“because the adjudication has been re-opened and the prior decision vacated, the decision that amponsah is challenging no longer marks 'the consummation of the agency's decisionmaking process,' and no legal consequences will flow from the prior decisions.”
756 citation events (756 in the last 25 years) across 71 distinct courts.
Strongest positive: Costa Soares v. United States Department of State (flmd, 2025-10-09)
Treatment trajectory · 2016 → 2026 · click a year to view as-of
2016 2021 2026
Top citers, strongest first. 50 distinct citers.
discussed Cited as authority (verbatim quote) mssd 2026
S.D. Miss. · 2026 · signal: see · quote attribution · 1 verbatim quote · confidence high
inal agency action is reviewable under the apa only if there are no adequate alternatives to apa review in court.
discussed Cited as authority (verbatim quote) Costa Soares v. United States Department of State
M.D. Fla. · 2025 · quote attribution · 1 verbatim quote · confidence high
n agency action is reviewable under the apa only if there are no adequate alternatives to apa review in court.
discussed Cited as authority (verbatim quote) American Federation of Government Employees, Afl-Cio v. Trump (2×) also: Cited "see, e.g."
9th Cir. · 2025 · signal: see · quote attribution · 1 verbatim quote · confidence high
nor is it an adequate alternative to apa review for a landowner to apply for a permit and then seek judicial review in the event of an unfavorable decision.
examined Cited as authority (verbatim quote) Gu v. McAleenan
D.D.C. · 2022 · quote attribution · 1 verbatim quote · confidence high
because the adjudication has been re-opened and the prior decision vacated, the decision that amponsah is challenging no longer marks 'the consummation of the agency's decisionmaking process,' and no legal consequences will flow from the prior decisions.
examined Cited as authority (verbatim quote) BCFS Health and Human Services v. United States Department of Labor (4×) also: Cited as authority (rule), Cited "see"
W.D. Tex. · 2022 · signal: see · quote attribution · 1 verbatim quote · confidence high
distill from precedents two conditions that generally must be satisfied for agency action to be 'final' under the apa
discussed Cited as authority (verbatim quote) Salinas v. Railroad Retirement Bd. (2×) also: Cited as authority (rule)
SCOTUS · 2021 · signal: see · quote attribution · 1 verbatim quote · confidence high
uch a 'count your bless- ings' argument is not an adequate rejoinder to the assertion of a right to judicial review
discussed Cited as authority (verbatim quote) Cambranis v. Pompeo
W.D. Tex. · 2020 · quote attribution · 1 verbatim quote · confidence high
even if final, an agency action is reviewable under the apa only if there are no adequate alternatives to apa review in court.
examined Cited as authority (verbatim quote) New Hampshire Lottery Commission, et al. Consolidated Case No. v. William Barr, in his official capacity as Attorney General of the United States of America, et al. (4×) also: Cited as authority (rule)
D.N.H. · 2019 · signal: see · quote attribution · 1 verbatim quote · confidence high
as we have long held, parties need not await enforcement proceedings before challenging final agency action where such proceedings carry the risk of 'serious criminal and civil penalties.
discussed Cited as authority (verbatim quote) N.H. Lottery Comm'n v. Barr (2×) also: Cited as authority (rule)
D.N.H. · 2019 · signal: see · quote attribution · 1 verbatim quote · confidence high
as we have long held, parties need not await enforcement proceedings before challenging final agency action where such proceedings carry the risk of 'serious criminal and civil penalties.
discussed Cited as authority (quoted) Kovarik v. Internal Revenue Services (IRS)
M.D. Penn. · 2025 · quote attribution · 1 verbatim quote · confidence low
inal agency action is reviewable under the apa only if there are no adequate alternative to apa review in court.
discussed Cited as authority (quoted) East Village New Deli Corp. v. United States Of America
S.D.N.Y. · 2021 · quote attribution · 1 verbatim quote · confidence low
n agency action is reviewable under the apa only if there are no adequate alternatives to apa review in court.
discussed Cited as authority (rule) Bushireddy v. Lyons
D.D.C. · 2026 · confidence medium
First, the action must “mark the consummation of the agency’s decisionmaking process”—i.e., it “must not be of a merely tentative or interlocutory nature.” U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 597 (2016) (quoting Bennett v. Spear, 520 U.S. 154 , 177–78 (1997)).
cited Cited as authority (rule) Widakuswara v. Lake
D.D.C. · 2026 · confidence medium
Cir. 2020) (quoting U.S. Army Corps. of Eng’rs v. Hawkes Co., 578 U.S. 590, 598 (2016).
discussed Cited as authority (rule) Alnaddaf v. Rubio
D.D.C. · 2026 · confidence medium
And as the Supreme Court has explained, the “possibility” that an agency “may revise” its decision “based on ‘new information’” “does not make an other- wise definitive decision nonfinal.” U.S. Army Corps of Eng’rs v. Hawkes Co., Inc., 578 U.S. 590, 598 (2016); accord Sackett v. EPA, 566 U.S. 120, 127 (2012).
discussed Cited as authority (rule) Hicks
M.D. La. · 2026 · confidence medium
Further, it is clear 50 578 U.S. 590 (2016). 51 Id. at 596 (noting that the applicants administratively appealed before seeking judicial review). 52 Darby v. Cisneros, 509 U.S. 137, 144 (1993) (quoting Williamson County Regional Planning Comm'n v. Hamilton Bank of Johnson City, 473 U.S. 172, 193 (1985)). 53 Id. at 154 (emphasis in original). 54 Rec.
cited Cited as authority (rule) Trump
E.D. Mo. · 2026 · confidence medium
Accountability Coal., Inc. v. Garland, 112 F.4th 507, 518 (8th Cir. 2024) (citing U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 597 (2016) (cleaned up)).
cited Cited as authority (rule) Allen
D. Maryland · 2026 · confidence medium
ECF 37 at 15–16 (citing U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 597 (2016); Bennett v. Spear, 520 U.S. 154, 177 (1997); and other authorities).
discussed Cited as authority (rule) Krishnan
N.D. Ind. · 2026 · confidence medium
For an agency action to be final and thus challengeable under the APA, it must represent the “consummation” of an agency’s decisionmaking process, and it must “determine rights or obligations.” Army Corps of Engineers v. Hawkes Co., 578 U.S. 590, 597 (2016).
