Definitions

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 2008–2025 38citing cases
At a glance

Courts have cited this section in 38 opinions since 2008, 8 of them in the last five years.

The terms and definitions contained in 33 CFR Parts 320 through 330 are applicable to this part. In addition, the following terms are defined for the purposes of this part:

Affected party means a permit applicant, landowner, a lease, easement or option holder (i.e., an individual who has an identifiable and substantial legal interest in the property) who has received an approved JD, permit denial, or has declined a proffered individual permit.

Agent(s) means the affected party's business partner, attorney, consultant, engineer, planner, or any individual with legal authority to represent the appellant's interests.

Appealable action means an approved JD, a permit denial, or a declined permit, as these terms are defined in this section.

Appellant means an affected party who has filed an appeal of an approved JD, a permit denial or declined permit under the criteria and procedures of this part.

Approved jurisdictional determination means a Corps document stating the presence or absence of waters of the United States on a parcel or a written statement and map identifying the limits of waters of the United States on a parcel. Approved JDs are clearly designated appealable actions and will include a basis of JD with the document.

Basis of jurisdictional determination is a summary of the indicators that support the Corps approved JD. Indicators supporting the Corps approved JD can include, but are not limited to: indicators of wetland hydrology, hydric soils, and hydrophytic plant communities; indicators of ordinary high water marks, high tide lines, or mean high water marks; indicators of adjacency to navigable or interstate waters; indicators that the wetland or waterbody is of part of a tributary system; or indicators of linkages between isolated water bodies and interstate or foreign commerce.

Declined permit means a proffered individual permit, including a letter of permission, that an applicant has refused to accept, because he has objections to the terms and special conditions therein. A declined permit can also be an individual permit that the applicant originally accepted, but where such permit was subsequently modified by the district engineer, pursuant to 33 CFR 325.7, in such a manner that the resulting permit contains terms and special conditions that lead the applicant to decline the modified permit, provided that the applicant has not started work in waters of the United States authorized by such permit. Where an applicant declines a permit (either initial or modified), the applicant does not have a valid permit to conduct regulated activities in waters of the United States, and must not begin construction of the work requiring a Corps permit unless and until the applicant receives and accepts a valid Corps permit.

Denial determination means a letter from the district engineer detailing the reasons a permit was denied with prejudice. The decision document for the project will be attached to the denial determination in all cases.

Jurisdictional determination (JD) means a written Corps determination that a wetland and/or waterbody is subject to regulatory jurisdiction under Section 404 of the Clean Water Act (33 U.S.C. 1344) or a written determination that a waterbody is subject to regulatory jurisdiction under Section 9 or 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. 401 et seq.). Additionally, the term includes a written reverification of expired JDs and a written reverification of JDs where new information has become available that may affect the previously written determination. For example, such geographic JDs may include, but are not limited to, one or more of the following determinations: the presence or absence of wetlands; the location(s) of the wetland boundary, ordinary high water mark, mean high water mark, and/or high tide line; interstate commerce nexus for isolated waters; and adjacency of wetlands to other waters of the United States. All JDs will be in writing and will be identified as either preliminary or approved. JDs do not include determinations that a particular activity requires a DA permit.

Notification of Appeal Process (NAP) means a fact sheet that explains the criteria and procedures of the administrative appeal process. Every approved JD, permit denial, and every proffered individual permit returned for reconsideration after review by the district engineer in accordance with § 331.6(b) will have an NAP form attached.

Notification of Applicant Options (NAO) means a fact sheet explaining an applicant's options with a proffered individual permit under the administrative appeal process.

Permit denial means a written denial with prejudice (see 33 CFR 320.4(j)) of an individual permit application as defined in 33 CFR 325.5(b).

Preliminary JDs are written indications that there may be waters of the United States on a parcel or indications of the approximate location(s) of waters of the United States on a parcel. Preliminary JDs are advisory in nature and may not be appealed. Preliminary JDs include compliance orders that have an implicit JD, but no approved JD.

