United States v. Behan, 110 U.S. 338 (1884). · Go Syfert
United States v. Behan, 110 U.S. 338 (1884). Cases Citing This Book View Copy Cite
773 citation events (55 in the last 25 years) across 105 distinct courts.
Treatment trajectory · 1900 → 2026 · click a year to view as-of
1900 1963 2026
Top citers, strongest first. 50 distinct citers. How cited ↗
discussed Cited as authority (rule) Long Island Savings Bank, FSB v. United States
Fed. Cl. · 2004 · confidence medium
LaSalle Talman, 317 F.3d at 1371 (citing United States v. Behan, 110 U.S. 338, 345, 4 S.Ct. 81 , 28 L.Ed. 168 (1884)); see also Restatement Contracts § 344(a) & cmt. a (courts ordinarily provide a remedy for a breach of contract by “protecting the expectation that the injured party had when [it] made the contract”).
examined Cited as authority (rule) American Capital Corp. v. United States (4×) also: Cited "see, e.g."
Fed. Cl. · 2004 · confidence medium
See PLApp. on Liability at 14-25 (Aug. 21, 1986 FHLBB Resolution No. 86-864); id. at 233-280 (Aug. 29, 1986 Assistance Agreement); Def.App. on Damages II at 74.
discussed Cited as authority (rule) Century Marine Inc v. United States
5th Cir. · 1998 · confidence medium
Christian, 312 F.2d at 423 (citing United States v. Behan, 110 U.S. 338, 346 (1884); United States v. Spearin, 248 U.S. 132, 138 (1918); Broadbent Portable Laundry Corp. v. United States, 56 Ct. Cl. 128, 132 (1921)).
discussed Cited as authority (rule) Tabatchnick's II, Inc. v. Davis
Fla. Dist. Ct. App. · 1980 · confidence medium
In United States v. Behan, 110 U.S. 338, 344-45 , 4 S.Ct. 81, 83-84 , 28 L.Ed. 168, 170 (1884), that court stated: The prima facie measure of damages for the breach of a contract is the amount of the loss which the injured party has sustained thereby.
discussed Cited as authority (rule) Earl Dubey & Sons, Inc. v. MacOmb Concrete Corp.
Mich. Ct. App. · 1978 · confidence medium
But where the profits are wholly speculative and unprovable, the one who prevents performance may not go scot-free. " 'Unless there is some artificial rule of law which has taken the place of natural justice in relation to the measure of damages, it would seem to be quite clear that the claimant ought at least to be made whole for his losses and expenditures.’ United States v Behan, 110 US 338, 344 (4 Sup Ct 81.) "Where profits are speculative, the measure of damages is the actual expenditures and value of services reasonably spent in a bona fide attempt to perform the contract or reasonably…
cited Cited as authority (rule) St. Paul at Chase Corp. v. Manufacturers Life Insurance
Md. · 1971 · confidence medium
Ed. 168 .” Id. at 301-02. (i) First Count The trial judge allowed $5.00 compensatory damages and $50,000 punitive damages.
discussed Cited as authority (rule) Dale Construction Co. v. United States, Seaboard Surety Co. (2×) also: Cited "see, e.g."
Ct. Cl. · 1964 · confidence medium
United States v. Behan, 110 U.S. 338, 346 (1884); United States v. Spearin, 248 U.S. 132 (1918); Chain Belt Co. v. United States, 127 Ct. Cl. 38 , 115 F. Supp. 701 (1953); Seatrain Lines, Inc. v. United States, 99 Ct. Cl. 272, 317 (1943); Joplin v. United States, 89 Ct. Cl. 345, 360 (1939); Williston on Contracts, § 1344 (Eev.
discussed Cited as authority (rule) G. L. Christian & Associates v. United States (2×) also: Cited "see"
Ct. Cl. · 1963 · confidence medium
In this connection, it is settled that, when the Government enters into a contract, it has rights and.it ordinarily incurs' responsibilities similar to those of a private person who is a party to a contract (Lynch v. United States, 292 U.S. 571, 579 (1934); Perry v. United States, 294 U.S. 330, 352 (1935)), and if the Government terminates a contract without justification, such termination is a breach of the contract and the Government becomes liable for' all the damages resulting from the wrongful act (United States v. Behan, 110 U.S. 338, 346 (1884); United States v. Spearin, 248 U.S. 132, 1…
discussed Cited as authority (rule) Alexander H. Kerr & Co. v. Fooks
W.D. Ark. · 1956 · confidence medium
One of the landmark cases is United States v. Behan, 110 U.S. 338, 344, 345 , 4 S.Ct. 81, 83 , 28 L.Ed. 168 , wherein the court said: “Unless there is some artificial rule of law which has taken the place of natural justice in relation to the measure of damages, it would seem to be quite clear that the claimant ought at least to be made whole for his losses and expenditures.
discussed Cited as authority (rule) Al Burstein and Violet R. Burstein, Co-Partners Doing Business as Braeburn Company v. United States
8th Cir. · 1956 · confidence medium
