' fees may be a ministerial duty collateral to the merits of the action, see McQurter v. City of Atlanta, 724 F.2d 881, 882 (11th Cir.1984) (per curiam); Holmes v. J. Ray McDermott & Co., 682 F.2d 1143, 1146 (5th Cir.1982), this is not such a case. The determination of whether a bona fide settlement offer was made is the type of fact finding that is intertwined with the merits and thus involves the use of judicial judgment. This raises the responsibility of the bankruptcy court out of the realm of ministerial duties.

III. CONCLUSION

[*~1192]12

The requirement of finality is essential to avoid piecemeal review, inconvenience and unnecessary costs. This Court does not have jurisdiction until the district court decision is final. See Gillespie v. United States Steel Corp., 379 U.S. 148, 152-53, 85 S.Ct. 308, 310-11, 13 L.Ed.2d 199 (1964); Dickinson v. Petroleum Conversion Corp., 338 U.S. 507, 511, 70 S.Ct. 322, 324, 94 L.Ed. 299 (1950). Because the issues remanded to the bankruptcy court are the gravamen of the counterclaim and since the open issues involve essential elements of those claims, this decision is not final. Therefore, this appeal is DISMISSED for lack of jurisdiction.

*

Honorable Walter E. Hoffman, Senior U.S. District Judge for the Eastern District of Virginia, sitting by designation

1

According to the liquidated damages clause, Walden could penalize Miscott $500.00 per day for each day Miscott was late in delivering each building. The parties do not dispute the interpretation of the penalty clause and understand it to apply on a per building basis

2

The bankruptcy court found that Miscott completed the buildings ahead of schedule as follows: Building One--70 days; Building Two--70 days; Building Three--70 days; Building Four--70 days; Building Five--73 days; Building Six--76 days; Building Seven--76 days; and Building Eight--77 days

3

Miscott also sued Safeco Insurance Company of America for recovery under the surety transfer bond pursuant to Fla.Stat. Sec. 713.24 (1985)