Proffered permit means a permit that is sent to an applicant that is in the proper format for the applicant to sign (for a standard permit) or accept (for a letter of permission). The term “initial proffered permit” as used in this part refers to the first time a permit is sent to the applicant. The initial proffered permit is not an appealable action. However, the applicant may object to the terms or conditions of the initial proffered permit and, if so, a second reconsidered permit will be sent to the applicant. The term “proffered permit” as used in this part refers to the second permit that is sent to the applicant. Such proffered permit is an appealable action.

Request for appeal (RFA) means the affected party's official request to initiate the appeal process. The RFA must include the name of the affected party, the Corps file number of the approved JD, denied permit, or declined permit, the reason(s) for the appeal, and any supporting data and information. No new information may be submitted. A grant of right of entry for the Corps to the project site is a condition of the RFA to allow the RO to clarify elements of the record or to conduct field tests or sampling for purposes directly related to the appeal. A standard RFA form will be provided to the affected party with the NAP form. For appeals of decisions related to unauthorized activities a signed tolling agreement, as required by 33 CFR 326.3(e)(1)(v), must be included with the RFA, unless a signed tolling agreement has previously been furnished to the Corps district office. The affected party initiates the administrative appeal process by providing an acceptable RFA to the appropriate Corps of Engineers division office. An acceptable RFA contains all the required information and provides reasons for appeal that meets the criteria identified in § 331.5.

Review officer (RO) means the Corps official responsible for assisting the division engineer or higher authority responsible for rendering the final decision on the merits of an appeal.

Tolling agreement refers to a document signed by any person who appeals an approved JD associated with an unauthorized activity or applies for an after-the-fact (ATF) permit, where the application is accepted and evaluated by the Corps. The agreement states that the affected party agrees to have the statute of limitations regarding any violation associated with that approved JD or application “tolled” or temporarily set aside until one year after the final Corps decision, as defined at § 331.10. No ATF permit application or administrative appeal associated with an unauthorized activity will be accepted until a tolling agreement is furnished to the district engineer.