discussed Cited as authority (rule) D.N.N. (2×)
D. Maryland · 2025 · confidence medium
U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 591 (2016) (citing Abbott Laboratories v. Gardner, 387 U.S. 136 (1967)).
discussed Cited as authority (rule) Florida Agency for Health Care Administration v. Administrator for the Centers for Medicare & Medicaid Services (2×)
11th Cir. · 2025 · confidence medium
Two conditions “generally must be satisfied for agency action to be ‘final’ under the APA.” U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 597 (2016).
examined Cited as authority (rule) Scotts Valley Band of Pomo Indians v. Burgum (3×) also: Cited "see"
D.D.C. · 2025 · confidence medium
The Supreme Court has described this inquiry as 11 “pragmatic.” U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 599 (2016) (cleaned up).
cited Cited as authority (rule) Planned Parenthood of Greater New York v. U.S. Department of Health and Human Services
D.D.C. · 2025 · confidence medium
U.S. Army Corps. of Eng’rs v. Hawkes, 578 U.S. 590, 599-600 (2016) 38 (quoting Abbott, 387 U.S. at 150 , and citing Frozen Foods, 351 U.S. at 44-45 ).
cited Cited as authority (rule) Hicks v. United States
M.D. La. · 2025 · confidence medium
United States Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 595 (2016).
cited Cited as authority (rule) Chen v. Vilsack
S.D.N.Y. · 2025 · confidence medium
The action “must not be of a merely tentative or interlocutory nature.” U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 597 (2016).
examined Cited as authority (rule) Columbia Riverkeeper v. Caswell, Jr. (4×) also: Cited "see", Cited "see, e.g."
D. Or. · 2025 · confidence medium
U.S. Army Corps of Eng'rs v. Hawkes Co, 578 U.S. 590, 599 (2016) (internal quotation marks and citation omitted); see Prutehi Litekyan: Save Ritidian v. U.S. Dep't of Airforce, 128 F.4th 1089, 1108 (9th Cir. 2025) (quoting Saliba v. U.S. Sec. & Exch.
discussed Cited as authority (rule) National Council of Agricultural Employers v. DOL
D.C. Cir. · 2025 · confidence medium
And second, the action must be one by which rights or obligations have been determined, or from which legal consequences will flow.” U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 597 (2016) (quoting Bennett v. Spear, 520 U.S. 154 , 177–78 (1997)).
cited Cited as authority (rule) University of Washington Medical Center v. Becerra
D.D.C. · 2025 · confidence medium
Cir. 2020) (quoting U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 599 (2016)).
discussed Cited as authority (rule) Kingdom v. Trump
D.D.C. · 2025 · confidence medium
Cir. 2020) (“The possibility of revision ‘is a common characteristic of agency action, and does not make an otherwise definitive decision nonfinal.’”) (quoting U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 598 (2016)).6 2.
discussed Cited as authority (rule) Ntl Ctr for Pub Plcy Rsrch v. SEC
5th Cir. · 2025 · confidence medium
Data Marketing, in turn, relied on the Supreme Court’s most recent explanation that for appellate review purposes, the finality of agency action, including its legal effect, “is generally a ‘pragmatic’ inquiry.” Id. at 854-55 (quoting U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 599 , 136 S. Ct. 1807, 1815 (2016)).
discussed Cited as authority (rule) Widakuswara v. Lake
D.D.C. · 2025 · confidence medium
Cir. 1986); U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 599 (2016) (noting the “‘pragmatic’ approach [the Supreme Court] ha[s] long taken to finality”). 23 As Judge Oetken concluded in granting the TRO, the defendants’ actions constitute final agency actions.
discussed Cited as authority (rule) Patrick Regan v. Secretary United States Navy
3rd Cir. · 2025 · confidence medium
And second, the action must be one by which rights or obligations have been determined, or from which legal consequences will flow.” U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 597 (2016) (quoting Bennett v. Spear, 520 U.S. 154 , 177–78 (1997)).
discussed Cited as authority (rule) Golden Gate Bridge, Highway and Transportation District v. United States Department of Labor
N.D. Cal. · 2025 · confidence medium
An agency action is only final if it satisfies two 21 conditions: (1) “the action must mark the consummation of the agency’s decisionmaking 22 process—it must not be of a merely tentative or interlocutory nature,” and (2) “the action must be 23 one by which rights or obligations have been determined, or from which legal consequences will 24 flow.” U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 597 (2016) (quoting Bennett v. 25 Spear, 520 U.S 154, 177–78 (1997)). “[A]n agency letter to a single entity that was purely 26 informational in nature and compelled no one to d…
cited Cited as authority (rule) Lewis v. United States
M.D. La. · 2025 · confidence medium
United States Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 595 (2016).
cited Cited as authority (rule) State of Texas v. DHS
5th Cir. · 2024 · confidence medium
These are the “Bennett prongs.” See, e.g., U.S. Army Corps of Eng’rs v. Hawkes Co., Inc., 578 U.S. 590, 599 (2016); Nat’l Pork Producers Council v. EPA, 635 F.3d 738 , 755–56 (5th Cir. 2011).
discussed Cited as authority (rule) Ntl Ctr for Pub Plcy Rsrch v. SEC (2×) also: Cited "see"
5th Cir. · 2024 · confidence medium
Data Marketing, in turn, relied on the Supreme Court’s most recent explanation that for appellate review purposes, the finality of agency action, including its legal effect, “is generally a ‘pragmatic’ inquiry.” Id. at 854-55 (quoting U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 599 , 136 S. Ct. 1807, 1815 (2016)).
discussed Cited as authority (rule) Community Associations Institute v. U.S. Department of the Treasury
E.D. Va. · 2024 · confidence medium
For agency action to be final, it (1) “must mark the consummation of the agency’s decisionmaking process;” and (2) “the action must be one by which rights or obligations have been determined, or from which legal consequences will flow.” United States Army Corps of Engineers v. Hawkes Co., Inc., 578 U.S. 590, 597 (2016) (quoting Bennett v. Spear, 520 U.S. 177 -178 (1997)).
discussed Cited as authority (rule) Comanche Nation v. Ware
W.D. Okla. · 2024 · confidence medium
