Syfert Injury Law Firm

Your Trusted Partner in Personal Injury & Workers' Compensation

Call Now: 904-383-7448

2018 Georgia Code 44-14-361.1 | Car Wreck Lawyer

TITLE 44 PROPERTY

Section 14. Mortgages, Conveyances to Secure Debt, and Liens, 44-14-1 through 44-14-613.

ARTICLE 8 LIENS

44-14-361.1. How liens declared and created; amendment; record; commencement of action; notice; priorities; parties; limitation on aggregate amount of liens.

  1. To make good the liens specified in paragraphs (1) through (8) of subsection (a) of Code Section 44-14-361, they must be created and declared in accordance with the following provisions, and on failure of any of them the lien shall not be effective or enforceable:
    1. A substantial compliance by the party claiming the lien with his or her contract for building, repairing, or improving; for architectural services furnished; for registered forester services furnished or performed; for registered land surveying or registered professional engineering services furnished or performed; or for materials or machinery furnished or set up;
    2. The filing for record of his or her claim of lien within 90 days after the completion of the work, the furnishing of the architectural services, or the furnishing or performing of such surveying or engineering services or within 90 days after the material or machinery is furnished in the office of the clerk of the superior court of the county where the property is located. The lien shall include a statement regarding its expiration pursuant to Code Section 44-14-367 and a notice to the owner of the property on which a claim of lien is filed that such owner has the right to contest the lien; the absence of such statement or notice shall invalidate the lien. The claim shall be in substance as follows:

      "A.B., a mechanic, contractor, subcontractor, materialman, machinist, manufacturer, registered architect, registered forester, registered land surveyor, registered professional engineer, or other person (as the case may be) claims a lien in the amount of (specify the amount claimed) on the house, factory, mill, machinery, or railroad (as the case may be) and the premises or real estate on which it is erected or built, of C.D. (describing the houses, premises, real estate, or railroad), for satisfaction of a claim which became due on (specify the date the claim was due, which is the same as the last date the labor, services, or materials were supplied to the premises) for building, repairing, improving, or furnishing material (or whatever the claim may be)."

      No later than two business days after the date the claim of lien is filed of record, the lien claimant shall send a true and accurate copy of the claim of lien by registered or certified mail or statutory overnight delivery to the owner of the property or, if the owner's address cannot be found, the contractor, as the agent of the owner; provided, however, if the property owner is an entity on file with the Secretary of State's Corporations Division, sending a copy of the claim of lien to the entity's address or the registered agent's address shall satisfy this requirement. In all cases in which a notice of commencement is filed with the clerk of the superior court pursuant to subsection (b) of Code Section 44-14-361.5, a lien claimant shall also send a copy of the claim of lien by registered or certified mail or statutory overnight delivery to the contractor at the address shown on the notice of commencement;

    3. The commencement of a lien action for the recovery of the amount of the party's claim within 365 days from the date of filing for record of his or her claim of lien. In addition, within 30 days after commencing such lien action, the party claiming the lien shall file a notice with the clerk of the superior court of the county wherein the subject lien was filed. The notice shall contain a caption referring to the then owner of the property against which the lien was filed and referring to a deed or other recorded instrument in the chain of title of the affected property. The notice shall be executed, under oath, by the party claiming the lien or by such party's attorney of record, but failure to execute the notice under oath shall be an amendable defect which may be cured by the party claiming the lien or by such party's attorney without leave of court at any time before entry of the pretrial order and thereafter by leave of court. An amendment of notice pursuant to this Code section shall relate back to the date of filing of the notice. The notice shall identify the court or arbitration venue wherein the lien action is brought; the style and number, if any, of the lien action, including the names of all parties thereto; the date of the filing of the lien action; and the book and page number of the records of the county wherein the subject lien is recorded in the same manner in which liens specified in Code Section 44-14-361 are filed. The clerk of the superior court shall enter on the subject lien so referred to the book and page on which the notice is recorded and shall index such notice in the name of the then purported owner as shown by the caption contained in such notice. A separate lis pendens notice need not be filed with the commencement of this action; and
    4. In the event any contractor or subcontractor procuring material, architect's services, registered forester's services, registered land surveyor's services, or registered professional engineer's services, labor, or supplies for the building, repairing, or improving of any real estate, building, or other structure shall abscond or die or leave the state during the required time period for filing a lien action, so that personal jurisdiction cannot be obtained on the contractor or subcontractor in a lien action for the services, material, labor, or supplies, or if the contractor or subcontractor shall be adjudicated a bankrupt, or if, after the filing of a lien action, no final judgment can be obtained against him or her for the value of such material, services, labor, or supplies because of his or her death, adjudication in bankruptcy, or the contract between the party claiming the lien and the contractor or subcontractor includes a provision preventing payment to the claimant until after the contractor or the subcontractor has received payment, then and in any of these events, the person or persons furnishing material, services, labor, and supplies shall be relieved of the necessity of filing a lien action or obtaining judgment against the contractor or subcontractor as a prerequisite to enforcing a lien against the property improved by the contractor or subcontractor. Subject to Code Section 44-14-361, the person or persons furnishing material, services, labor, and supplies may enforce the lien directly against the property so improved in a lien action against the owner thereof, if filed within the required time period for filing a lien action, with the judgment rendered in any such proceeding to be limited to a judgment in rem against the property improved and to impose no personal liability upon the owner of the property; provided, however, that in such lien action for recovery, the owner of the real estate improved, who has paid the agreed price or any part of same, may set up the payment in any lien action brought and prove by competent and relevant evidence that the payments were applied as provided by law, and no judgment shall be rendered against the property improved. Within 30 days after filing such lien action, the party claiming the lien shall file a notice with the clerk of the superior court of the county wherein the subject lien was filed. The notice shall contain a caption referring to the then owner of the property against which the lien was filed and referring to a deed or other recorded instrument in the chain of title of the affected property. The notice shall be executed, under oath, by the party claiming the lien or by his or her attorney of record. The notice shall identify the court or arbitration venue wherein the lien action is brought; the style and number of the lien action, if any, including the names of all parties thereto; the date of the filing of the lien action; and the book and page number of the records of the county wherein the subject lien is recorded in the same manner in which liens specified in Code Section 44-14-361 are filed. The clerk of the superior court shall enter on the subject lien so referred to the book and page on which the notice is recorded and shall index such notice in the name of the then purported owner as shown by the caption contained in such notice. A separate lis pendens notice need not be filed with the commencement of this action.

