C.F.R. homeSearch C.F.R.
C.F.R.Title 33Chapter II—Corps of Engineers, Department of the Army, Department of DefensePart 325—Processing of Department of the Army Permits

33 C.F.R. § 325.1 (2026)

Applications for permits

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1979–2022 51citing cases
At a glance

Courts have cited this section in 51 opinions since 1979, 2 of them in the last five years. The most litigated part is subsection (d) (4 cases).

(a) General. The processing procedures of this part apply to any Department of the Army (DA) permit. Special procedures and additional information are contained in 33 CFR parts 320 through 324, 327 and part 330. This part is arranged in the basic timing sequence used by the Corps of Engineers in processing applications for DA permits.

(b) Pre-application consultation for major applications. The district staff element having responsibility for administering, processing, and enforcing federal laws and regulations relating to the Corps of Engineers regulatory program shall be available to advise potential applicants of studies or other information foreseeably required for later federal action. The district engineer will establish local procedures and policies including appropriate publicity programs which will allow potential applicants to contact the district engineer or the regulatory staff element to request pre-application consultation. Upon receipt of such request, the district engineer will assure the conduct of an orderly process which may involve other staff elements and affected agencies (Federal, state, or local) and the public. This early process should be brief but thorough so that the potential applicant may begin to assess the viability of some of the more obvious potential alternatives in the application. The district engineer will endeavor, at this stage, to provide the potential applicant with all helpful information necessary in pursuing the application, including factors which the Corps must consider in its permit decision making process. Whenever the district engineer becomes aware of planning for work which may require a DA permit and which may involve the preparation of an environmental document, they shall contact the principals involved to advise them of the requirement for the permit(s) and the attendant public interest review including the development of an environmental document. Whenever a potential applicant indicates the intent to submit an application for work which may require the preparation of an environmental document, a single point of contact shall be designated within the district's regulatory staff to effectively coordinate the regulatory process, including the National Environmental Policy Act (NEPA) procedures and all attendant reviews, meetings, hearings, and other actions, including the scoping process if appropriate, leading to a decision by the district engineer. Effort devoted to this process should be commensurate with the likelihood of a permit application actually being submitted to the Corps. The regulatory staff coordinator shall maintain an open relationship with each potential applicant or their consultants so as to assure that the potential applicant is fully aware of the substance (both quantitative and qualitative) of the data required by the district engineer for use in preparing an environmental assessment (EA) or an environmental impact statement (EIS) in accordance with 33 CFR part 333.

(c) Application form. Applicants for all individual DA permits must use the standard application form (ENG Form 4345, OMB Approval No. OMB 49-R0420). Local variations of the application form for purposes of facilitating coordination with federal, state and local agencies may be used. The appropriate form may be obtained from the district office having jurisdiction over the waters in which the activity is proposed to be located. Certain activities have been authorized by general permits and do not require submission of an application form but may require a separate notification.

(d) Content of application. (1) The application must include a complete description of the proposed activity including necessary drawings, sketches, or plans sufficient for public notice (detailed engineering plans and specifications are not required); the location, purpose and need for the proposed activity; scheduling of the activity; the names and addresses of adjoining property owners; the location and dimensions of adjacent structures; and a list of authorizations required by other federal, interstate, state, or local agencies for the work, including all approvals received or denials already made. See § 325.3 for information required to be in public notices. District and division engineers are not authorized to develop additional information forms but may request specific information on a case-by-case basis. (See § 325.1(e)).

(2) All activities which the applicant plans to undertake which are reasonably related to the same project and for which a DA permit would be required should be included in the same permit application. District engineers should reject, as incomplete, any permit application which fails to comply with this requirement. For example, a permit application for a marina will include dredging required for access as well as any fill associated with construction of the marina.

(3) If the activity would involve dredging in navigable waters of the United States, the application must include a description of the type, composition and quantity of the material to be dredged, the method of dredging, and the site and plans for disposal of the dredged material.

(4) If the activity would include the discharge of dredged or fill material into the waters of the United States or the transportation of dredged material for the purpose of disposing of it in ocean waters the application must include the source of the material; the purpose of the discharge, a description of the type, composition and quantity of the material; the method of transportation and disposal of the material; and the location of the disposal site. Certification under section 401 of the Clean Water Act is required for such discharges into waters of the United States.

(5) If the activity would include the construction of a filled area or pile or float-supported platform the project description must include the use of, and specific structures to be erected on, the fill or platform.

(6) If the activity would involve the construction of an impoundment structure, the applicant may be required to demonstrate that the structure complies with established state dam safety criteria or that the structure has been designed by qualified persons and, in appropriate cases, independently reviewed (and modified as the review would indicate) by similarly qualified persons. No specific design criteria are to be prescribed nor is an independent detailed engineering review to be made by the district engineer.