Two conditions generally must be met for an agency’s action to be “final” under the APA: (1) “the action must mark the consummation of the agency’s decisionmaking process—it must not be of a merely tentative or interlocutory nature”; and (2) “the action must be one by which rights or obligations have been determined, or from which legal consequences will flow.” U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 597 (2016) (internal quotation marks omitted).
discussed Cited as authority (rule) Firearms Regulatory Accountability Coalition, Inc. v. Merrick B. Garland (2×) also: Cited "see"
8th Cir. · 2024 · confidence medium
For an agency action to be “final” under the APA, the action must (1) “mark the consummation of the agency’s decisionmaking process,” and (2) “be one by which rights or obligations have been determined, or from which legal consequences will flow.” U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 597 (2016) (quoting Bennett, 520 U.S. at 177–78).
examined Cited as authority (rule) The Chemours Company FC, LLC v. EPA (3×) also: Cited "see"
3rd Cir. · 2024 · confidence medium
Second, “the action must be one by which rights or obligations have been determined, or from which legal consequences will flow.” Id. at 178 (cleaned up); U.S. Army Corps of Eng’rs v. Hawkes Co., 4 Chemours asserts (and EPA does not contest) that venue would be proper in this Circuit because Chemours is headquartered in Delaware and has facilities in New Jersey that are affected by the health advisory. 5 Although the Supreme Court has said these two requirements “generally” apply, U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 597 (2016); Bennett v. Spear, 520 U.S. 154, 177…
cited Cited as authority (rule) Mills v. United States
D. Neb. · 2024 · confidence medium
Cir. 2018) (citing U.S. Army Corps of Engineers v. Hawkes Co., Inc., 578 U.S. 590, 597 (2016)).
examined Cited as authority (rule) Jake's Fireworks Inc. v. United States Consumer Product Safety Commission (3×) also: Cited "see"
4th Cir. · 2024 · confidence medium
And second, the action must be one by which rights or obligations have been determined, or from which legal consequences will flow.” U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 597 (2016) (quoting Bennett v. Spear, 520 U.S. 154 , 177–78 (1997)) (emphasis added).
examined Cited as authority (rule) White v. United States Environmental Protection Agency (3×) also: Cited "see", Cited "see, e.g."
E.D.N.C. · 2024 · confidence medium
U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 602 (2016) (Kennedy, J., concurring).
discussed Cited as authority (rule) State of Tenn. v. Dep't of Educ. (2×) also: Cited "see, e.g."
6th Cir. · 2024 · confidence medium
U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 599 (2016) (quoting Abbott Lab’ys v. Gardener, 387 U.S. 136, 149 (1967)).
discussed Cited as authority (rule) Mark Jones v. MSPB
4th Cir. · 2024 · confidence medium
In addition, as a general matter, the power to reopen “is a common characteristic of agency action[] and does not make an otherwise definitive decision nonfinal.” U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 598 (2016); see Berry v. U.S. Dep’t of Lab., 832 F.3d 627, 633 (6th Cir. 2016) (finding final agency action even though the Department could reopen its judgment in Berry’s workers’ compensation claim at any time, “either on its own initiative or in response to a[] request”); cf. 5 U.S.C. § 704 .
cited Cited as authority (rule) The Daily Wire, LLC v. United States Department of State
E.D. Tex. · 2024 · confidence medium
U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 599 (2016) (quoting Abbott Labs. v. Gardner, 387 U.S. 136, 149 (1967)).
cited Cited as authority (rule) The Daily Wire, LLC v. United States Department of State
E.D. Tex. · 2024 · confidence medium
U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 599 (2016) (quoting Abbott Labs. v. Gardner, 387 U.S. 136, 149 (1967)).
discussed Cited as authority (rule) Garcia v. Unknown Parties
D. Ariz. · 2024 · confidence medium
For an agency action to be final, 5 it "must mark the consummation of the agency's decisionmaking process—it must not be of 6 a merely tentative or interlocutory nature" and "the action must be one by which rights or 7 obligations have been determined, or from which legal consequences will flow." United 8 States Army Corps of Engineers v. Hawkes Co., 578 U.S. 590, 597 (2016), quoting Bennett 9 v. Spear, 520 U.S. 154 , 177–78 (1997).
discussed Cited as authority (rule) Corrales Jr. v. Dutschke
S.D. Cal. · 2024 · confidence medium
An agency action is “final” under the APA 22 when: (1) the action “mark[s] the consummation of the agency’s decisionmaking process”; 23 and (2) the action is “one by which rights or obligations have been determined, or from 24 which legal consequences will flow.” U.S. Army Corps of Engineers v. Hawkes Co., 25 578 U.S. 590, 597 (2016) (quoting Bennett v. Spear, 520 U.S. 154 , 177–78 (1997)). 26 Defendants contend the Complaint fails at the inquiry’s second step.
cited Cited as authority (rule) Eb5 Holdings Inc. v. Jaddou
D.D.C. · 2024 · confidence medium
Cir. 2020) (first quoting U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 599 (2016); and then quoting Cal. Cmtys.
discussed Cited as authority (rule) Haleem v. Department of Defense
D.D.C. · 2024 · confidence medium
It is well established that to be “final,” an agency action must both “mark the consummation of the agency’s decisionmaking process” and “be one by which rights or obligations have been determined or from which legal consequences will flow.” U.S. Army Corps of Eng’rs v. Hawkes Co., 578 U.S. 590, 597 (2016) (quoting Bennett v. Spear, 520 U.S. 154 , 177–78 (1997)).
UNITED STATES ARMY CORPS OF ENGINEERS, Petitioner
v.
HAWKES CO., INC., Et Al.
David R. Cooper, Chief Counsel, United States Army, Corps of Engineers, Washington, DC, Donald B. Verrilli, Jr., Solicitor General, John C. Cruden, Assistant Attorney General, Malcolm L. Stewart, Deputy Solicitor General, Ginger D. Anders, Assistant to the Solicitor General, Aaron P. Avila, Jennifer Scheller Neumann, Robert J. Lundman, Attorneys, Department of Justice, Washington, DC, for petitioner., Nancy Quattlebaum Burke, Gregory R. Mertz, of counsel, Gray Plant Mooty, Minneapolis, MN, M. Reed Hopper, Pacific Legal Foundation, Sacramento, CA, Mark Miller, Pacific Legal Foundation, Palm Beach Gardens, FL, for respondents.
Roberts, Kagan.
Cited by 285 opinions  |  Published
2 passages pin-cited by 2 cases
Pinpoint authority: bottom 78%
Citer courts: S.D. New York (1) · M.D. Pennsylvania (1)

