49 C.F.R. § 192.511

Test requirements for service lines

Read at: eCFRecfr.gov CornellLII GovInfogovinfo.gov CasesGoogle Scholar

(a) Each segment of a service line (other than plastic) must be leak tested in accordance with this section before being placed in service. If feasible, the service line connection to the main must be included in the test; if not feasible, it must be given a leakage test at the operating pressure when placed in service.

(b) Each segment of a service line (other than plastic) intended to be operated at a pressure of at least 1 p.s.i. (6.9 kPa) gage but not more than 40 p.s.i. (276 kPa) gage must be given a leak test at a pressure of not less than 50 p.s.i. (345 kPa) gage.

(c) Each segment of a service line (other than plastic) intended to be operated at pressures of more than 40 p.s.i. (276 kPa) gage must be tested to at least 90 p.s.i. (621 kPa) gage, except that each segment of a steel service line stressed to 20 percent or more of SMYS must be tested in accordance with § 192.507 of this subpart.

[35 FR 13257, Aug. 19, 1970, as amended by Amdt. 192-74, 61 FR 18517, Apr. 26, 1996; Amdt. 192-85, 63 FR 37504, July 13, 1998]
Notes of Decisions
Cited in 1 case, 2009–2009 · leading case: Columbia Gas of Ohio, Inc. v. Util. Workers Union of Am., Local 349, 329 F. App'x 1 (6th Cir. 2009).
Columbia Gas of Ohio, Inc. v. Util. Workers Union of Am., Local 349, 329 F. App'x 1 (6th Cir. 2009). “273 ), and that provide testing standards for service lines and plastic *4 pipelines ( 49 C.F.R. §§ 192.511 and 192.513). As for state law, Ohio has adopted the federal gas pipeline regulations (Ohio Admin.”