(7) For activities involving discharges of dredged or fill material into waters of the United States, the application must include a statement describing how impacts to waters of the United States are to be avoided and minimized. The application must also include either a statement describing how impacts to waters of the United States are to be compensated for or a statement explaining why compensatory mitigation should not be required for the proposed impacts. (See § 332.4(b)(1) of this chapter.)

(8) Signature on application. The application must be signed by the person who desires to undertake the proposed activity (i.e., the applicant) or by a duly authorized agent. When the applicant is represented by an agent, that information will be included in the space provided on the application or by a separate written statement. The signature of the applicant or the agent will be an affirmation that the applicant possesses or will possess the requisite property interest to undertake the activity proposed in the application, except where the lands are under the control of the Corps of Engineers, in which cases the district engineer will coordinate the transfer of the real estate and the permit action. An application may include the activity of more than one owner provided the character of the activity of each owner is similar and in the same general area and each owner submits a statement designating the same agent.

(9) If the activity would involve the construction or placement of an artificial reef, as defined in 33 CFR 322.2(g), in the navigable waters of the United States or in the waters overlying the outer continental shelf, the application must include provisions for siting, constructing, monitoring, and managing the artificial reef.

(10) Complete application. An application will be determined to be complete when sufficient information is received to issue a public notice (See 33 CFR 325.1(d) and 325.3(a).) The issuance of a public notice will not be delayed to obtain information necessary to evaluate an application.

(e) Additional information. In addition to the information indicated in paragraph (d) of this section, the applicant will be required to furnish only such additional information as the district engineer deems essential to make a public interest determination including, where applicable, a determination of compliance with the section 404(b)(1) guidelines or ocean dumping criteria. Such additional information may include environmental data and information on alternate methods and sites as may be necessary for the preparation of the required environmental documentation.

(f) Fees. Fees are required for permits under section 404 of the Clean Water Act, section 103 of the Marine Protection, Research and Sanctuaries Act of 1972, as amended, and sections 9 and 10 of the Rivers and Harbors Act of 1899. A fee of $100.00 will be charged when the planned or ultimate purpose of the project is commercial or industrial in nature and is in support of operations that charge for the production, distribution or sale of goods or services. A $10.00 fee will be charged for permit applications when the proposed work is non-commercial in nature and would provide personal benefits that have no connection with a commercial enterprise. The final decision as to the basis for a fee (commercial vs. non-commercial) shall be solely the responsibility of the district engineer. No fee will be charged if the applicant withdraws the application at any time prior to issuance of the permit or if the permit is denied. Collection of the fee will be deferred until the proposed activity has been determined to be not contrary to the public interest. Multiple fees are not to be charged if more than one law is applicable. Any modification significant enough to require publication of a public notice will also require a fee. No fee will be assessed when a permit is transferred from one property owner to another. No fees will be charged for time extensions, general permits or letters of permission. Agencies or instrumentalities of federal, state or local governments will not be required to pay any fee in connection with permits.