The 20 cases that cite 33 C.F.R. § 331.2 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENU.S. Army Corps of Eng'rs v. Hawkes Co., 578 U.S. 590 (2016).
cites § 331.2 3×cited by 285 cases
Where it cites § 331.2
“See 33 CFR §331.2 and pt. 331, App. C (2015).”
The case’s holding
An agency action is final when it marks the consummation of the agency's decision-making process and determines legal rights or obligations.
Later courts cite it for
“the action must mark the consummation of the agency's decisionmaking process-it must not be of a merely tentative or interlocutory nature” · 12 citing courts
2
GREENNat'l Ass'n of Home Builders v. Env't Prot. Agency, 786 F.3d 34 (D.C. Cir. 2015).
cites § 331.2 6×cited by 42 cases
Where it cites § 331.2
“33 C.F.R. § 331.2 (emphasis added). Preliminary JDs are usually issued at the request of landowners wishing “to voluntarily waive or set aside questions regarding CWA[] jurisdiction” over their property, such as where jurisdiction is clear or is otherwise not worth contesting.”
The case’s holding
Issue preclusion bars relitigation of a jurisdictional dismissal unless a material change following the dismissal cures the original jurisdictional deficiency.
Later courts cite it for
“only if a material change following dismissal cured the original jurisdictional deficiency.” · 7 citing courts
cites § 331.2 3×cited by 65 cases
Where it cites § 331.2
“; see also Jurisdictional Determinations, Corps Regulatory Guidance Letter 08-02, at 1 (June 26, 2008) (“An approved [jurisdictional determination] is an official Corps determination that jurisdictional [waters under the CWA] are either present or absent on a particular site”).”
The case’s holding
An agency jurisdictional determination is not final agency action under the APA if it does not impose new obligations, deny existing rights, or fix a legal relationship.
Later courts cite it for
“finality is a jurisdictional requirement to obtaining judicial review under the apa.” · 4 citing courts
4
GREENNat'l Ass'n of Home Builders v. Env't Prot. Agency, 667 F.3d 6 (D.C. Cir. 2011).
cites § 331.2 1×cited by 124 cases
Where it cites § 331.2
“2011); 33 C.F.R. § 331.2 (“Approved jurisdictional determination means a Corps document stating the presence or absence of waters of the United States on a parcel or a written statement and map identifying the limits of waters of the United States on a parcel.”
The case’s holding
An association lacks standing if it fails to allege concrete and particularized injuries or operational costs beyond those normally expended to carry out its advocacy mission.
Later courts cite it for
“while the burden of production to establish standing is more relaxed at the pleading stage than at summary judgment, a plaintiff must nonetheless allege 'general factual allegations of injury resulting from the defendant's conduct' (notwithstanding 'the court presumes that general allegations embrace the specific facts that are necessary to support the claim').” · 12 citing courts
5
GREENHawkes Co. v. United States Army Corps of Engineers, 782 F.3d 994 (8th Cir. 2015).
cites § 331.2 2×cited by 19 cases
Where it cites § 331.2
“See 33 C.F.R. §§ 331.2 , 331.3, 331.6. In October 2012, the Corps’ Deputy Commanding General for Civil and Emergency Operations sustained the appeal, concluding after detailed analysis that the administrative record “does not support [the District’s] determination that the…”
Later courts cite it for
“this is a unique aspect of the cwa; most laws do not require the hiring of expert consultants to determine if they even apply to you or your property” · 3 citing courts
6
GREENBenham v. Ozark Materials River Rock, LLC, 885 F.3d 1267 (10th Cir. 2018).
cites § 331.2 1×cited by 26 cases
Where it cites § 331.2
“See 33 C.F.R. §§ 331.2 , 331.12 (2017). Moreover, Section 505 contains the "diligently prosecuting" requirement, not an administrative exhaustion requirement.”
Later courts cite it for
“to satisfy the traceability requirement, the defendant's conduct must have caused the injury.” · 3 citing courts
7
GREENShort v. United States Army Corps of Engineers, 613 F. Supp. 2d 103 (D.D.C. 2009).
cites § 331.2 1×cited by 21 cases
Where it cites § 331.2
“” 33 C.F.R. § 331.2 . Section 404 is codified at 33 U.”
Later courts cite it for
“the causation requirement is missing when disclosure results not from the suit but from delayed administrative processing.” · 5 citing courts
8
GREENBelle Co. v. United States Army Corps of Engineers, 761 F.3d 383 (5th Cir. 2014).
cites § 331.2 1×cited by 20 cases
Where it cites § 331.2
“33 C.F.R. § 331.2 . Once a JD has proceeded through the administrative appeal process, the final JD is not subject to further formal review by the agency.”