      "That certain claim of lien filed by A.B. against property of C.D. on (date) and recorded at book (book#), page (page#) in the lien index of (name of county) County is hereby amended by reducing the amount of such claim of lien to (specify reduced amount claimed). The remaining terms of such original claim of lien are hereby incorporated by reference into this amended claim of lien. This amended claim of lien relates back to the date that such original claim of lien was filed for record."

      and shall be sent to the owner of the property in the same manner as required for a claim of lien in paragraph (2) of subsection (a) of this Code section.

  2. As between themselves, the liens provided for in Code Section 44-14-361 shall rank according to the date filed; but all of the liens mentioned in this Code section for repairs, building, or furnishing materials or services, upon the same property, shall, as to each other, be of the same date when declared and filed for record within 90 days after the work is done or before that time.
  3. The liens specified in Code Section 44-14-361 shall be inferior to liens for taxes, to the general and special liens of laborers, to the general lien of landlords of rent when a distress warrant is issued out and levied, to claims for purchase money due persons who have only given bonds for titles, and to other general liens when actual notice of the general lien of landlords and others has been communicated before the work was done or materials or services furnished; but the liens provided for in Code Section 44-14-361 shall be superior to all other liens not excepted by this subsection.
  4. In any proceeding brought by any materialman, by any mechanic, by any laborer, by any subcontractor, or by any mechanic of any sort employed by any subcontractor or by any materialmen furnishing material to any subcontractor, or by any laborer furnishing labor to any subcontractor, to enforce such a lien, the contractor having a direct contractual relationship with the subcontractor shall not be a necessary party; but he or she may be made a party. In any proceedings brought by any mechanic employed by any subcontractor, by any materialmen furnishing material to any subcontractor, or by any laborer furnishing labor to any subcontractor, the subcontractor shall not be a necessary party; but he or she may be made a party. The contractor or subcontractor or both may intervene in the proceedings at any time before judgment for the purpose of resisting the establishment of the lien or of asserting against the lienor any claim of the contractor or subcontractor growing out of or related to the transaction upon which the asserted lien is based.
  5. In no event shall the aggregate amount of liens set up by Code Section 44-14-361 exceed the contract price of the improvements made or services performed.
  6. The filing fees for a claim of materialman's or mechanic's lien and any related document created pursuant to this Code section, including but not limited to a notice of commencement of action, shall be the amount set by Code Section 15-6-77 for liens on real estate and personal property.

(a.1)A claim of lien may be amended at any time to reduce the amount claimed, and such amended claim of lien shall relate back to the date of filing for record of the original claim of lien. An amended claim of lien filed for record pursuant to this subsection shall be in substance as follows:

(Ga. L. 1873, p. 42, § 7; Code 1873, § 1980; Ga. L. 1874, p. 45, § 1; Code 1882, § 1980; Civil Code 1895, § 2804; Civil Code 1910, § 3353; Code 1933, § 67-2002; Ga. L. 1941, p. 345, § 1; Ga. L. 1952, p. 291, § 1; Ga. L. 1953, Jan.-Feb. Sess., p. 582, §§ 3-5; Ga. L. 1956, p. 185, §§ 2, 3; Ga. L. 1956, p. 562, § 3; Ga. L. 1960, p. 103, § 1; Ga. L. 1967, p. 456, § 1; Ga. L. 1968, p. 317, § 1; Ga. L. 1977, p. 675, § 1; Ga. L. 1981, p. 846, § 1; Code 1981, §44-14-362; Code 1981, §44-14-361.1, enacted by Ga. L. 1983, p. 1450, § 1; Ga. L. 1984, p. 22, § 44; Ga. L. 1985, p. 1322, § 3; Ga. L. 1989, p. 438, § 1; Ga. L. 1991, p. 639, § 1; Ga. L. 1997, p. 829, § 1; Ga. L. 1998, p. 860, § 1; Ga. L. 2000, p. 1589, § 3; Ga. L. 2008, p. 1063, § 2/SB 374; Ga. L. 2010, p. 859, § 1/SB 362.)

The 2000 amendment, effective July 1, 2000, substituted "certified mail or statutory overnight delivery" for "certified mail" in the last undesignated paragraph following paragraph (2)(a).

The 2008 amendment, effective March 31, 2009, rewrote this Code section.

The 2010 amendment, effective July 1, 2010, added subsection (a.1).

Editor's notes.

- Ga. L. 1998, p. 860, § 3, not codified by the General Assembly, provides that this Act is applicable to claims of lien filed on or after July 1, 1998.

Ga. L. 2000, p. 1589, § 16, not codified by the General Assembly, provides that this Act is applicable with respect to notices delivered on or after July 1, 2000.

Law reviews.

- For article discussing status of lienor at time of bankruptcy, see 10 Ga. B.J. 181 (1947). For article discussing failure of consideration, see 4 Mercer L. Rev. 327 (1953). For article advocating more protection of subcontractor's interest by modification of lien laws, see 14 Ga. St. B.J. 88 (1977). For article discussing role of attorney in representing subcontractor and available enforcement mechanisms, see 14 Ga. St. B.J. 104 (1978). For article, "Lien Claimants and Real Estate Lenders - The Struggle For Priority," see 16 Ga. St. B.J. 187 (1980). For article on construction law, see 42 Mercer L. Rev. 25 (1990). For annual survey of construction law, see 43 Mercer L. Rev. 141 (1991). For article, "Caveat Venditor: The Material Supplier's Dilemma on a Construction Project," see 28 Ga. St. B.J. 154 (1992). For article, "Recent Developments in Construction Law," see 5 Ga. St. B.J. 24 (1999). For annual survey article discussing developments in construction law, see 51 Mercer L. Rev. 181 (1999). Commercial Law, see 53 Mercer L. Rev. 153 (2001). Construction Law, see 53 Mercer L. Rev. 173 (2001). For annual survey of construction law, see 57 Mercer L. Rev. 79 (2005). For survey article on construction law, see 60 Mercer L. Rev. 59 (2008). For survey article on real property law, see 60 Mercer L. Rev. 345 (2008). For annual survey on construction law, see 61 Mercer L. Rev. 65 (2009). For annual survey of construction law, see 67 Mercer L. Rev. 23 (2015). For note surveying revisions to Georgia Condominium Act between 1963 and 1975 regarding expansion, disclosure, liens, and incorporation, see 24 Emory L.J. 891 (1975). For comment on Victory Lumber Co. v. Ellison, 95 Ga. App. 105, 97 S.E.2d 334 (1957), holding "that unless a materialman files suit against a contractor prior to the contractor's discharge in bankruptcy, he cannot enforce his lien against the property upon which the materials were used," see 21 Ga. B.J. 91 (1958).