[51 FR 41236, Nov. 13, 1986, as amended at 73 FR 19670, Apr. 10, 2008; 90 FR 29472, July 3, 2025]
The 20 cases that cite 33 C.F.R. § 325.1 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENCrutchfield v. United States Army Corps of Engineers, 214 F. Supp. 2d 593 (E.D. Va. 2002).
cites § 325.1 24×cited by 6 cases
Where it cites § 325.1
“20 See 33 C.F.R. § 325.1 (d)(9) (explaining that “[a]n application will be determined to be complete when sufficient information is received to issue a public notice”).”
The case’s holding
Corps may switch from individual permitting to nationwide permits without notifying interested parties, since no regulation mandates such notice, so the switch is not arbitrary or capricious.
Later courts cite it for
“no precise regulation mandates that the corps must notify interested parties of a decision to switch from the individual permitting mode to the nwp mode.” · 2 citing courts
2
GREENU.S. Army Corps of Eng'rs v. Hawkes Co., 578 U.S. 590 (2016).
cites § 325.1 2×cited by 285 cases
Where it cites § 325.1
“On top of the standard permit application that respond- ents were required to submit, see 33 CFR §325.1 (d) (detailing contents of permit application), the Corps de- manded that they undertake, among other things, a “hydrogeologic assessment of the rich fen system including the…”
The case’s holding
An agency action is final when it marks the consummation of the agency's decision-making process and determines legal rights or obligations.
Later courts cite it for
“the action must mark the consummation of the agency's decisionmaking process-it must not be of a merely tentative or interlocutory nature” · 12 citing courts
3
GREENOhio Valley Env't Coalition v. United States Army Corps of Engineers, 674 F. Supp. 2d 783 (S.D. W. Va. 2010).
cites § 325.1 21×subsections: (d)(9) 4× (d) 3× (d)(1) 3×cited by 5 cases
Where it cites § 325.1
“A complete application is defined in terms of the sufficiency of the submitted materials to provide a meaningful opportunity for public comment, 33 C.F.R. § 325.1 (d)(9) (“An application will be determined to be complete when sufficient information is received to issue a public…”
4
GREENCrutchfield v. United States Army Corps of Engineers, 154 F. Supp. 2d 878 (E.D. Va. 2001).
cites § 325.1 10×cited by 9 cases
Where it cites § 325.1
“, and the Corps’ regulations, 33 C.F.R. § 325.1 and 33 C.F.R. § 330.6 .”
Later courts cite it for
“remarkably illogical conclusion” · 3 citing courts
5
GREENResource Investments, Inc. v. United States, 85 Fed. Cl. 447 (Fed. Cl. 2009).
cites § 325.1 2×cited by 60 cases
Where it cites § 325.1
“2 ; see also 33 C.F.R. § 325.1 (d)(10) (“An application will be determined to be complete when sufficient information is received to issue a public notice____”).”
The case’s holding
A regulatory taking arising from a permit denial accrues at the time the permit is denied.
Later courts cite it for
“a year or two of delay, without bad faith, is exceedingly unlikely to be extraordinary” · 2 citing courts
6
GREENMehaffy v. United States, 98 Fed. Cl. 604 (Fed. Cl. 2011).
cites § 325.1 7×cited by 3 cases
Where it cites § 325.1
“” 33 C.F.R. § 325.1 (d)(9) (2006) (citations omitted); see Scott Dep.”
7
GREENTown of Abita Springs v. U.S. Army Corps of Engineers, 153 F. Supp. 3d 894 (E.D. La. 2015).
cites § 325.1 3×cited by 8 cases
Where it cites § 325.1
“See 33 C.F.R. § 325.1 (d)(1) (stating “detailed engineering plans and specifications are not required” to be included in a public notice); Ohio Valley, 674 F.”
Later courts cite it for
“the specific location of the project may be an important aspect of fulfilling the overall project purpose . . . as such location can limit what alternatives are considered practicable.” · 2 citing courts
8
REDSierra Club v. United States Army Corps of Engineers, 450 F. Supp. 2d 503 (D.N.J. 2006).
cites § 325.1 3×cited by 7 cases
Vacated by Sierra Club v. United States Army Corps of Engineers (2008): the Court of Appeals for the Third Circuit's own opinion in this case.
Where it cites § 325.1
“” 33 C.F.R. § 325.1 (d). 27 In fact, in considering a comment made during the permitting process regarding the impacts of project components that are market-dependent and that are scheduled to be phased-in, the Army Corps recognized its obligation under 33 C.”
9
GREENAbenaki Nation of Mississquoi v. Hughes, 805 F. Supp. 234 (D. Vt. 1992).
cites § 325.1 2×cited by 25 cases
Where it cites § 325.1
“Plaintiffs cite 33 C.F.R. § 325.1 (d)(2) which provides: All activities which the applicant plans to undertake which are reasonably related to the same project and for which the DA [Department of the Army] permit would be required should be included in the same permit…”
Later courts cite it for
“arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” · 3 citing courts
10
cites § 325.1 1×cited by 14 cases
Where it cites § 325.1
“For the first kind, an individual permit, a person seeking to fill a wetland must submit to the appropriate Corps district office a detailed application, see 33 C.F.R. §§ 325.1 (c)–(d), 325.2(a), that includes “a list of authoriza- tions required by other federal, interstate,…”
Later courts cite it for
“article iii standing requires a plaintiff to have suffered an injury in fact, that is fairly traceable to the challenged conduct of the defendant, and that is likely to be redressed by a favorable judicial decision.” · 2 citing courts
cites § 325.1 1×cited by 34 cases
Where it cites § 325.1
“Agency regulations Appellants first argue that the Corps has a regulation, 33 C.F.R. § 325.1 (d)(7), that requires that the applicant actually have necessary property rights in the area of the project and make an affirmation to that effect.”
Later courts cite it for
“deference is not due to interpretations that are post hoc rationalizations offered by an agency seeking to defend past agency action against attack . . ., or to interpretations that have varied erratically over time.” · 2 citing courts
12
GREENCrutchfield v. United States Army Corps of Engineers, 230 F. Supp. 2d 687 (E.D. Va. 2002).
cites § 325.1 3×cited by 5 cases
Where it cites § 325.1
“More important still, on remand in Crutchfield II, the Corps is obligated to follow its regulations concerning relatedness and independent utility ( 33 C.F.R. §§ 325.1 (d)(2), 330.2®, 330.6(c) and 67 Fed.”
13
GREENCannon v. State, 807 A.2d 556 (Del. 2002).
cites § 325.1 2×cited by 8 cases
Where it cites § 325.1
“" [60] Similarly, 33 C.F.R. § 325.1 (d)(7) states that an applicant's signature will be an affirmation that the applicant will possess the requisite property interest.”
14
GREENRoute 26 Land Dev. Ass'n v. United States Gov't, 753 F. Supp. 532 (D. Del. 1990).
cites § 325.1 2×cited by 16 cases
Where it cites § 325.1
“Among these required items are: (1) the standard application form, 33 C.F.R. § 325.1 (c); (2) a certification from the State in which the discharge originates that the discharge will comply with the applicable water quality standards, 33 U.”
15
GREENSierra Club v. Pena, 915 F. Supp. 1381 (N.D. Ohio 1996).
cites § 325.1 2×cited by 16 cases
Where it cites § 325.1
“They claim that the 1990 application was not properly signed by an ODOT official, as required by 33 C.F.R. § 325.1 (d)(7). They claim that ODOT failed to include on the application three acres of wetlands known as Manhattan Marsh.”
Later courts cite it for
“all other currently pending motions,” · 2 citing courts
16
GREENBelle Co. v. United States Army Corps of Engineers, 761 F.3d 383 (5th Cir. 2014).
cites § 325.1 1×cited by 20 cases
Where it cites § 325.1
“33 C.F.R. § 325.1 (b). The regulations also authorize the Corps “to issue formal determinations concerning the applicability of the Clean Water Act .”
Later courts cite it for
“if there is no final agency action.” · 2 citing courts
cites § 325.1 2×cited by 6 cases
Where it cites § 325.1
“See 33 C.F.R. § 325.1 (d)(7) ("The signature of the applicant or the agent will be an affirmation that the applicant possesses or will possess the requisite property interest to undertake the activity proposed in the application .”
18
GREENNofelco Realty Corp. v. United States, 521 F. Supp. 458 (S.D.N.Y. 1981).
cites § 325.1 2×cited by 10 cases
Where it cites § 325.1
“The regulations governing the issuance of such permits are found in 33 C.F.R. §§ 325.1 et seq. (1980) and provide for, inter alia, public notice of the permit application, receipt of written comments from interested parties, an opportunity for the applicant to rebut all…”
19
GREENAll. for Legal Action v. United States Army Corps of Engineers, 314 F. Supp. 2d 534 (M.D.N.C. 2004).
cites § 325.1 1×cited by 13 cases
Where it cites § 325.1
“See 33 C.F.R. § 325.1 (d)(7). The applicant’s signature on the permit application “affirm[s] that the applicant possesses or will possess the requisite property interest to undertake the activity proposed in the application.”
Later courts cite it for
“the corps's determination that the faa's alternatives analysis satisfied the section 404(b)(1) guidelines was not arbitrary or capricious” · 2 citing courts
20
GREENShoreline Assocs. v. Marsh, 555 F. Supp. 169 (D. Md. 1983).
cites § 325.1 1×cited by 25 cases
Where it cites § 325.1
“33 CFR §§ 325.1 & 325.2. The District Engineer, in accordance with the applicable regulations and the record, determines if a permit should issue.”
Later courts cite it for
“primary aspect of the proposed project is the construction of a townhouse community, not the construction of a boat storage facility and launch, which are incidental to it.” · 2 citing courts