At 91 C.J.S., United States, § 101e, page 240, it is stated: “Damages for breach of contract with the government must be proved with reasonable certainty, and the prima facie measure of such damages is the amount of loss which the injured party has sustained.” The rule for damages for breach of contract is discussed in United States v. Behan, 110 U.S. 338, 344, 345 , 4 S.Ct. 81, 83 , 28 L.Ed. 168 , where the Court states in part: “The prima facie measure of damages for the breach of a contract is the amount of the loss which the injured party has sustained thereby. * * * “ * * * As be…
discussed Cited as authority (rule) L. Albert & Son v. Armstrong Rubber Co.
2d Cir. · 1949 · confidence medium
Story Parchment Co. v. Paterson Parchment Paper Co., 282 U.S. 555, 563 , 51 S.Ct. 248 , 75 L.Ed. 544 . 12 . 110 U.S. 338, 345, 346 , 4 S.Ct. 81 , 28 L.Ed. 168 . 13 . 2 Conn. 485 . 14 . 108 Conn. 683 , 145 A. 273 . 15 .
discussed Cited as authority (rule) United States v. Penn Foundry & Manufacturing Co. (2×)
SCOTUS · 1949 · confidence medium
United States v. Behan, 110 U.S. 338, 345, 346, 347 ; Western Union Tel.
cited Cited as authority (rule) Modern Industrial Bank v. United States
Ct. Cl. · 1944 · confidence medium
United States v. Behan, 110 U. S. 338, 345, 346 .
cited Cited as authority (rule) Polar Steamship Corp. v. Inland Overseas Steamship Corp.
4th Cir. · 1943 · confidence medium
United States v. Behan, 110 U.S. 338, 345, 346, 347 , 4 S.Ct. 81 [ 28 L.Ed. 168 ]; Western Union Tel.
discussed Cited as authority (rule) Montrose Contracting Co. v. Westchester County
2d Cir. · 1938 · confidence medium
It will not be presumed. * * * The claimant might also have recovered the profits of the contract. * * * The prima facie measure of damages for the breach of a contract is the amount of the loss which the injured party has sustained thereby. * * * But when he elects to go for damages for the breach of the contract, the first and most obvious damage-to be shown is the amount which he has been induced to expend on the faith of the contract, including a fair allowance for his own time and services. * * * It does not lie, however, in the mouth of the party, who has voluntarily and wrongfully put a…
discussed Cited as authority (rule) Tross v. H. E. G. Clarke Co.
Mich. · 1936 · confidence medium
“Unless there is some artificial rule of law which has taken the place of natural justice in relation to the measure of damages, it would seem to be quite clear that the claimant ought at least to be made whole for his losses and expenditures.” United States v. Behan, 110 U. S. 338, 344 (4 Sup. Ct. 81.) Where profits are speculative, the measure of damages is the actual expenditures and value of services reasonably spent in a bona fide attempt to perform the contract or reasonably expended upon, the faith of the contract.
cited Cited as authority (rule) Stewart v. Hansen
Utah · 1923 · confidence medium
United States v. Behan, 110 U. S. 338, 345, 346, 347 ; Western Union Tel.
discussed Cited as authority (rule) Guerini Stone Co. v. P. J. Carlin Construction Co.
SCOTUS · 1919 · confidence medium
It is true that in answer to the objection of immateriality plaintiff’s counsel said: “I will show you a case where it says that the rule is that the plaintiff’s expenditure minus any materials which , he may have .on hand and plus any profits which he might have made” — evidently referring to United States v. Behan, 110 U. S. 338, 344, 346 ; but in responding to a further objection that the material could not be charged to defendant, plaintiff’s counsel insisted: "I propose to show that the defendant took it and has it,” ¿nd followed it up with proof to this effect.
discussed Cited as authority (rule) J. P. Smith Shoe Co. v. Curme-Feltman Shoe Co. (2×)
unknown court · 1918 · confidence medium
There is nothing in the term ‘profits,’ that excludes their being given in evidence, more than any other item of damages; but proof of them is made to depend, like all other proof in relation to damages, upon the fact that the loss of them is the natural and direct result of the injury, and not á remote consequence; and the language of the court, in the last case, is significant: ‘that if reasonable proof be given that the plaintiff would have made the profits, that is, that those profits were the direct result of the performance by the defendant, and the loss the direct result of the b…
cited Cited as authority (rule) Blair v. Brownstone Oil & Refining Co.
Cal. Ct. App. · 1917 · confidence medium
The rule which supports the judgment in this action is well expressed in United States v. Behan, 110 U. S. 338, 345, 347 , [ 28 L.
discussed Cited as authority (rule) Jones v. Lanier
Ala. · 1916 · confidence medium