JUDICIAL DECISIONS

General Consideration

Editor's notes.

- The pre-1984 cases noted below were decided under former Code section 44-14-362. See, also, the annotations under that Code section for decisions applicable to present Code section 44-14-361.1.

Purpose.

- The purpose of the recording statutes is to protect both the lienholder and innocent persons acting in good faith but without means of discovering the lien of another. An attorney is given the privilege of protecting a lien by recording the attorney's claim thereto, and the attorney's failure to utilize such privilege brings upon the attorney the same disaster that befalls other lienholders who neglect to record the lien as authorized by law. Anderson v. Burnham, 12 Bankr. 286 (Bankr. N.D. Ga. 1981).

The purpose of the former statutory provision (now O.C.G.A. § 44-14-361.1(c)), which required that notice of a subcontractor's suit against the contractor to recover the claim on which the lien was based need only be filed within 12 months of the time the claim for materials became due, was primarily to provide potential purchasers of the property with constructive notice to enable them to determine whether or not the claim of lien was still extant. Amafra Enters., Inc. v. All-Steel Bldgs., Inc., 169 Ga. App. 388, 313 S.E.2d 110 (1984).

The intent of O.C.G.A. § 44-14-361.1 as to timely filing of liens is to establish a time certain beyond which liens cannot be filed, for the protection of the contracting parties and innocent third parties. Womack Indus., Inc. v. B & A Equip. Co., 199 Ga. App. 660, 405 S.E.2d 880, cert. denied, 199 Ga. App. 907, 405 S.E.2d 880 (1991).

O.C.G.A. § 44-14-361.1 is to be strictly construed. Ballard v. Grubbs, 9 Bankr. 499 (M.D. Ga. 1981).

O.C.G.A. § 44-14-361.1 is in derogation of common law and is to be strictly construed against the materialman, and strict compliance is required. Womack Indus., Inc. v. B & A Equip. Co., 199 Ga. App. 660, 405 S.E.2d 880, cert. denied, 199 Ga. App. 907, 405 S.E.2d 880 (1991).

The creation of liens under O.C.G.A. § 44-14-361.1 is in derogation of the common law, and strict compliance with the requirements of the statute is required. Consolidated Sys. v. AMISUB, Inc., 261 Ga. 590, 408 S.E.2d 109 (1991).

A materialman's lien effectively permits the transfer of liability from the person who actually contracted with the materialman for materials to be used on improving real estate to the owner of the improved property, even though that property owner usually will have no relationship with the materialman, contractual or otherwise. Consequently, the court has long recognized that statutes involving materialman's liens must be strictly construed in favor of the property owner and against the materialman. Palmer v. Duncan Whsle., Inc., 262 Ga. 28, 413 S.E.2d 437 (1992).

Failure to prove lien amount.

- Trial court erred by granting summary judgment to a subcontractor because the subcontractor failed to prove the lien amount, if any, the subcontractor was entitled to and the subcontractor was not entitled to a lien for the attorney fees and interest allegedly owed since there was no agreement for such amounts. Hill v. VNS Corp., 329 Ga. App. 274, 764 S.E.2d 876 (2014).

No damages available.

- O.C.G.A. § 44-14-361.1 does not provide for an action for damages for its violation, as it explicitly states that failure to comply with its provisions will result in the unenforceability of the lien. Hicks v. McLain's Bldg., Materials, Inc., 209 Ga. App. 191, 433 S.E.2d 114 (1993).

Prejudgment interest.

- Owners were not insulated against the payment of prejudgment interest since an award of such interest is distinct and separate from and not to be included in the calculation of the "aggregate amount of liens" within the meaning of O.C.G.A. § 44-14-361.1(e). Gaster Lumber Co. v. Browning, 219 Ga. App. 435, 465 S.E.2d 524 (1995), aff'd, 267 Ga. 72, 475 S.E.2d 576 (1996).

"Properly appropriate" payment construed.

- Where liens were filed prior to payment of the full contract price to the general contractor, payment that is thereafter made to any other materialman as a potential lien claimant is not payment which is "properly appropriate" and may not be set up by the owner in defense of the subsequent foreclosure of those previously filed liens. Electrical Distrib., Inc. v. Turner Constr. Co., 196 Ga. App. 359, 395 S.E.2d 879 (1990).

One seeking to foreclose a contractor's lien for labor and materials must show a substantial compliance with the contract and, if the completion of the contract was prevented by the defendant, this is equivalent to a completion of the contract as a remedial element. Summit-Top Dev., Inc. v. Williamson Constr., Inc., 203 Ga. App. 460, 416 S.E.2d 889 (1992).

Failure to follow statutory procedure renders lien unenforceable.

- Where a party fails to follow the mandatory procedure established in O.C.G.A. § 44-14-361.1, and where a suit against the contractor is mandatory, the party's lien is unenforceable and the trial court would be correct in granting summary judgment to the opposing party. D & T Glass, Inc. v. Barrow Enters., Inc., 172 Ga. App. 797, 325 S.E.2d 170 (1984).

Failure to comply with the statutory mandate of filing notice of a lien under oath renders the lien unenforceable. Allied Elec. Contractors v. Kern & Co., 184 Ga. App. 747, 362 S.E.2d 452 (1987), cert. denied, 184 Ga. App. 909, 362 S.E.2d 452 (1988).

Failure to file lien notice.

- Homeowner was entitled to summary judgment on the contractor's claim for foreclosure of a lien because the contractor failed to file the notice required by O.C.G.A. § 44-14-361.1(a)(3). Wagner v. Robinson, 329 Ga. App. 169, 764 S.E.2d 189 (2014).

Effect of discharge of lien by bond.

- When contractor and insurance company posted a bond to discharge supplier's liens, the bond served as a replacement for the lien and supplier's later execution of waiver and release of lien did not affect its contract claims against the bond. Benning Constr. Co. v. All-Phase Elec. Supply Co., 206 Ga. App. 279, 424 S.E.2d 830 (1992).

A lien is not a pleading for purposes of O.C.G.A. § 51-5-8 and statements made within a surveyor's lien are not afforded absolute privilege until the lien becomes attached to a lawsuit and verified notice of the suit is filed under O.C.G.A. § 44-14-361.1, at which point, the lien becomes an act of legal, or judicial process, and achieves the formality, solemnity, and status of a sworn statement. Simmons v. Futral, 262 Ga. App. 838, 586 S.E.2d 732 (2003).

Pre-lien payments.

