Connecticut General Statutes
Conn. Gen. Stat. § 42-158m (2026)
Adjudication of disputes in this state
✓ current as of May 2026
Find cases:
SyfertCases citing this section
CT-CGAcga.ct.gov (official)
JustiaTitle on Justia
CornellLII Search
CasesGoogle Scholar
Any provision in a construction contract for the performance of work on a construction site located in this state that purports to require that any dispute arising under the construction contract be mediated, arbitrated or otherwise adjudicated in or under the laws of a state other than Connecticut shall be void and of no effect, regardless of whether the construction contract was executed in this state.
(P.A. 99-153, S. 5; P.A. 11-149, S. 2.)
History: P.A. 11-149 substituted “mediated, arbitrated or otherwise adjudicated” for “adjudicated”.