C.F.R. homeSearch C.F.R.
C.F.R.Title 48Chapter 1—Federal Acquisition RegulationSubchapter B—Acquisition PlanningPart 11—Describing Agency NeedsSubpart 11.7—Variation in Quantity

48 C.F.R. § 11.702 (2026)

11.702 Construction contracts.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 2008 1citing case
At a glance

Courts have cited this section in 1 opinion since 2008.

Construction contracts may authorize a variation in estimated quantities of unit-priced items. When the variation between the estimated quantity and the actual quantity of a unit-priced item is more than plus or minus 15 percent, an equitable adjustment in the contract price shall be made upon the demand of either the Government or the contractor. The contractor may request an extension of time if the quantity variation is such as to cause an increase in the time necessary for completion. The contracting officer must receive the request in writing within 10 days from the beginning of the period of delay. However, the contracting officer may extend this time limit before the date of final settlement of the contract. The contracting officer shall ascertain the facts and make any adjustment for extending the completion date that the findings justify.

The 1 case that cites 48 C.F.R. § 11.702 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENBurchick Constr. Co. v. United States, 83 Fed. Cl. 12 (Fed. Cl. 2008).
cites § 11.702 1×cited by 7 cases
Where it cites § 11.702
“211-18 , ‘Variation in Estimated Quantity (Apr 1984),” was not incorporated into the contract (see 48 C.F.R. § 11.702 (2007)). While excavating the site, plaintiff removed thousands of cubic yards of rock in excess of the 100 cubic yard estimate.”
Later courts cite it for
“in order to decide how to apply the doctrine of contra proferentem, after a court finds contract terms to be ambiguous and 'susceptible to more than one reasonable interpretation,' the court must first determine whether the ambiguity is latent or patent.” · 2 citing courts

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com