Lead Opinion

Chief Justice ROBERTS delivered the opinion of the Court.

The Clean Water Act regulates the discharge of pollutants into "the waters of the United States." 33 U.S.C. §§ 1311(a), 1362(7), (12). Because it can be difficult to determine whether a particular parcel of property contains such waters, the U.S. Army Corps of Engineers will issue to property owners an "approved jurisdictional determination" stating the agency's definitive view on that matter. See 33 CFR § 331.2 and pt. 331, App. C (2015). The question presented is whether that determination is final agency action judicially reviewable under the Administrative Procedure Act, 5 U.S.C. § 704.

I

A

The Clean Water Act prohibits "the discharge of any pollutant" without a permit into "navigable waters," which it defines, in turn, as "the waters of the United States." 33 U.S.C. §§ 1311(a), 1362(7), (12). During the time period relevant to this case, the U.S. Army Corps of Engineers defined the waters of the United States to include land areas occasionally or regularly saturated with water-such as "mudflats, sandflats, wetlands, sloughs, prairie potholes, wet meadows, [and] playa lakes"-the "use, degradation or destruction of which could affect interstate or foreign commerce." 33 CFR § 328.3(a)(3) (2012). The Corps has applied that definition to assert jurisdiction over "270-to-300 million acres of swampy lands in the United States-including half of Alaska and an area the size of California in the lower 48 States."