This loss, however, he is clearly entitled to recover in all cases, unless the other party, who has voluntarily stopped the performance of the contract, can show the contrary. * * * But failure to prove profits will not prevent the party from recovering his losses for actual outlay and expenditure.” —U. S. v. Behan, 110 U. S. 338, 344, 345 , 4 Sup. Ct. 81, 83 ( 28 L.
cited Cited as authority (rule) Hagan v. Nashville Trust Co.
Tenn. · 1910 · confidence medium
United States v. Behan, 110 U. S., 338, 345, 346, 347 (4 Sup. Ct., 81) 28 L.
cited Cited as authority (rule) River Spinning Co. v. Atlantic Mills
circtdri · 1907 · confidence medium
The proper rule of dámages in this case I find to be that stated in United States v. Behan, 110 U. S. 338, 344, 345, 346 , 4 Sup. Ct. 81, 83 ( 28 L.
cited Cited as authority (rule) Choctaw, Oklahoma & Gulf Railroad v. Jacobs
Okla. · 1905 · confidence medium
(United States v. Behan, 110 U. S. 338, 345, 346, 347 ; Western Union Tel.
cited Cited as authority (rule) Tootle v. Kent
unknown court · 1903 · confidence medium
(United States v. Behan, 110 U. S. 338, 345, 346, 347 ; Western Union Tel.
discussed Cited as authority (rule) Speirs v. Union Drop Forge Co. (2×) also: Cited "see"
unknown court · 1901 · confidence medium
Before considering what the evidence was it is worth remarking that when it is established that such a contract has been made and that under it the plaintiff has been idle for months in constant expectation of orders that never came, it reasonably may be presumed by the judge of facts that the plaintiff’s loss has been substantial, — indeed maintaining the shop and waiting is an expenditure toward the performance of the contract to be recovered under the rule in United States v. Behan, 110 U. S. 338, 344, 345 , cited by the defendant, — and it would be unjust to turn the plaintiff off wi…
cited Cited as authority (rule) Cincinnati Siemens-Lungren Gas Illuminating Co. v. Western Siemens-Lungren Co.
SCOTUS · 1894 · confidence medium
United States v. Behan, 110 U. S. 338, 345, 346, 347 ; Western Union Tel.
cited Cited as authority (rule) Howard v. Stillwell & Bierce Manufacturing Co.
SCOTUS · 1891 · confidence medium
United States v. Behan, 110 U. S. 338, 345, 346, 347 ; Western Union Tel.
examined Cited "see" Agam v. Gavra (3×)
Cal. Ct. App. · 2015 · signal: see · confidence high
(Cederberg v. Robison (1893) 100 Cal. 93, 99 [34 R 625] (Cederberg); see United States v. Behan (1884) 110 U.S. 338, 345-346 [ 28 L.Ed. 168 , 4 S.Ct. 81 ] (Behan) [nonbreaching party’s damages include “actual outlay and expenditure”].) This measure of damages often is referred to as “reliance damages.” (US Ecology, Inc. v. State of California (2005) 129 Cal.App.4th 887, 907 [ 28 Cal.Rptr.3d 894 ]; see Rest.2d Contracts, § 349.) It has been held to apply where, as here, “one party to an established business association fails and refuses to carry out the terms of the agreement, and …
examined Cited "see" GULF GROUP GENERAL ENTERPRISES CO. W.L.L., Plaintiff, v. UNITED STATES, Defendant (6×)
Fed. Cl. · 2013 · signal: see · confidence high
See United States v. Behan, 110 U.S. 338 , 4 S.Ct. 81 , 28 L.Ed. 168 (1884).
examined Cited "see" American Capital Corp. v. United States (6×) also: Cited "see, e.g."
Fed. Cl. · 2005 · signal: see · confidence high
See American Capital II, 59 Fed.Cl. at 580 -82 (citing United States v. Behan, 110 U.S. 338, 344-45 , 4 S.Ct. 81 , 28 L.Ed. 168 (1884) (holding the non-breaching party may always recover the “loss of actual outlay and expense.”)); RESTATEMENT § 349 (the essential reliance may be equated with the contract price paid for performance).
examined Cited "see" American Capital Corp. v. United States (6×) also: Cited "see, e.g."
Fed. Cl. · 2005 · signal: see · confidence high
See American Capital II, 59 Fed.Cl. at 580 -82 (citing United States v. Behan, 110 U.S. 338, 344-45 , 4 S.Ct. 81 , 28 L.Ed. 168 (1884) (holding the non-breaching party may always recover the “loss of actual outlay and expense.”)); Restatement § 349 (the essential reliance may be equated with the contract price paid for performance).
examined Cited "see" LaSalle Talman Bank, F.S.B. v. United States (9×) also: Cited "see, e.g."
Fed. Cl. · 1999 · signal: see · confidence high
See Behan, 110 U.S. at 345 , 4 S.Ct. 81 ; ATACS, 155 F.3d at 671 ; RTC v. FSLIC, 25 F.3d 1493 , 1505 (10th Cir.1994); Bausch & Lomb, 977 F.2d at 729 ; Restatement (Second) of Contracts § 371 cmt. a.
examined Cited "see" American Science & Engineering, Inc. v. United States (3×)
Ct. Cl. · 1985 · signal: see · confidence high
See United States v. Behan, 110 U.S. 338, 344 , 4 S.Ct. 81, 83 , 28 L.Ed. 168 (1884).
cited Cited "see" R. Zoppo Co. Inc. v. Commonwealth
Mass. · 1967 · signal: see · confidence high