- An owner is not entitled to credit under O.C.G.A. § 44-14-361.1(a)(4) where pre-lien payments to the contractor are disbursed post-lien by the contractor in payment of inferior-ranked, inchoate claims of materialmen and laborers. Browning v. Gaster Lumber Co., 267 Ga. 72, 475 S.E.2d 576 (1996).

What an owner must show to defeat a materialmen's lien.

- An owner must not only show that full payment was actually made to the contractor, the owner is also required to show that the sums paid to the contractor were properly appropriated to materialmen and laborers or that the contractor's statutory affidavit concerning such indebtedness had been obtained. Freeman v. Fulton Concrete Co., 204 Ga. App. 465, 419 S.E.2d 536 (1992).

The defense provided in O.C.G.A. § 44-14-361.1(e) requires that the owner show the sums paid to the contractor were properly appropriated, i.e., paid before the filing of the lien, to materialmen and laborers or that the contractor's affidavit concerning such indebtedness has been obtained. Gaster Lumber Co. v. Browning, 219 Ga. App. 435, 465 S.E.2d 524 (1995), aff'd, 267 Ga. 72, 475 S.E.2d 576 (1996).

Owners failed to produce any lien waiver or other documentary proof that paving subcontractor paid paving company for the labor and materials it furnished, and therefore failed to rebut the paving company's prima facie showing that it was entitled to summary judgment on its materialman's lien claim. Little Tallapoosa Dev., Inc. v. Baldwin Paving Co., 251 Ga. App. 238, 553 S.E.2d 860 (2001).

An abandonment of the work before compliance with the contract upon a mere apprehension that payment will not be received is unauthorized and defeats the contractor's claim of lien. Summit-Top Dev., Inc. v. Williamson Constr., Inc., 203 Ga. App. 460, 416 S.E.2d 889 (1992).

Contractor unable to complete job.

- Where the contractor was prevented from completing the job due to the developer's inability to pay, the contractor's cessation of work was not an abandonment of the contract. Summit-Top Dev., Inc. v. Williamson Constr., Inc., 203 Ga. App. 460, 416 S.E.2d 889 (1992).

No enforceable lien absent contract between owner and person furnished materials.

- In the absence of a showing of a contractual relationship between the property owner and the person to whom the materials were furnished, no enforceable lien is created against the owner's property. Ben Hill Ready Mix Concrete Co. v. Prather, 160 Ga. App. 149, 286 S.E.2d 481 (1981); Frank Woods Constr. Co. v. Randi, 177 Ga. App. 438, 339 S.E.2d 406 (1986).

No entitlement to claim in full amount of creditor's materialman's liens.

- Creditor would not necessarily be entitled to a claim in the full amount of the creditor's materialman's liens under O.C.G.A. § 44-14-361 but rather, would only be entitled to recover the damages the creditor suffered pursuant to O.C.G.A. § 51-1-6 due to the debtor's crime of false swearing, which would be the value of liens lost, which in turn depended on the value of the properties to which the liens attached and the existence of any superior liens on those properties. In the absence of an established underlying claim, summary judgment in the creditor's favor on the creditor's nondischargeability claims was not warranted. Thomas Concrete of Ga., Inc. v. Osbourne (In re Osbourne), Bankr. (Bankr. N.D. Ga. Aug. 24, 2017).

Invoices for materials create presumption of receipt by contractor.

- Invoices showing that materials were shipped by the supplier to the contractor for use at the job site created a rebuttable presumption that the materials were received and used by the contractor for the benefit of the property owner. Williamscraft Dev., Inc. v. Vulcan Materials Co., 196 Ga. App. 703, 397 S.E.2d 122 (1990).

Materialman relieved from obtaining judgment before enforcing lien where contractor adjudicated bankrupt.

- A building contractor who filed a bankruptcy petition was "adjudicated a bankrupt" within the meaning of O.C.G.A. § 44-14-361.1 though the contractor was not discharged in bankruptcy; therefore, a materialman was relieved from obtaining a judgment against the contractor before enforcing a materialman's lien against the improved property. Reid v. Harbin Lumber Co., 172 Ga. App. 615, 323 S.E.2d 845 (1984).

Where part of a construction contract is sublet to a subcontractor by a prime contractor, the owner may not be subjected to a lien for any claim or amount which the main contractor could not assert against the owner. Troup Enters. v. Mitchell, Carrington & Rayfield, Inc., 199 Ga. App. 173, 404 S.E.2d 337 (1991).

Subcontractor not eligible for lien.

- Because a subcontractor did not actually comply with O.C.G.A. § 43-14-8(f) as the evidence indicated that a Georgia-licensed electrician that the subcontractor affiliated itself with through an alleged joint venture only presented electrical contracting licenses when permits for the work were applied for and took no action to inspect others' electrical work or to verify that the work complied with the applicable codes, the subcontractor could not enforce the subcontract with the contractor, could not recover in quantum meruit under O.C.G.A. § 9-2-7 as the express contract violated public policy, and could not file a subcontractor's lien under O.C.G.A. §§ 44-14-361.1 and44-14-367. JR Construction/Electric, LLC v. Ordner Constr. Co., 294 Ga. App. 453, 669 S.E.2d 224 (2008).

Completion of contract as question of fact.

- When the record does not disclose as a matter of law whether the work performed by a contractor should be considered as completion of the original contract, the matter rests with the factfinders. Troup Enters. v. Mitchell, Carrington & Rayfield, Inc., 199 Ga. App. 173, 404 S.E.2d 337 (1991).

Evidence demanded a conclusion that a subcontractor substantially completed its contract work on the date when the work was approved as substantially complete, or on the date when the subcontractor gave its warranty, or in all events no later than the date when the subcontractor said that its employees were last on the job. Womack Indus., Inc. v. B & A Equip. Co., 199 Ga. App. 660, 405 S.E.2d 880, cert. denied, 199 Ga. App. 907, 405 S.E.2d 880 (1991).

Materialman's lien statute not applicable to attorney's lien.

- O.C.G.A. § 44-14-361.1 did not apply to the enforcement of an attorney's lien. Hester v. Chalker, 222 Ga. App. 783, 476 S.E.2d 79 (1996).

Applicability to supplier of equipment.

- Under O.C.G.A. §§ 44-14-360(3) and44-14-361.1(a), a supplier of equipment for a construction project was a supplier of material and thus had to furnish its equipment for the improvement of the project in order for its lien to arise. Cent. Atlanta Tractor Sales, Inc. v. Athena Dev., LLC, 289 Ga. App. 355, 657 S.E.2d 290 (2008).