[*1812] Rapanos v. United States, 547 U.S. 715, 722, 126 S.Ct. 2208, 165 L.Ed.2d 159 (2006) (plurality opinion).[1]

It is often difficult to determine whether a particular piece of property contains waters of the United States, but there are important consequences if it does. The Clean Water Act imposes substantial criminal and civil penalties for discharging any pollutant into waters covered by the Act without a permit from the Corps. See 33 U.S.C. §§ 1311(a), 1319(c), (d), 1344(a). The costs of obtaining such a permit are significant. For a specialized "individual" permit of the sort at issue in this case, for example, one study found that the average applicant "spends 788 days and $271,596 in completing the process," without "counting costs of mitigation or design changes." Rapanos, 547 U.S., at 721, 126 S.Ct. 2208. Even more readily available "general" permits took applicants, on average, 313 days and $28,915 to complete. Ibid. See generally 33 CFR § 323.2(h) (limiting "general" permits to activities that "cause only minimal individual and cumulative environmental impacts").

The Corps specifies whether particular property contains "waters of the United States" by issuing "jurisdictional determinations" (JDs) on a case-by-case basis. § 331.2. JDs come in two varieties: "preliminary" and "approved." Ibid. While preliminary JDs merely advise a property owner "that there may be waters of the United States on a parcel," approved JDs definitively "stat[e] the presence or absence" of such waters. Ibid. (emphasis added). Unlike preliminary JDs, approved JDs can be administratively appealed and are defined by regulation to "constitute a Corps final agency action." §§ 320.1(a)(6), 331.2. They are binding for five years on both the Corps and the Environmental Protection Agency, which share authority to enforce the Clean Water Act. See 33 U.S.C. §§ 1319, 1344(s) ; 33 CFR pt. 331, App. C ; EPA, Memorandum of Agreement: Exemptions Under Section 404(F) of the Clean Water Act § VI-A (1989) (Memorandum of Agreement).

B

Respondents are three companies engaged in mining peat in Marshall County, Minnesota. Peat is an organic material that forms in waterlogged grounds, such as wetlands and bogs. See Xuehui & Jinming, Peat and Peatlands, in 2 Coal, Oil Shale, Natural Bitumen, Heavy Oil and Peat 267-272 (G. Jinsheng ed. 2009) (Peat and Peatlands). It is widely used for soil improvement and burned as fuel. Id., at 277. It can also be used to provide structural support and moisture for smooth, stable greens that leave golfers with no one to blame but themselves for errant putts. See Monteith & Welton, Use of Peat and Other Organic Materials on Golf Courses, 13 Bulletin of the United States Golf Association Green Section 90, 95-100 (1933). At the same time, peat mining can have significant environmental and ecological impacts, see Peat and Peatlands 280-281, and therefore is regulated by both federal and state environmental protection agencies, see, e.g., Minn.Stat. § 103G.231 (2014).

Respondents own a 530-acre tract near their existing mining operations. The tract includes wetlands, which respondents believe contain sufficient high quality peat, suitable for use in golf greens, to extend[*1813] their mining operations for 10 to 15 years. App. 8, 14-15, 31.

In December 2010, respondents applied to the Corps for a Section 404 permit for the property. Id., at 15. A Section 404 permit authorizes "the discharge of dredged or fill material into the navigable waters at specified disposal sites." 33 U.S.C. § 1344(a). Over the course of several communications with respondents, Corps officials signaled that the permitting process would be very expensive and take years to complete. The Corps also advised respondents that, if they wished to pursue their application, they would have to submit numerous assessments of various features of the property, which respondents estimate would cost more than $100,000. App. 16-17, 31-35.

In February 2012, in connection with the permitting process, the Corps issued an approved JD stating that the property contained "water of the United States" because its wetlands had a "significant nexus" to the Red River of the North, located some 120 miles away. Id., at 13, 18, 20. Respondents appealed the JD to the Corps' Mississippi Valley Division Commander, who remanded for further factfinding. On remand, the Corps reaffirmed its original conclusion and issued a revised JD to that effect. Id., at 18-20; App. to Pet. for Cert. 44a-45a.

Respondents then sought judicial review of the revised JD under the Administrative Procedure Act (APA), 5 U.S.C. § 500 et seq. The District Court dismissed for want of subject matter jurisdiction, holding that the revised JD was not "final agency action for which there is no other adequate remedy in a court," as required by the APA prior to judicial review, 5 U.S.C. § 704. 963 F.Supp.2d 868, 872, 878 (Minn.2013). The Court of Appeals for the Eighth Circuit reversed, 782 F.3d 994, 1002 (2015), and we granted certiorari, 577 U.S. ----, 136 S.Ct. 615, 193 L.Ed.2d 495 (2015).

II

The Corps contends that the revised JD is not "final agency action" and that, even if it were, there are adequate alternatives for challenging it in court. We disagree at both turns.

