C.F.R. homeSearch C.F.R.
C.F.R.Title 48Chapter 1—Federal Acquisition RegulationSubchapter H—Clauses and FormsPart 52—Solicitation Provisions and Contract ClausesSubpart 52.2—Text of Provisions and Clauses

48 C.F.R. § 52.217-8 (2026)

52.217-8 Option To Extend Services.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1998–2020 11citing cases
At a glance

Courts have cited this section in 11 opinions since 1998.

As prescribed in 17.208(f), insert a clause substantially the same as the following:

Option To Extend Services (NOV 1999)

The Government may require continued performance of any services within the limits and at the rates specified in the contract. These rates may be adjusted only as a result of revisions to prevailing labor rates provided by the Secretary of Labor. The option provision may be exercised more than once, but the total extention of performance hereunder shall not exceed 6 months. The Contracting Officer may exercise the option by written notice to the Contractor within ___ [insert the period of time within which the Contracting Officer may exercise the option].

(End of clause) [54 FR 29283, July 11, 1989, as amended at 64 FR 51843, Sept. 24, 1999]
The 11 cases that cite 48 C.F.R. § 52.217-8 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENDyncorp Int'l LLC v. United States, 113 Fed. Cl. 298 (Fed. Cl. 2013).
cites § 52.217-8 4×cited by 11 cases
Where it cites § 52.217-8
“The agency has taken the position that, even if PAE’s transition for each of these contracts began in September of 2013, there is still a very real possibility that DOS will have to unilaterally extend some 7 of the incumbent contracts pursuant to 48 C.F.R. § 52.217-8 to ensure…”
Later courts cite it for
“presumptively qualify for inclusion in the administrative record.” · 4 citing courts
cites § 52.217-8 1×cited by 177 cases
Where it cites § 52.217-8
“Before the option expired, HHS approved a six-month extension, called a “task order,” pursuant to 48 C.F.R. § 52.217-8 . That task order expired on October 10, 2011.”
The case’s holding
The voluntary cessation doctrine applies only in exceptional situations and requires the plaintiff to prove that the challenged activity is likely to recur.
Later courts cite it for
“with limited exceptions, not present here, issuance of a declaratory judgment deeming past conduct illegal is also not permissible as it would be merely advisory.” · 16 citing courts
3
GREENKeeton Corr., Inc. v. United States, 59 Fed. Cl. 753 (Fed. Cl. 2004).
cites § 52.217-8 1×cited by 105 cases
Where it cites § 52.217-8
“48 C.F.R. § 52.217-8 "Option to Extend Services" provides: "The Government may require continued performance of any services within the limits and at the rates specified in the contract.”
The case’s holding
An agency decision to override an automatic stay is arbitrary and capricious if the agency fails to consider using sole-source purchase orders to meet urgent needs.
Later courts cite it for
“must look to see whether the agency considered the relevant factors and made a rational determination.” · 6 citing courts
4
GREENArko Exec. Servs., Inc. v. United States, 553 F.3d 1375 (Fed. Cir. 2009).
cites § 52.217-8 1×cited by 63 cases
Where it cites § 52.217-8
“48 CFR § 52.217-8 (emphasis added). Section F.”
The case’s holding
A government agency may validly exercise a service extension clause at contract rates even if the extension exceeds the contract's total duration limit for renewal options.
Later courts cite it for
“summary judgment is appropriate where there is no genuine dispute as to any material fact and the moving party is entitled to judgment as a matter of law.” · 3 citing courts
5
GREENArko Exec. Servs., Inc. v. United States, 78 Fed. Cl. 420 (Fed. Cl. 2007).
cites § 52.217-8 2×cited by 7 cases
Where it cites § 52.217-8
“Defendant argues that the extension was properly made under the option to extend services clause found in one provision of the Federal Acquisition Regulation (FAR), 48 C.F.R. § 52.217-8 , while plaintiff asserts that the extension could have occurred only under the continuity of…”
6
GREENInnovation Dev. Enter. of Am., Inc. v. United States, 108 Fed. Cl. 711 (Fed. Cl. 2013).
cites § 52.217-8 1×cited by 16 cases
Where it cites § 52.217-8
“217-8, 48 C.F.R. § 52.217-8 (2012)). 6 Thus, in October 2004, the Air Force was on notice that by no later than March 31, 2010 it should have completed a procurement for CMAS services to follow the “old” contract, if CMAS contract services were indeed required on an ongoing…”
Later courts cite it for
“sole-source procurements may not be used when the circumstances justifying the award were due to the agency's own lack of advanced planning.” · 3 citing courts
7
GREENGreen Mgmt. Corp. v. United States, 42 Fed. Cl. 411 (Fed. Cl. 1998).
cites § 52.217-8 1×cited by 13 cases
Where it cites § 52.217-8
“48 C.F.R. § 52.217-8 (1987). Pursuant to this direction, the contract at issue, at Section F(l)(b), contains the following language: (1) The Government may extend the term of this contract at its sole discretion for three 1-year periods by written notice to the Contractor.”
8
GREENcooper/ports Am., LLC v. Sec'y of Def., 959 F.3d 1373 (Fed. Cir. 2020).
cites § 52.217-8 1×cited by 3 cases
Where it cites § 52.217-8
“65; see also 48 C.F.R. § 52.217-8 . In support of its claim, CPA asserts that Mr.”
Later courts cite it for
“we review de novo the board's conclusions of law, including grants of summary judgment, and the interpretation of a government contract.” · 2 citing courts
9
GREENStorage Tech. Corp. v. CCL Serv. Corp., 94 F. Supp. 2d 697 (D. Md. 2000).
cites § 52.217-8 3×cited by 2 cases
Where it cites § 52.217-8
“The Prime Contract adopts the language of 48 C.F.R. § 52.217-8 , allowing the government “to require continued performance of any services within the limits and at the rates specified in the contract” for up to six months.”
10
NO FLAGNorth Wind Site Servs., LLC v. United States, No. 19-148 (Fed. Cl. Apr. 26, 2019).
cites § 52.217-8 1×cited by 0 cases
Where it cites § 52.217-8
“These rates may be adjusted only as a result of revisions to prevailing labor rates provided by the Secretary of 6 48 C.F.R. § 52.217-8 , “Option to Extend Services” provides “[t]he Government may require continued performance of any services within the limits and at the rates…”
11
NO FLAGHarmonia Holdings Grp., LLC v. United States, No. 19-1421 (Fed. Cl. Apr. 26, 2020).
cites § 52.217-8 1×cited by 0 cases
Where it cites § 52.217-8
“48 C.F.R § 52.217-8 (2019). The RFQ provided the contracting officer three days within the contract end date to exercise the option.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199820092020

One bar per year. Tallest: 3 cases in 2013. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Fed. Cl.7Fed. Cir.21st Cir.1D. Md.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com