Cited in AAA Plastering Co. v. TPM Constructors, Inc., 247 Ga. 601, 277 S.E.2d 910 (1981); Ansley Park Plumbing & Heating Co. v. Mikart, Inc., 9 Bankr. 144 (Bankr. N.D. Ga. 1981); Linco Constr. Co. v. Tri-City Concrete, Inc., 161 Ga. App. 174, 288 S.E.2d 125 (1982); Dodson v. Earley, 161 Ga. App. 666, 290 S.E.2d 105 (1982); H.R.H. Prince Ltc. Faisal M. Saud v. Batson-Cook Co., 161 Ga. App. 219, 291 S.E.2d 249 (1982); Lincoln Log Homes Mktg., Inc. v. Holbrook, 163 Ga. App. 592, 295 S.E.2d 567 (1982); Cheek v. Lowe's of Ga., Inc., 17 Bankr. 875 (Bankr. M.D. Ga. 1982); Thompson v. Crouch Contracting Co., 164 Ga. App. 532, 297 S.E.2d 524 (1982); Coley Elec. Supply, Inc. v. Colonial Eggs of Alma, Inc., 165 Ga. App. 108, 299 S.E.2d 165 (1983); Dunoco Dev. Corp. v. Ed Taylor Constr. Co., 178 Ga. App. 738, 344 S.E.2d 531 (1986); Spicewood, Inc. v. Ferro Pipeline Co., 181 Ga. App. 277, 351 S.E.2d 711 (1986); Olympic Constr., Inc. v. Village Ctrs., Inc., 80 Bankr. 574 (Bankr. N.D. Ga. 1987); Stonepecker, Inc. v. Shepherd Constr. Co., 188 Ga. App. 513, 373 S.E.2d 295 (1988); Hardee v. Spivey, 193 Ga. App. 234, 387 S.E.2d 430 (1989); Dallas Bldg. Material, Inc. v. Smith, 193 Ga. App. 512, 388 S.E.2d 359 (1989); Roberts v. Porter, Davis, Saunders & Churchill, 193 Ga. App. 898, 389 S.E.2d 361 (1989); CC & B Indus., Inc. v. Stroud, 198 Ga. App. 658, 402 S.E.2d 527 (1991); Abacus, Inc. v. Hebron Baptist Church, Inc., 201 Ga. App. 376, 411 S.E.2d 113 (1991); Georgia N. Contracting, Inc. v. Haney & Haney Constr. & Mgt. Corp., 204 Ga. App. 366, 419 S.E.2d 348 (1992); Resurgens Plaza S. Assocs. v. Consolidated Elec. Supply, Inc., 215 Ga. App. 818, 452 S.E.2d 784 (1994); FDIC v. Gray, 225 Ga. App. 415, 484 S.E.2d 67 (1997); GF/Legacy Dallas, Inc. v. Juneau Constr. Co., LLC, 282 Ga. App. 14, 637 S.E.2d 511 (2006); Consumer Portfolio Servs. v. Rouse, 282 Ga. App. 314, 638 S.E.2d 442 (2006); L. Lowe & Co., Inc. v. Sunset Strip Props., LLC, 283 Ga. App. 357, 641 S.E.2d 797 (2007); LandSouth Constr., LLC v. Lake Shadow Ltd., LLC., 303 Ga. App. 413, 693 S.E.2d 608 (2010); Sun Nurseries, Inc. v. Lake Erma, LLC, 316 Ga. App. 832, 730 S.E.2d 556 (2012); Stock Building Supply, Inc. v. Platte River Insurance Company, 336 Ga. App. 113, 783 S.E.2d 708 (2016).

Compliance

Compliance with section unnecessary as to issue between attorney and client.

- O.C.G.A. § 44-14-361.1 is applicable to attorney's liens only when the struggle is between the attorney and an innocent third party; as to an issue between the attorney and client only, it is not necessary to show compliance with that section in order to recover. Griner v. Foskey, 158 Ga. App. 769, 282 S.E.2d 150 (1981).

Affidavit.

- Trial court did not err by granting partial summary judgment to a buyer on its claim that the seller's mechanic's lien was invalid for failure to record an affidavit for the commencement of an action so as to establish the lien as required by O.C.G.A. § 44-14-361.1(a)(3). Krut v. Whitecap Hous. Group, LLC, 268 Ga. App. 436, 602 S.E.2d 201 (2004).

Description of property.

- Where the description of real property in a materialman's lien inaccurately described the property and did not contain an adequate "key" to remedy the deficiency, the lien was unenforceable. Mull v. Mickey's Lumber & Supply Co., 218 Ga. App. 343, 461 S.E.2d 270 (1995).

Home purchasers and a mortgagee were entitled to summary judgment on a contractor's materialmen's liens because the property descriptions in each of the liens did not accurately describe the purchasers' property as they differed from the description in the warranty and security deeds and, thus, the liens did not comply O.C.G.A. § 44-14-361.1(a). Bollers v. Noir Enters., 297 Ga. App. 435, 677 S.E.2d 338 (2009).

Compliance with copy requirement.

- Trial court did not err in granting a subcontractor summary judgment in the subcontractor's action against a property owner and surety to recover under a lien discharge bond for monies allegedly owed for materials, services, and labor the subcontractor supplied to a construction project because the subcontractor complied with the copy requirement of O.C.G.A. § 44-14-361.1(a)(2); the subcontractor's claim of lien was not ineffective by reason of the slight variance to be found in the copy supplied to the owner because the copy of the claim of lien the subcontractor sent to the owner clearly served the purpose of the claim of lien provisions found in § 44-14-361.1(a)(2) of ensuring that the owner timely received notice of its lien, even though one word of the owner's name was omitted. Madison Retail Suwanee, LLC v. Orion Enters. Sales & Serv., 309 Ga. App. 712, 711 S.E.2d 71 (2011).

Effect of unperfecting on claim for money damages.

- Filing of imperfect notice rendered a materialman's lien unenforceable, but was not a defense to the materialman's complaint for money damages for the value of materials. Consolidated Sys. v. AMISUB, Inc., 261 Ga. 590, 408 S.E.2d 109 (1991).

Liens in excess of remaining contract price were invalid.

- Subcontractor's liens on property were invalid as excessive under O.C.G.A. § 44-14-361.1(e) because the amount of remaining unpaid principal on the contract was $326,661, and the subcontractor filed $727,919 in liens against one parcel (and $1,819,799 against all parcels in the project). Seaboard Constr. Co. v. Kent Realty Brunswick, LLC, 331 Ga. App. 742, 771 S.E.2d 429 (2015).