A

In Bennett v. Spear, 520 U.S. 154, 117 S.Ct. 1154, 137 L.Ed.2d 281 (1997), we distilled from our precedents two conditions that generally must be satisfied for agency action to be "final" under the APA. "First, the action must mark the consummation of the agency's decisionmaking process-it must not be of a merely tentative or interlocutory nature. And second, the action must be one by which rights or obligations have been determined, or from which legal consequences will flow." Id., at 177-178, 117 S.Ct. 1154 (internal quotation marks and citation omitted).[2]

The Corps does not dispute that an approved JD satisfies the first Bennett condition. Unlike preliminary JDs-which are "advisory in nature" and simply indicate that "there may be waters of the United States" on a parcel of property, 33 CFR § 331.2 -an approved JD clearly "mark[s] the consummation" of the Corps' decisionmaking process on that question, Bennett, 520 U.S., at 178, 117 S.Ct. 1154 (internal quotation marks omitted). It is issued after extensive factfinding by the Corps regarding the physical and hydrological characteristics of the property, see[*1814] U.S. Army Corps of Engineers, Jurisdictional Determination Form Instructional Guidebook 47-60 (2007), and is typically not revisited if the permitting process moves forward. Indeed, the Corps itself describes approved JDs as "final agency action," see 33 CFR § 320.1(a)(6), and specifies that an approved JD "will remain valid for a period of five years," Corps, Regulatory Guidance Letter No. 05-02, § 1(a), p. 1 (June 14, 2005) (2005 Guidance Letter); see also 33 CFR pt. 331, App. C.

The Corps may revise an approved JD within the five-year period based on "new information." 2005 Guidance Letter § 1(a), at 1. That possibility, however, is a common characteristic of agency action, and does not make an otherwise definitive decision nonfinal. See Sackett v. EPA, 566 U.S. ----, ----, 132 S.Ct. 1367, 1372, 182 L.Ed.2d 367 (2012) ; see also National Cable & Telecommunications Assn. v. Brand X Internet Services, 545 U.S. 967, 981, 125 S.Ct. 2688, 162 L.Ed.2d 820 (2005). By issuing respondents an approved JD, the Corps for all practical purposes "has ruled definitively" that respondents' property contains jurisdictional waters. Sackett, 566 U.S., at ----, 132 S.Ct., at 1374-1375 (GINSBURG, J., concurring).

The definitive nature of approved JDs also gives rise to "direct and appreciable legal consequences," thereby satisfying the second prong of Bennett , 520 U.S., at 178, 117 S.Ct. 1154. Consider the effect of an approved JD stating that a party's property does not contain jurisdictional waters-a "negative" JD, in Corps parlance. As noted, such a JD will generally bind the Corps for five years. See 33 CFR pt. 331, App. C ; 2005 Guidance Letter § 1. Under a longstanding memorandum of agreement between the Corps and EPA, it will also be "binding on the Government and represent the Government's position in any subsequent Federal action or litigation concerning that final determination." Memorandum of Agreement §§ IV-C-2, VI-A. A negative JD thus binds the two agencies authorized to bring civil enforcement proceedings under the Clean Water Act, see 33 U.S.C. § 1319, creating a five-year safe harbor from such proceedings for a property owner. Additionally, although the property owner may still face a citizen suit under the Act, such a suit-unlike actions brought by the Government-cannot impose civil liability for wholly past violations. See §§ 1319(d), 1365(a) ; Gwaltney of Smithfield, Ltd. v. Chesapeake Bay Foundation, Inc., 484 U.S. 49, 58-59, 108 S.Ct. 376, 98 L.Ed.2d 306 (1987). In other words, a negative JD both narrows the field of potential plaintiffs and limits the potential liability a landowner faces for discharging pollutants without a permit. Each of those effects is a "legal consequence[ ]" satisfying the second Bennett prong. 520 U.S., at 178, 117 S.Ct. 1154 ; see also Sackett, 566 U.S., at ----, 132 S.Ct., at 1371.

It follows that affirmative JDs have legal consequences as well: They represent the denial of the safe harbor that negative JDs afford. See 5 U.S.C. § 551(13) (defining "agency action" to include an agency "rule, order, license, sanction, relief, or the equivalent," or the "denial thereof"). Because "legal consequences ... flow" from approved JDs, they constitute final agency action. Bennett, 520 U.S., at 178, 117 S.Ct. 1154 (internal quotation marks omitted).[3]

[*1815] This conclusion tracks the "pragmatic" approach we have long taken to finality. Abbott Laboratories v. Gardner, 387 U.S. 136, 149, 87 S.Ct. 1507, 18 L.Ed.2d 681 (1967). For example, in Frozen Food Express v. United States, 351 U.S. 40, 76 S.Ct. 569, 100 L.Ed. 910 (1956), we considered the finality of an order specifying which commodities the Interstate Commerce Commission believed were exempt by statute from regulation, and which it believed were not. Although the order "had no authority except to give notice of how the Commission interpreted" the relevant statute, and "would have effect only if and when a particular action was brought against a particular carrier," Abbott, 387 U.S., at 150, 87 S.Ct. 1507 we held that the order was nonetheless immediately reviewable, Frozen Food, 351 U.S., at 44-45, 76 S.Ct. 569. The order, we explained, "warns every carrier, who does not have authority from the Commission to transport those commodities, that it does so at the risk of incurring criminal penalties." Id., at 44, 76 S.Ct. 569. So too here, while no administrative or criminal proceeding can be brought for failure to conform to the approved JD itself, that final agency determination not only deprives respondents of a five-year safe harbor from liability under the Act, but warns that if they discharge pollutants onto their property without obtaining a permit from the Corps, they do so at the risk of significant criminal and civil penalties.