Later courts cite it for
“if there is no final agency action.” · 2 citing courts
cites § 331.2 2×cited by 5 cases
Where it cites § 331.2
“If a property owner is unsure if his or her land contains waters regulated under the CWA, he or she can request a jurisdictional determination (“JD”) from the Corps. U.S. Army Corps of Eng’rs, Regulatory Guidance Letter No.”
10
GREENLewis v. United States, 88 F.4th 1073 (5th Cir. 2023).
cites § 331.2 1×cited by 5 cases
Where it cites § 331.2
“” 33 C.F.R. § 331.2 . 2 As an aside, during a historic 500-year flood in 2016, this property was unscathed although 80% of the Livingston Parish homes were flooded.”
cites § 331.2 1×cited by 6 casesunpublished
Where it cites § 331.2
“33 C.F.R. § 331.2 . Section 404 requires, among other things, a permit for the “discharge of dredged or fill material into the navigable waters,” which are defined in turn as “waters of the United States.”
12
GREENDefenders of Wildlife v. Tuggle, 607 F. Supp. 2d 1095 (D. Ariz. 2009).
cites § 331.2 1×cited by 6 cases
Where it cites § 331.2
“The CWA regulations require affected parties to solicit the Corps’ official position about the scope of the agency’s regulatory jurisdiction, 33 C.F.R. § 331.2 , so the decision delimits the stopping point of the decision-making process for issuance and review of jurisdictional…”
13
cites § 331.2 1×cited by 5 cases
Where it cites § 331.2
“” 33 C.F.R. § 331.2 . "Approved jurisdictional determination means a Corps document stating the *206 presence or absence of waters of the United States on a parcel or a written statement and map identifying the limits of waters of the United States on a parcel.”
14
REDHawkes Co. v. United States Army Corps of Engineers, 963 F. Supp. 2d 868 (D. Minn. 2013).
cites § 331.2 1×cited by 5 cases
Reversed by Hawkes Co. v. United States Army Corps of Engineers (2015): the Court of Appeals for the Eighth Circuit's own opinion in this case.
Where it cites § 331.2
“See 33 C.F.R. §§ 331.2 , 331.3. On April 4, 2012, in accordance with CWA regulations, Plaintiffs appealed the Approved JD to the designated Corps Review Officer.”
Later courts cite it for
“face no such obligations or changes in their rights as a result of their jurisdictional determination.” · 1 citing court
15
GREENNormandy Corp. v. South Carolina Dep't of Transp., 688 S.E.2d 136 (S.C. Ct. App. 2009).
cites § 331.2 1×cited by 4 cases
Where it cites § 331.2
“” 33 C.F.R. § 331.2 (2000). 7 . In his order, the master ruled that the ditching was "indisputably legal.”
Later courts cite it for
“may be raised at any time, including on appeal.” · 3 citing courts
16
GREENRauseo v. Army Corps of Engineers, 368 F. Supp. 3d 202 (D.D.C. 2019).
cites § 331.2 1×cited by 2 cases
Where it cites § 331.2
“Under 33 C.F.R. § 331.2 , a JD by the Corps that a wetland and/or waterbody is subject to regulatory jurisdiction under Section 404 of the CWA must be in writing and either be identified as preliminary or approved.”
17
GREENShort v. United States Army Corps of Engineers, 593 F. Supp. 2d 69 (D.D.C. 2009).
cites § 331.2 1×cited by 3 cases
Where it cites § 331.2
“” 33 C.F.R. § 331.2 . Section 404 is codified at 33 U.”
18
GREENNew Jersey Transit Corp. v. Eugene E. Mori, 89 A.3d 237 (N.J. Super. Ct. App. Div. 2014).
cites § 331.2 1×cited by 3 cases
Where it cites § 331.2
“[ 33 C.F.R. § 331.2 (2014).] A jurisdictional determination "represent[s] the [ACOE's] definitive administrative position that [] property contain[s] wetlands.”
cites § 331.2 1×cited by 3 cases
Where it cites § 331.2
“See 33 C.F.R. § 331.2 (2015) ("Jurisdictional determination (JD) means a written Corps determination that a wetland and/or waterbody is subject to regulatory jurisdiction under Section 404 of the [CWA].”
Later courts cite it for
“as to questions of fact, this court may not substitute its judgment for the alc's judgment when weighing the evidence.” · 1 citing court
20
GREENGrosscup v. Pantano, 725 F. Supp. 2d 1370 (S.D. Fla. 2010).
cites § 331.2 1×cited by 1 case
Where it cites § 331.2
“The Corps denied the appeal, stating that the withdrawal of a permit application was not an appealable action under 33 C.F.R. § 331.2 . Id.; (D.E. No. 15, Exh.”

Show all 38 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
200820162025

One bar per year. Tallest: 7 cases in 2009. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
D.D.C.89th Cir.3D.C. Cir.35th Cir.2M.D. La.2D. Ariz.110th Cir.111th Cir.1

The 8 courts with the most citing cases, of 25 courts in all.

By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Show all 38 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com