Show all 51 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
197920002022

One bar per year. Tallest: 5 cases in 2002. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Fed. Cl.5E.D. Va.511th Cir.4D.D.C.4N.D. Ohio35th Cir.2D. Del.2M.D. Fla.2

The 8 courts with the most citing cases, of 30 courts in all.

By subsection
(d)4 cases
Ohio Valley Env't Coalition v. United States Army Corps of Engineers, 674 F. Supp. 2d 783 (S.D. W. Va. 2010).“A complete application is defined in terms of the sufficiency of the submitted materials to provide a meaningful opportunity for public comment, 33 C.F.R. § 325.1 (d)(9) (“An application will be determined to be complete when sufficient information is received to issue a public…”
Env't Coalition of Broward Cnty., Inc. v. Myers, 831 F.2d 984 (11th Cir. 1987).
State Site, Inc. v. K/S A/S Heragas, 628 F. Supp. 1569 (E.D. Tex. 1986).
(d)(1)1 case
(d)(4)1 case
City of Olmsted Falls v. United States Env't Prot. Agency, 266 F. Supp. 2d 718 (N.D. Ohio 2003).
(d)(8)1 case
Aylward v. City of Charlotte, No. 3:21-cv-00232 (W.D.N.C. Sept. 1, 2022).
(d)(9)1 case

Show all 51 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com