See United States v. Behan, 110 U. S. 338, 344 .
discussed Cited "see" G. L. Christian and Associates v. The United States (2×)
Ct. Cl. · 1963 · signal: see · confidence high
Broadbent Portable Laundry Corp. v. United States, 56 Ct.Cl. 128, 132 (1921); see United States v. Behan, supra, 110 U.S. at p. 344 , 4 S.Ct. at p. 83 .
examined Cited "see" Davis v. Merrick (3×)
N.M. · 1959 · signal: see · confidence high
See United States v. Behan, 1884, 110 U.S. 338 , 4 S.Ct. 81 , 28 L.Ed. 168 ; Allen, Heaton & McDonald, Inc. v. Castle Farm Amusement Co., 1949, 151 Ohio St. 522 , 86 N.E.2d 782 , 17 A.L.R.2d 963 , and American Law Institute Restatement, Contracts, vol. 2, § 347.
examined Cited "see" Sofarelli Bros. v. Elgin (3×)
4th Cir. · 1942 · signal: see · confidence high
See United States v. Behan, 110 U.S. 338 , 4 S.Ct. 81 , 28 L.Ed. 168 ; Dravo Contracting Co. v. James Rees & Sons Co., 291 Pa. 387 , 140 A. 148 ; Grand Trunk Western Ry.
examined Cited "see" Kolker v. United States (3×)
D. Maryland · 1941 · signal: see · confidence high
See United States v. Behan, 110 U.S. 338, 342, 343 , 4 S.Ct. 81 , 28 L.Ed. 168 ; Grand Trunk *975 Western R.
cited Cited "see" Keeling-Easter Co. v. R. B. Dunning & Co.
Me. · 1915 · signal: see · confidence high
See U. S. v. Behan, 110 U. S., 338 .
examined Cited "see, e.g." Department of Transportation v. White Oak Corp. (3×)
Conn. · 2008 · signal: see also · confidence low
“Wrongful termination gives the wrongfully terminated party: (1) the right to acquiesce to the termination by rescinding the contract and to recover upon quantum meruit for its performance to date; (2) the right to keep the contract in force, be prepared to perform and seek damages plus the contract price; or (3) the right to treat the breach as terminating the contract and to sue for profits it would have realized from performing.” 2 S. Stein, Construction Law (2007) § 4.15 [5], pp. 4-152 through 4-153; see also United States v. Behan, 110 U.S. 338, 344-45 , 4 S. Ct. 81 , 28 L.
examined Cited "see, e.g." Nashville Lodging Co. v. Resolution Trust Corporation (3×)
D.C. Cir. · 1995 · signal: see also · confidence low
This backup remedy gives the plaintiff “the repayment of his expenditures in preparing-to perform and in part performance.” McCormick, Damages § 142 at 583; see also United States v. Behan, 110 U.S. 338, 344-45 , 4 S.Ct. 81, 83-84 , 28 L.Ed. 168 (1884) (non-breaching party may always recover “his loss of actual *246 outlay and expense,” even if lost profits are incapable of proof).
examined Cited "see, e.g." Kizas v. Webster (3×)
D.D.C. · 1982 · signal: see also · confidence low
Ohio 1963); see also United States v. Behan, 110 U.S. 338 , 4 S.Ct. 81 , 28 L.Ed. 168 (1884).
examined Cited "see, e.g." Hidalgo Properties, Inc. v. Wachovia Mortgage Co. (3×)
10th Cir. · 1980 · signal: see also · confidence low
See also United States v. Behan, 110 U.S. 338 , 4 S.Ct. 81 , 28 L.Ed. 168 (1833); L.
examined Cited "see, e.g." Hidalgo Properties, Inc. v. Wachovia Mortgage Company (3×)
10th Cir. · 1980 · signal: see also · confidence low
See also United States v. Behan, 110 U.S. 338 , 4 S.Ct. 81 , 28 L.Ed. 168 (1833); L.
cited Cited "see, e.g." McTernan v. LeTendre
Mass. App. Ct. · 1976 · signal: see also · confidence medium
See also United States v. Behan, 110 U. S. 338, 342-347 (1884); L.
examined Cited "see, e.g." United States Ex Rel. F. E. Robinson Co. of N. C., Inc. v. Alpha-Continental (3×)
E.D.N.C. · 1967 · signal: see also · confidence low
See also United States v. Behan, 110 U.S. 338 , 4 S.Ct. 81 , 28 L.Ed. 168 (1884).
examined Cited "see, e.g." French v. Nabob Silver-Lead Company (3×)
Idaho · 1960 · signal: see also · confidence low
See also United States v. Behan, 110 U.S. 338 , 4 S.Ct. 81 , 28 L.Ed. 168 .
examined Cited "see, e.g." United States ex rel. Farwell, Ozmun, Kirk & Co. v. Shea-Adamson Co. (3×)
D. Minnesota · 1937 · signal: see also · confidence low
See, also, U.S. v. Behan, 110 U.S. 338, 339 , 4 S.Ct. 81 , 28 L.Ed. 168 .
discussed Cited "see, e.g." Lake Shore & Michigan Southern Railway Co. v. Richards
unknown court · 1894 · signal: see also · confidence low
See, also, United States v. Behan, supra; Crabtree v. Messersmith, 19 Iowa, 179 ; Holloway v. Griffith, 32 id. 409; Dugan v. Anderson, 36 Md. 567 ; Burtis v. Thompson, 42 N. Y. 246 ; Howard v. Daly, 61 id. 362 ; Smoot’s case, 15 Wall. 36 ; Dingley v. Oler, 117 U. S. 503 .
Retrieving the full opinion text from the archive…
United States
v.
Behan
1126.
Supreme Court of the United States.
Feb 4, 1884.
110 U.S. 338
Mr. Solicitor- General {Mr. John S. Blair was with him) for appellant., Mr. J. W. Douglass for appellee.
Bradley.
Cited by 399 opinions  |  Published
Mt?. Justioe Bradley