Identity of real person whose interest in premises subject to lien.

- Where a lien claim was filed solely against the owner's reversionary interest and not against the leasehold interest in the premises, the lien document failed to reveal affirmatively the identity of the real person whose interest in the premises was being subjected to the lien, the lien claim was not effective. Meco of Atlanta, Inc. v. Super Valu Stores, Inc., 215 Ga. App. 146, 449 S.E.2d 687 (1994).

The general contractor was not an indispensable party in an action by an insolvent subcontractor's supplier against the contractor's surety where the supplier satisfied the statutory requirements to prevail on the underlying lien. Hendricks v. Blake & Pendleton, Inc., 221 Ga. App. 651, 472 S.E.2d 482 (1996).

Owner as "contractor."

- There was no reason why an owner could not also have been a contractor for purposes of a materialman's lien; because a property owner listed itself as "general contractor" in its notices of commencement, and because a materials supplier was not in privity with the owner, the supplier was required to provide the owner with the O.C.G.A. § 44-14-361(a) notice to contractor; since the supplier failed to give the proper notice, its materialman's liens were invalid. Roofing Supply of Atlanta, Inc. v. Forrest Homes, Inc., 279 Ga. App. 504, 632 S.E.2d 161 (2006).

Subcontractor satisfied requirements and did not refer to owners as contractors.

- Dismissal of the petitions was affirmed because the subcontractor's claims of liens included statements that the liens were against specific properties for materials furnished to the respective property owner or owners, and at no point in the claims of liens did the subcontractor describe the owners as contractors. Robertson v. Ridge Envtl., LLC, 319 Ga. App. 570, 737 S.E.2d 578 (2013).

Filing of Claims

Failure to meet filing requirement.

- Georgia law requires that a contractor suing an owner directly file a notice of the suit brought against the owner with the clerk of the superior court in which the subject property is located. Where this is not done, the requirements of O.C.G.A. § 44-14-361.1 have not been met; the lien has not been "made good"; and there can be no "relation back" concerning either the lien or any judgment arising out of said lien. Opportunities Industrialization Ctr. of Atlanta, Inc. v. T & B - Scottdale Contractors, 26 Bankr. 394 (Bankr. N.D. Ga. 1983).

Failure of materialman to comply with the notice provisions of O.C.G.A. § 44-14-361.1(a)(3) extinguished the materialman's right to a lien against the improved real estate. The contractor's subsequent bankruptcy filing could not breathe new life into the extinguished right to a lien so as to give the materialman another bite at the apple it had missed on its first bob. Palmer v. Duncan Whsle., Inc., 262 Ga. 28, 413 S.E.2d 437 (1992).

Materialmen's filing of notice against the contractor did not satisfy the requirement for filing a notice of subsequent action against property owners. Northside Wood Flooring, Inc. v. Borst, 232 Ga. App. 569, 502 S.E.2d 508 (1998).

Before a materialman's lien can be allowed, the lien claimant must show compliance with all conditions of O.C.G.A. § 44-14-361.1, and filing the notice of commencement of the action is a prerequisite to the enforceability of the lien; at the time the lien holder fails to file the notice, the lien becomes unenforceable. Gwinnett-Club Assocs., L.P. v. Southern Elec. Supply Co., 242 Ga. App. 507, 529 S.E.2d 636 (2000).

When a Chapter 7 debtor raised two counterclaims to a nondischargeability complaint that both involved state law issues (breach of contract and whether the creditor failed to timely file a notice of action under O.C.G.A. § 44-14-361.1(a)(3) and (4)), a bankruptcy court determined sua sponte that discretionary abstention under 28 U.S.C. § 1334(c)(1) was appropriate. While dischargeability was a bankruptcy matter, the state law liability issues were not so closely related that the dischargeability issue could not be severed, and it was in the best interest of the parties that the debtor's liability under state law be determined in a pending state court lien action. K.A.P., Inc. v. Hardigan (In re Hardigan), Bankr. (Bankr. S.D. Ga. Jan. 18, 2013).

Constructive trust not imposed.

- Georgia law does not impose a constructive trust in favor of a subcontractor on funds paid by an owner to a contractor when the subcontractor has not filed a lien, even when the owner has paid the contractor in full during the time the subcontractor could have filed a lien. Wachovia Bank v. American Bldg. Consultants, Inc., 138 Bankr. 1015 (Bankr. N.D. Ga. 1992).

Reliance on verbal promises to pay.

- A materialman is not excused from filing a claim of lien in reliance on the contractor's verbal promises to pay. Wachovia Bank v. American Bldg. Consultants, Inc., 138 Bankr. 1015 (Bankr. N.D. Ga. 1992).

The three-month deadline for filing a mechanic's lien cannot be excused, relaxed, or extended by the actions of either the debtor or the creditor. Ballard v. Grubbs, 9 Bankr. 499 (M.D. Ga. 1981).

Strict construction of three-month time limit for filing lien.

- The method of time computation in O.C.G.A. § 1-3-1(d)(3), which would allow plaintiff to file its materialman's lien after the three-month period expired because the period expired on a weekend, did not apply to extend the filing requirement of O.C.G.A. § 44-14-361.1(a)(2). United States Filter Distrib. Group, Inc. v. Barnett, 241 Ga. App. 759, 526 S.E.2d 912 (1999), aff'd, 273 Ga. 254, 538 S.E.2d 739 (2000).

Subcontractor was not required to file notice of lien under O.C.G.A. § 44-14-361.1(a)(3) in order to recover on a bond obtained by a general contractor which discharges a lien against property. Burgess v. Travelers Indem. Co., 185 Ga. App. 82, 363 S.E.2d 308 (1987), cert. denied, 185 Ga. App. 909, 363 S.E.2d 308 (1988).

Commencement of Action

The purpose of former O.C.G.A. § 44-14-362(3) (now O.C.G.A. § 44-14-361.1(a)(3)) is to provide notice that a statutory lien has been perfected by the filing of a suit. Opportunities Industrialization Ctr. of Atlanta, Inc. v. T & B - Scottdale Contractors, 26 Bankr. 394 (Bankr. N.D. Ga. 1983).

The purpose of the notice provision is directed toward providing notice to interested third parties rather than property owners. Ragsdale v. Chiu (In re Harbor Club), 185 Bankr. 959 (Bankr. N.D. Ga. 1995).

Filing of notice prerequisite to enforceability of lien.