B

Even if final, an agency action is reviewable under the APA only if there are no adequate alternatives to APA review in court. 5 U.S.C. § 704. The Corps contends that respondents have two such alternatives: either discharge fill material without a permit, risking an EPA enforcement action during which they can argue that no permit was required, or apply for a permit and seek judicial review if dissatisfied with the results. Brief for Petitioner 45-51.

Neither alternative is adequate. As we have long held, parties need not await enforcement proceedings before challenging final agency action where such proceedings carry the risk of "serious criminal and civil penalties." Abbott, 387 U.S., at 153, 87 S.Ct. 1507. If respondents discharged fill material without a permit, in the mistaken belief that their property did not contain jurisdictional waters, they would expose themselves to civil penalties of up to $37,500 for each day they violated the Act, to say nothing of potential criminal liability. See 33 U.S.C. §§ 1319(c), (d) ; Sackett, 566 U.S., at ----, n. 1, 132 S.Ct., at 1370, n. 1 (citing 74 Fed.Reg. 626, 627 (2009) ). Respondents need not assume such risks while waiting for EPA to "drop the hammer" in order to have their day in court. Sackett, 566 U.S., at ----, 132 S.Ct., at 1372.

Nor is it an adequate alternative to APA review for a landowner to apply for a permit and then seek judicial review in the event of an unfavorable decision. As Corps officials indicated in their discussions with respondents, the permitting process can be arduous, expensive, and long. See Rapanos, 547 U.S., at 721, 126 S.Ct. 2208 (plurality opinion). On top of the standard permit application that respondents were required to submit, see 33 CFR § 325.1(d) (detailing contents of permit application), the Corps demanded that[*1816] they undertake, among other things, a "hydrogeologic assessment of the rich fen system including the mineral/nutrient composition and pH of the groundwater; groundwater flow spatially and vertically; discharge and recharge areas"; a "functional/resource assessment of the site including a vegetation survey and identification of native fen plan communities across the site"; an "inventory of similar wetlands in the general area (watershed), including some analysis of their quality"; and an "inventory of rich fen plant communities that are within sites of High and Outstanding Biodiversity Significance in the area." App. 33-34. Respondents estimate that undertaking these analyses alone would cost more than $100,000. Id., at 17. And whatever pertinence all this might have to the issuance of a permit, none of it will alter the finality of the approved JD, or affect its suitability for judicial review. The permitting process adds nothing to the JD.

The Corps nevertheless argues that Congress made the "evident [ ]" decision in the Clean Water Act that a coverage determination would be made "as part of the permitting process, and that the property owner would obtain any necessary judicial review of that determination at the conclusion of that process." Brief for Petitioner 46. But as the Corps acknowledges, the Clean Water Act makes no reference to standalone jurisdictional determinations, ibid., so there is little basis for inferring anything from it concerning the reviewability of such distinct final agency action. And given "the APA's presumption of reviewability for all final agency action," Sackett, 566 U.S., at ----, 132 S.Ct., at 1373, "[t]he mere fact" that permitting decisions are "reviewable should not suffice to support an implication of exclusion as to other[ ]" agency actions, such as approved JDs, Abbott, 387 U.S., at 141, 87 S.Ct. 1507 (internal quotation marks omitted); see also Sackett, 566 U.S., at ----, 132 S.Ct., at 1373 ("[I]f the express provision of judicial review in one section of a long and complicated statute were alone enough to overcome the APA's presumption of reviewability ..., it would not be much of a presumption at all").

Finally, the Corps emphasizes that seeking review in an enforcement action or at the end of the permitting process would be the only available avenues for obtaining review "[i]f the Corps had never adopted its practice of issuing standalone jurisdictional determinations upon request." Reply Brief 3; see also id., at 4, 23. True enough. But such a "count your blessings" argument is not an adequate rejoinder to the assertion of a right to judicial review under the APA.

The judgment of the Court of Appeals for the Eighth Circuit is affirmed.

It is so ordered.

Justice KENNEDY, with whom Justice THOMAS and Justice ALITO join, concurring.

My join extends to the Court's opinion in full. The following observation seems appropriate not to qualify what the Court says but to point out that, based on the Government's representations in this case, the reach and systemic consequences of the Clean Water Act remain a cause for concern. As Justice ALITO has noted in an earlier case, the Act's reach is "notoriously unclear" and the consequences to landowners even for inadvertent violations can be crushing. See Sackett v. EPA, 566 U.S. ----, ----, 132 S.Ct. 1367, 1374-1375, 182 L.Ed.2d 367 (2012) (concurring opinion).

An approved Jurisdictional Determination (JD) gives a landowner at least some measure of predictability, so long as the[*1817] agency's declaration can be relied upon. Yet, the Government has represented in this litigation that a JD has no legally binding effect on the Environmental Protection Agency's (EPA) enforcement decisions. It has stated that the memorandum of agreement between the EPA and the Army Corps of Engineers, which today's opinion relies on, does not have binding effect and can be revoked or amended at the Agency's unfettered discretion. Reply Brief 12; Tr. of Oral Arg. 16. If that were correct, the Act's ominous reach would again be unchecked by the limited relief the Court allows today. Even if, in an ordinary case, an agency's internal agreement with another agency cannot establish that its action is final, the Court is right to construe a JD as binding in light of the fact that in many instances it will have a significant bearing on whether the Clean Water Act comports with due process.