delivered the opinion of the court.

Behan, the appellee and claimant, filed a petition in the court below, setting forth that on the 26th of December, 1879, one John Boy entered into a contract with C. W. Howell,' major of engineers of the United States army, to make certain improvements in the harbor of New Orleans (describing the same), and that the claimant and two other persons named became bondsmen for the faithful performance of the work; that on February 10th, 1881, the contract with Boy was annulled by the engineer office, and the bondsmen were notified that they had a right to continue the work under the contract if they desired to do so, and that the claimant complied with this suggestion and undertook the work; that he went to great expense in providing the requisite machinery,, materials, and labor for fulfilling the contract, but that in September, 1881, it being found, by the report of a board of engineers, that the plan of improve[*340] ment was a failure, without any fault of the claimant, the work was ordered to ¿¡ease; that thereupon the claimant stopped all operations, and disposed of the machinery and materials on hand upon the best terms possible, and sent to the "War Department an account of his outlay and expenses, and the value of his own time, claiming as due to him, after all just credits and offsets, the sum of $36,347.94, for which sum he prayed judgment.

The claimant afterwards filed an amended petition, in which the various transactions, and his operations under the contract,, were set forth in greater detail, showing amongst other things, that the amount of his ^expenses for machinery and tools, for materials, and for labor and operations carried on, after deducting the proceeds realized from the sale of the- plant remaining when the work was suspended, amounted to the sum of $33,192.90. The petition further alleged that the claimant . could have completed the work contemplated by the contract by a' further expense of $10,000, and that the amount which would then have been due therefor would have been $52,000,' leaving a profit to him of $8,807.10.