- The notice required to be filed is the notice of the commencement of action against the contractor and is a prerequisite to the enforceability of the lien. Statham Mach. & Equip. Co. v. Howard Constr. Co., 160 Ga. App. 466, 287 S.E.2d 249 (1981).

A supplier's failure to file, in county wherein property is located, notice of commencement of action against contractor in another county renders the supplier's claim of lien unenforceable. Bettis v. McClure, 160 Ga. App. 412, 287 S.E.2d 291 (1981).

Where actions to enforce a materialman's lien against the property owner are commenced beyond the statutory 12-month period by virtue of the bankruptcy exception, failure properly to file a notice of the claim or action with the superior court clerk of the county wherein the subject lien was filed extinguishes said claim of lien and renders it unenforceable. Newton Lumber & Supply, Inc. v. Crumbley, 161 Ga. App. 741, 290 S.E.2d 114 (1982).

Filing notice is a prerequisite to enforcement of a lien. Frank Woods Constr. Co. v. Randi, 177 Ga. App. 438, 339 S.E.2d 406 (1986).

Filing notice of commencement of the action is a prerequisite to enforceability of the lien. Eurostyle, Inc. v. Jones, 197 Ga. App. 188, 397 S.E.2d 620 (1990).

Because a notice under O.C.G.A. § 44-14-361.1(a)(3) was not filed within 14 days of a lien claimant's suit being initiated, the lien was unenforceable, and the trial court did not err in granting a developer's motion for partial summary judgment against the lien claimant; while the appeals court sympathized with the lien claimant's argument that the claimant received a file-stamped copy and as a result believed no fee was due, ultimately it was the responsibility of plaintiff and plaintiff's counsel to see that the appropriate fees were paid in a timely manner. Kendall Supply, Inc. v. Pearson Cmtys., Inc., 285 Ga. App. 863, 648 S.E.2d 158 (2007).

When a subcontractor filed a proof of claim in a general contractor's bankruptcy action, but did not file a notice of commencement of the action as required by O.C.G.A. § 44-14-361.1(a)(3), the subcontractor's lien claim was extinguished and could not be revived in an action by the subcontractor against the property owner. Action Concrete v. Portrait Homes - Little Suwanee Point, LLC, 285 Ga. App. 650, 647 S.E.2d 353 (2007).

Materialmen's lien creditor was required to file a notice of commencement within 14 days of filing the creditor's proof of claim under O.C.G.A. § 44-14-361.1(a)(3), and the creditor's failure to do so rendered the creditor's claim unperfected under 11 U.S.C. § 546(b)(2), and unsecured, so that the creditor's lien could be avoided under 11 U.S.C. § 545(2). In re R & B Constr., Bankr. (Bankr. N.D. Ga. Aug. 17, 2010).

Lien rights lost where notice not filed.

- Because filing notice is a prerequisite to enforcing a lien, a party's right to enforce a lien based on that action is forever lost as of the fifteenth day after it commences its action without filing notice. The filing of a subsequent action does not revive the party's lien rights. Metromont Materials Corp. v. Cargill, Inc., 221 Ga. App. 853, 473 S.E.2d 498 (1996); Weber Air Conditioning, Inc. v. Triple-R Pooler, Inc., 245 Ga. App. 590, 538 S.E.2d 499 (2000).

Notice requirement applies whether claim brought against contractor or owner.

- The notice requirement of O.C.G.A. § 44-14-361.1(a)(3) applies whether the recovery of the amount of the materialman's claim be properly brought against the contractor or the owner, whichever one is contractually responsible for the debt. Beall v. F.H.H. Constr., Inc., 193 Ga. App. 544, 388 S.E.2d 342 (1989).

All recovery suits, including those against a property owner, are subject to the requirements set forth in O.C.G.A. § 44-14-361.1(a)(3) because application of its provisions is dependent upon whether the defendant is the one primarily or contractually liable for the alleged debt, not upon whether the defendant is a contractor. Ragsdale v. Chiu (In re Harbor Club), 185 Bankr. 959 (Bankr. N.D. Ga. 1995).

Facsimile not effective as notice.

- Trial court properly granted summary judgment to property owner after the subcontractor sued the property owner so that the subcontractor could perfect its materialman's lien against the property owner's property, as the subcontractor's method of providing notice of the lien to the property owner did not comply with applicable statutory law, O.C.G.A. § 44-14-361.1(a)(2), since that statute expressly allowed the lien notice to be provided to the property owner by registered mail, certified mail, or statutory overnight delivery, and not though the facsimile transmission that the subcontractor used, especially since the facsimile transmission was not the equivalent method of providing notice as those methods set forth in the statute. Phillips, Inc. v. Historic Props. of Am., 260 Ga. App. 886, 581 S.E.2d 389 (2003).

Notice of commencement defective.

- Grant of summary judgment to the property owner on a materialman's lien was reversed because it failed to identify or provide contact information for its construction lender in its Notice of Commencement, rendering it fatally defective under O.C.G.A. § 44-14-361.5(d) and because the Notice of Commencement did not substantially comply with § 44-14-361.5(b), the material supplier's failure to file its Notice to Contractor within the prescribed time was excused under § 44-14-361.5(d). Capitol Materials, Inc. v. JLB Buckhead, LLC, 337 Ga. App. 848, 789 S.E.2d 803 (2016).

Timely action against contractor prerequisite.

- Lien claimant had to commence a timely action against a contractor under the statute as a prerequisite to suing the owner on the bond, as such, the property owner did not create a new cause of action for the lien claimant by filing a bond under O.C.G.A. § 44-14-364; the bond stood in the place of the real property as security for the lien claimant and because no new action was created, the lien claimant in an action on the bond still had to comply with the statutory requirements for perfecting a lien. Few v. Capitol Materials Inc., 274 Ga. 784, 559 S.E.2d 429 (2002).

Reasonable time for filing notice.

- A period of 16 days between the date of the filing of the foreclosure suit in one county, where the foreign corporate defendant maintained its registered office, and the date of the filing of the notice of suit, with reference to giving notice to the bona fide purchasers of the property subject to the lien, was not so unreasonable so as to render the claim unenforceable, in that the language of O.C.G.A. § 44-14-361.1(a)(3) requires only a reasonable time for the filing of the notice after the suit had been filed. American Hosp. Supply Corp. v. Starline Mfg. Corp., 171 Ga. App. 790, 320 S.E.2d 857 (1984) (decided prior to 1991 amendment).

Three months meant three calendar months, not 90 days.

