C.F.R. homeSearch C.F.R.
C.F.R.Title 47Chapter I—Federal Communications CommissionSubchapter C—Broadcast Radio ServicesPart 73—Radio Broadcast ServicesSubpart H—Rules Applicable to All Broadcast Stations

47 C.F.R. § 73.1610 (2026)

Equipment tests

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 2016 1citing case
At a glance

Courts have cited this section in 1 opinion since 2016.

(a) During the process of construction of a new broadcast station, the permittee, after notifying the FCC in Washington, D.C. may, without further authority from the FCC, conduct equipment tests for the purpose of making such adjustments and measurements as may be necessary to assure compliance with the terms of the construction permit, the technical provisions of the application therefore, the rules and regulations and the applicable engineering standards. For AM stations, equipment tests, including either a directional or nondirectional proof of performance required by the construction permit, may be conducted during daytime hours provided that the antenna system is first substantially tuned during the experimental period. The nondirectional proof shall be conducted with power adjusted to 25% of that specified in the permit for the authorized directional facilities or, if applicable, to such higher power as is specified in the same permit for authorized nondirectional facilities. For licensed stations, see § 73.1615, Operation During Modification of Facilities; and § 73.157, Antenna Testing During Daytime.

(b) The FCC may notify the permittee not to conduct equipment tests or may modify, cancel, suspend, or change the modes of testing or the dates and times for such tests in order to resolve interference complaints or when such action may appear to be in the public interest, convenience, and necessity.

(c) Equipment tests may be continued so long as the construction permit shall remain valid.

(d) The authorization for tests embodied in this section shall not be construed as constituting a license to operate but as a necessary part of construction.

[43 FR 32783, July 28, 1978, as amended at 47 FR 40174, Sept. 13, 1982; 50 FR 30947, July 31, 1985]
The 1 case that cites 47 C.F.R. § 73.1610 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENUnited States v. Hodson Broad., 666 F. App'x 624 (9th Cir. 2016).
cites § 73.1610 1×cited by 2 casesunpublished
Where it cites § 73.1610
“Because his construction permit contained a special condition requiring FCC approval before program testing—which was never granted—Hodson’s transmissions could not have been valid under 47 C.F.R. § 73.1620 . And because he transmitted at variance from the terms of his permit,…”
Later courts cite it for
“the fcc noted some material supporting the defendant's claimed inability to pay-the only downward criteria he argued-but also found that any consequent reduction was offset by multiple upward adjustments for intentional and repeated violations.” · 1 citing court

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com