. The petition concluded as follows:

. “Your petitioner therefore respectfully shows that his reasonable and necessary expenditures upon the work above described amounted to $33,192.90, which sum represents the losses actually sustained by petitioner by reason of the defendants’ breach of the contract. And petitioner further sets forth that the reasonable and legitimate profits which he might have obtained but for the said breach of contract may be properly computed at $8,807.10, assuming $52,000 as the amount to be paid for the completed work. And petitioner further shows that he has not Received one dollar . from the defendants on account of said work, but that his elaim and accompanying accounts, presented to the engineer department, have been transmitted to this court by the Secretary of War.
“Your petitioner therefore alleges that he is entitled to receive . from the United States the sum of forty-two thousand dollars ($42,000) over and above all just credits and offsets. Wherefore he prays judgment for that amount.”

The Court of Claims found the material facts to be substan[*341] tially as stated in the petition. The contract of Roy is set forth in full in the findings, from which it appears that the contracting party was required to furnish and lay down an artificial covering of cane-mats over the sloping portion of the riverbed of 'the Mississippi in front of the third district of New Orleans, to extend outward to a depth.in the river not exceeding 100 feet, and to be paid therefor at the rate of 65 cents per square yard. The court finds that Roy prosecuted the work under the contract during the year 1880, but his .progress not being satisfactory to the engineer officers, the contract was, formally annulled, and the bondsmen notified as stated in the, petition. In March, 1881, Behan, the claimant, gave notice to Major Howell that he would undertake the work, and at his request the major gave him a description of the work to be done, estimated as not exceeding 17,000 or 80,000 square yards, which, at the contract price, would amount to from $50,000 to - $52,000. The court further finds as follows:

“ The contract was of such a character as to require extensive preparations and a large initial expenditure. The claimant made the necessary preparations for carrying on the work to completion and in procuring boats, tools, materials, and apparatus for its prosecution. He engaged actively in carrying out the contract on his part, incurred large expenditure for labor and materials, and • had for some timé proceeded with the work when the undertaking. was abandoned by the defendants and the work stopped without fault of the claimant, as set forth in the following letters.”

Then follows a copy of correspondence between the officers and the department of engineers, showing that a board of engineer officers was appointed to examine and report upon the plan of improvement under which the work of the claimant was being carried on, and that this board, on the 23d of September, 1881, reported their unanimous opinion that the object sought to be accomplished by the improvement had not been attained, and that under the then existing plan of operations, it could not be attained. On the 29th of September, 1881, the claimant received notice to discontinue the work, which he did at once, and gave Major Howell notice to that effect, and called his[*342] attention to the exposed situation of the machinery, materials, and other .property on hand, and-requested instructions respecting the same. No instructions appear to have been given. The court then finds as follows:

The claimant thereupon closed up his work and sold the materials which he had on hand. Nothing has been paid to him for work, materials, or losses.
“ The actual and reasonable expenditures by the claimant in the prosecution of his work, together with his unavoidable losses on the materials on hand at the time of the stoppage by the defendants, were equal to the full amount claimed therefor in his petition, .$33,192.20.
“ It does not appear from the evidence thereon on the one side and the other whether or hot the claimant would have made any actual profit over and above expenditures, or would have incurred actual loss had' he continued the work to the end and been paid the full contract price therefor.
“ CONCLUSION OK LAW.
“ Upon the foregoing findings of facts the court decides as a conclusion of law that the claimant is' entitled to recover the sum of $33,192.20.”