The Act, especially without the JD procedure were the Government permitted to foreclose it, continues to raise troubling questions regarding the Government's power to cast doubt on the full use and enjoyment of private property throughout the Nation.

1

In 2015, the Corps adopted a new rule modifying the definition of the scope of waters covered by the Clean Water Act in light of scientific research and decisions of this Court interpreting the Act. See Clean Water Rule: Definition of "Waters of the United States," 80 Fed.Reg. 37054, 37055-37056. That rule is currently stayed nationwide, pending resolution of claims that the rule is arbitrary, capricious, and contrary to law. See In re EPA, 803 F.3d 804, 807-809 (C.A.6 2015).

2

Because we determine that a JD satisfies both prongs of Bennett, we need not consider respondents' argument that an agency action that satisfies only the first may also constitute final agency action. See Brief for Respondents 19-20.

3

The Corps asserts that the Memorandum of Agreement addresses only "special case" JDs, rather than "mine-run" ones "of the sort at issue here." Reply Brief 12, n. 3. But the memorandum plainly makes binding "[a]ll final determinations," whether in "[s]pecial" or "[n]on-special" cases. Memorandum of Agreement §§ IV-C, VI-A; see also Corps, Memorandum of Understanding Geographical Jurisdiction of the Section 404 Program, 45 Fed.Reg. 45019, n. 1 (1980) ("[U]nder this [memorandum], except in special cases previously agreed to, the [Corps] is authorized to make a final determination ... and such determination shall be binding.").

Concurrence

Justice KAGAN, concurring.

I join the Court's opinion in full. I write separately to note that for me, unlike for Justice GINSBURG, see post, at 1817 (opinion concurring in part and concurring in judgment), the memorandum of agreement between the Army Corps of Engineers and the Environmental Protection Agency is central to the disposition of this case. For an agency action to be final, "the action must be one by which rights or obligations have been determined, or from which legal consequences will flow." Bennett v. Spear, 520 U.S. 154, 178, 117 S.Ct. 1154, 137 L.Ed.2d 281 (1997). As the Court states, the memorandum of agreement establishes that jurisdictional determinations (JDs) are "binding on the Government and represent the Government's position in any subsequent Federal action or litigation concerning that final determination." Memorandum of Agreement §§ IV-C-2, VI-A; ante, at 1814 (majority opinion). A negative JD thus prevents the Corps and EPA-the two agencies with authority to enforce the Clean Water Act-from bringing a civil action against a property owner for the JD's entire 5-year lifetime. Ante, at 1814 - 1815, and n. 3. The creation of that safe harbor, which binds the agencies in any subsequent litigation, is a "direct and appreciable legal consequence[ ]" satisfying the second prong of Bennett , 520 U.S., at 178, 117 S.Ct. 1154.

Justice GINSBURG, concurring in part and concurring in the judgment.

I join the Court's opinion, save for its reliance upon the Memorandum of Agreement between the Army Corps of Engineers and the Environmental Protection Agency. Ante, at 1814 - 1815, and n. 3 (construing the memorandum to establish that Corps jurisdictional determinations (JDs) are binding on the Federal Government in litigation for five years). The Court received scant briefing about this memorandum, and the United States does not share the Court's reading of it. See Reply Brief 12, n. 3 (memorandum "does not address mine-run Corps jurisdictional determinations of the sort at issue here"); Tr. of Oral Arg. 7 (same); id., at 9 (reading of the memorandum to establish that JDs have binding effect in litigation does not "reflec[t] current government policy"). But the JD at issue is "definitive," not "informal" or "tentative," Abbott Laboratories v. Gardner, 387 U.S. 136, 151, 87 S.Ct. 1507, 18 L.Ed.2d 681 (1967), and has "an immediate and practical impact,"

[*1818] Frozen Food Express v. United States, 351 U.S. 40, 44, 76 S.Ct. 569, 100 L.Ed. 910 (1956). See also ante, at 1814 - 1815.* Accordingly, I agree with the Court that the JD is final.

The syllabus constitutes no part of the opinion of the Court but has been prepared by the Reporter of Decisions for the convenience of the reader. See United States v. Detroit Timber & Lumber Co., 200 U.S. 321, 337, 26 S.Ct. 282, 50 L.Ed. 499.

Bennett v. Spear, 520 U.S. 154, 178, 117 S.Ct. 1154, 137 L.Ed.2d 281 (1997), contrary to Justice KAGAN's suggestion, ante, at 1817, (concurring opinion) does not displace or alter the approach to finality established by Abbott Laboratories v. Gardner, 387 U.S. 136, 149-151, 87 S.Ct. 1507, 18 L.Ed.2d 681 (1967), and Frozen Food Express v. United States, 351 U.S. 40, 44, 76 S.Ct. 569, 100 L.Ed. 910 (1956). Bennett dealt with finality quickly, and did not cite those pathmarking decisions.