The government has appealed from this decree and complains of the rule of damages adopted by the court below. Counsel contend that, by making a claim for profits, the claimant asserts the existence of the contract as opposed to its rescission; and that in such case, the rule of damages, as settled in Speed's Case, 8 Wall. 77, is “.the difference between the cost of doing the work and what claimants were to receive for it, making reasonable reduction for the less time engaged, and for release from the care, trouble, risk, and responsibility attending á ftdl execution of the contract.” - And when such a claim is made, they contend that the burden of proof is on the claimant to show what the profits would have been; and as the Court of Claims expressly finds that it does not appear from the evidence whether or not the claimant would have made any profits, or would have incurred loss, therefore the[*343] claimant was not entitled to judgment for any amount whatever.

The manner in which this subject was viewed by the Court of Claims is shown by the following extract from its opinion:

“ Whatever rule may be adopted in calculating the damages to a contractor when, without his fault, the other party, during its progress, puts an end to the' contract before completion, the object is to indemnify him for his losses sustained and his gains prevented by the action of the party in fault, viewing these elements with relation to each other. The profits and losses must be determined according to the circumstances of the case and the subject-matter of the contract. The reasonable expenditures already incurred, the unavoidable losses incident to stoppage, the progress attained, the-unfinished part, and the probable cost of its completion, the whole contract price, and the estimated pecuniary result, favorable or unfavorable to him, had he been permitted or required to go on- and complete his contract, may be taken into consideration. Sickels’ Case, 1 C. Cls. R. 214 ; Speed’s Case, 2 C. Cls. R. 429 ; aifirmed on appeal, 8 Wall. 77, and 7 C. Cls. R. 93 ; Wilder’s Case, 5 C. Cls. R. 468 ; Bulkey’s Case, 7 C. Cls. R. 543 ; 19 Wall. 37 ; and 9 C. Cls. R. 81 ; Parish’s Case, 100 U. S. 500 ; Field’s Case, 16 C. Cls. R. 434 ; Moore & Krone’s Case, 17 C. Cls. R. 17; Power’s Case, 18 C. Cls. R. 493; Masterson v. Mayor, &c., of Brooklyn, 7 Hill, 61.
“ The amount of the claimant’s unavoidable expenditures and losses already incurred are set forth in the findings. But we can give him nothing on account of prospective profits, because none have been proved. So, for the same reason, we can deduct nothing from his expenditures on account of prospective losses-which he might 'have incurred had he not been relieved from completing his contract. ' This leaves his expenditures as the only damages proved to have resulted to him from the defendants’ breach of contract, and they are, therefore, the proper measure of damages under all the circumstances of the case.”

We think that these views, as applied to the case in hand, are substantially correct. The claimant has not received a dollar, either for what he did, dr for what he expended, except the proceeds of the property wkich remained on his hands when[*344] the performance óf the contract was stopped. Unless there is some artificial rule of law which has taken, the place of natural justice in relation to the measure of. damages, it would seem to be quite clear that the claimant ought at least to be made whole for his losses and expenditures. So far as appears, they were incurred in the fair endeavor to perform the contract which he assumed. If they were foolishly or unreasonably incurred, the government should have proven this fact. It will not be presumed. The court finds that his expenditures were reasonable. ' The claimant might also have recovered the profits of the contract if he had proven that any' direct, as distinguished from speculative, profits would have been realized. But this he failed to do; and the court below very properly restricted its award of damages to his actual expenditures and losses.

The prima facie measure of damages for the breach of a contract is the amount of the loss which the injured party has sustained thereby. If the breach consists in preventing the performance of the contract, without the fault of the other party, who is wiling to perform it, the loss of the latter will consist of two distinct items or grounds of. damage, namely: first, what he has already expended towards performance (less the value of materials on hand); secondly,"the profits that he would realize by performing the whole contract. The second item, profits, cannot always be' recovered. They may be too remote and speculative in their character, and therefore inca-' pable of that clear and direct- proof which the law requires. But when, in the language of Chief Justice Nelson, in the case of Masterson v. Mayor of Brooklyn, 7 Hill, 69, they áre “the direct and immediate fruits of the. contract,” they are free from this objection; they are then “ part and parcel of the contract itself, entering into and constituting a portion of its very elements ; something stipulated for, the right to the enjoyment of which is just as clear and plain as to'the fulfilment, of any other stipulation.” Still, in order to' furnish a ground of recovery in damages, they must be proved. If not proved, or if they are of such a remote and speculative character that they cannot be legally proved, the party is confined to his loss of actual outlay and expense. This loss, however, he is clearly entitled to re[*345] cover in all cases, unless the other party, who has voluntarily stopped the performance of the contract, can show the contrary.

The rule as stated in Speed’s case is only one aspect of the general rule. It is the rule as applicable to a particular case. As before stated, the primary measure of damages is the amount of the party’s loss; and this loss, as we have seen, may consist of two heads or classes of damage — actual outlay and anticipated profits. But failure to prove profits will not prevent the party from recovering his losses for actual outlay and expenditure. If he goes also for profits, then the rule applies as laid down in Speed’s case, and his ¡profits will be measured by “the difference between the cost of doing the work and what he was to receive for it,” &c. The claimant was not bound to go for profits, even though he counted for them in his petition. He might stop upon a showing of losses. The two heads of damage are distinct, though closely related. When profits are sought a recovery for outlay is included and something more. That something more is the profits. If the outlay equals or exceeds the amount to be,received, of course there can be no profits.,

When a party injured by the stoppage óf a contract elects to rescind it, then, it is true, he cannot recover any damages for a-breach of the contract, either for outlay or for loss of profits; he recovers .the value of his services actually performed as upon a quomtum meruit. There is then no question of losses or profits. But when lie elects to ga for damages for the breách of the contract, the first and most obvious damage to be shown is, the amount which he has been induced to expend on thq faith of the contract, including a fair allowance for his own time and services. If he chooses to go further, and claims for the loss of anticipated profits, he may do so, subject to the rules of law as to the character of profits which may be thus claimed. .It does not lie, however, in the mouth of the party, who has voluntarily and wrongfully put an end to the contract, to say that the party injured has not been damaged at least to the amount of what he has been induced fairly and in good faith to lay out and expend (including his own services), after ,mak[*346] ing allowance for the value of materials on hand; at least it does not he in the mouth of the party in fault to say this, unless he can show that the expenses of the party injured have been extravagant, and unnecessary for the purpose of carrying out the contract.

It is unnecessary to reviéw the authorities on this subject. Some of them are referred to in the extract made from the opinion of the court below; others may be found referred to in Sedgwick on the Measure of’Damages, in Smith’s Leading Cases, vol. 2, p. 36, &c. (notes to Cutter v. Powell); Addison on Contracts, §§ 881, 897. The cases usually referred to, and which, with many others, have been carefully examined, are Planché v. Colburn, 5 C. & P. 58 ; S. C. 8 Bing. 14; Masterson v. Mayor, &c., of Brooklyn, 7 Hill (N. Y.), 61; Goodman v. Pocock, 15 A. & E. 576; Hadley v. Baxendale, 9 Excheq. 341; Fletcher v. Tayleur, 17 C. B. 21; Smeed v. Ford, 1 El. & El. 602; Inchbald v. Western, &c., Coffee Company, 17 C. B. N. S. 733; Griffen v. Colver, 16 N. Y. 489 ; and the case of United States v. Speed, before referred to.

• It is iN be observed that when it is said in some of the books, that where one party puts an end to the contract, the other party cannot sue on the contract, hut must sue for the Avork actually done under it, as upon a qua/ntum meruit, this • only means that he cannot sue the party in fault upon the stipulations contained in the contract, for he himself has been prevented from performing his own part of the contract upon Avhich the stipulations depend. But surely, the wilful and wrongful putting an end to a contract, and preventing the other party from carrying it out, is itself a breach of the contract for which an action Avill lie for the recovery of all damage which the injured party has sustained. The distinction between those claims under a contract which result from a performance of it on, the part of the claimant, and those claims under'it which result from being prevented by the other party from performing it, has not always been attended to. The party Avho voluntarily and- wrongfully puts an end to a contract and pre\rents the other party from performing it, is es-topped from denying that the injured party has not been[*347] damaged to the extent of his actual loss and outlay fairly incurred.

The particular form of the petition in this case ought not to preclude the claimant from not recovering what was fairly .shown by the' evidence to be the damage sustained by him. Though it is true that he does pray judgment for damages arising. from loss of profits, yet he also prays judgment for the amount of his outlay and expenses less the amount realized from the sale of materials on .hand. The claim for profits, if not sustained by proof, ought not to preclude a recovery of the claim for losses sustained by outlay and expenses. In a proceeding like the present, in which the claimant sets forth, by way of petition, a plain statement of the facts without technical formality, and prays relief either in a general manner, or in an alternative or cumulative form, the court ought not to hold, the claimant to strict' technical rules of pleading, but should give to his statement a liberal interpretation, and afford him such relief as he may show himself substantially entitled to if within the fair scope of the claim as exhibited by the facts set forth in the petition.

We think that the judgment of the Court of Claims was right, and it

Is affirmed.