- The 1991 version of O.C.G.A. § 44-14-361.1, requiring a contractor to file the contractor's claim of lien three months from the completion of the work, governed and was satisfied by the contractor's filing the claim of lien on September 12 following the completion of work on June 13. The court rejected the owner's argument that "three months" meant 90 days. Fed. Trust Bank v. C. W. Matthews Contr. Co., 312 Ga. App. 200, 718 S.E.2d 63 (2011).

Recording a judgment on real property records some months after commencing a suit does not satisfy the requirement of former O.C.G.A. § 44-14-362(3) (now O.C.G.A. § 44-14-361.1(a)(3)) that notice be filed "at the time of filing such action," and is fatal to a claim of a statutory lien. Opportunities Industrialization Ctr. of Atlanta, Inc. v. T & B - Scottdale Contractors, 31 Bankr. 119 (Bankr. N.D. Ga. 1983) (decided prior to 1991 amendment).

Section deals with actions against contractors, not owners.

- The requirement of O.C.G.A. § 44-14-361.1(a)(3) as to the time within which an action may be commenced relates to the materialman's action against the contractor and not to the action against the owner of the real estate. Opportunities Industrialization Ctr. of Atlanta, Inc. v. T & B - Scottdale Contractors, 26 Bankr. 394 (Bankr. N.D. Ga. 1983).

Application of Bankruptcy Automatic Stay

Exception to the automatic stay pursuant to 11 U.S.C. § 362(b)(3) did not apply to a post-petition mechanic's lien because the lien was not properly perfected and enforceable as the Chapter 7 trustee did not authorize any of the work listed in the lien. Scarver v. Ellis (In re McKeever), 567 Bankr. 652 (Bankr. N.D. Ga. 2017).

Collection action not required where lessee in bankruptcy.

- Bankruptcy of the lessee who had contracted for the leasehold improvements with the unpaid contractor relieved the contractor from the requirement that a collection action against the lessee be commenced before a lien enforcement action could be brought against the lessor. Underground Festival, Inc. v. McAfee Eng'r Co., 214 Ga. App. 243, 447 S.E.2d 683 (1994).

Creditor's time for action tolled under bankruptcy provisions.

- Bankruptcy court held that the procedure under O.C.G.A. § 44-14-361.1 to "make good" a mechanic's or materialman's lien involved creating the lien, not mere perfection, and these acts were subject to an automatic stay; accordingly, because the automatic stay prevented the creditor from complying with O.C.G.A. § 44-14-361.1, the creditor's failure to take further action under that statute was tolled under 11 U.S.C. § 108. In re Durango Ga. Paper Co., 297 Bankr. 316 (Bankr. S.D. Ga. 2003).

Creditor's action not tolled under bankruptcy provisions.

- Chapter 11 trustee could avoid a creditor's mechanic's lien pursuant to 11 U.S.C. § 545(2) because the requirements of the Georgia Lien Statute, O.C.G.A. § 44-14-360 et seq., were acts of perfecting rather than creating or enforcing a lien and, therefore, 11 U.S.C. § 108(c)(2) did not toll creditor's obligation to timely comply with the statute; the creditor's failure to comply with the Georgia Lien Statute's requirements within the statute's time limits and receive the protection of relation back perfection under 11 U.S.C. § 546(b) permitted the trustee to avoid the lien under 11 U.S.C. § 545(2). Durango Ga. Paper Co. v. Milton J. Wood Fire Prot., Inc. (In re Durango Ga. Paper Co.), 356 Bankr. 305 (Bankr. S.D. Ga. 2005).

Avoidance of mechanic's lien in bankruptcy.

- Chapter 7 trustee's right to avoid mechanic's lien on estate property, which attached post-petition and without the trustee's consent or authorization by the court, was not limited by relevant state law because at no point since assuming duties as trustee had the trustee consented to any work being done by the transferee on the property, which was required for a lien to attach. Scarver v. Ellis (In re McKeever), 567 Bankr. 652 (Bankr. N.D. Ga. 2017).

Where action against contractor timely, action against owner need not be commenced within 12 months.

- An action to enforce the lien against the owner need not be instituted within the 12-month statutory period if a claim has been filed by the materialman in the contractor's bankruptcy proceedings during that time, and the filing of the bankruptcy claim satisfies the requirement of former O.C.G.A. § 44-14-362(3) (now O.C.G.A. § 44-14-361.1(a)(3)) of commencing an action within 12 months. Newton Lumber & Supply, Inc. v. Crumbley, 161 Ga. App. 741, 290 S.E.2d 114 (1982); Galbreath v. Vondenkamp, 197 Ga. App. 284, 398 S.E.2d 278 (1990).

Determination of when claims become due.

- The "due date" for purposes of O.C.G.A. § 44-14-361.1(a)(3) does not include an inspection period, but is determined from the last date the equipment was provided for the improvement of the real estate. In accordance with the mandate that Georgia's materialmen's lien law should be dealt with according to the strictest rules of strict construction, the three month period contemplated by O.C.G.A. § 44-14-361.1(a)(2) commences on the last date materials are furnished; there is no reason to treat the calculation of the 12-month period contemplated by O.C.G.A. § 44-14-361(a)(3) differently. Cent. Atlanta Tractor Sales, Inc. v. Athena Dev., LLC, 289 Ga. App. 355, 657 S.E.2d 290 (2008).

In a mechanic's lien foreclosure action brought by a construction company against a property owner, the trial court erred by dismissing the action as untimely since the lien, although stating that the debt became due on a date more than three months from the date the lien was filed, also stated that the construction company provided services, labor, and/or materials to the property owner within three months of the filing of the complaint. D.C. Ecker Constr., Inc. v. Ponce Inv., LLC, 294 Ga. App. 833, 670 S.E.2d 526 (2008), cert. denied, No. S09C0486, 2009 Ga. LEXIS 184 (Ga. 2009).

Failure to state date claim became due did not render lien invalid.

- Summary judgment for an owner in a supplier's suit to enforce a materialman's lien was improper because O.C.G.A. § 44-14-361.1(a)(2) tempered the principle of strict construction with respect to the form of the claim of lien, and the fact that the lien failed to state the date the supplier's claim became due did not render the lien invalid; the claim of lien complied "in substance" with the required form. Vulcan Constr. Materials, LP v. Franklin Builders Props., Inc., 298 Ga. App. 120, 679 S.E.2d 356 (2009).

Amendment of pleadings.

- O.C.G.A. § 9-11-15(c), which permits amendments to relate back to the time of the original pleading, is applicable to an action to enforce a lien under O.C.G.A. § 44-14-361.1. Coe & Payne Co. v. Foster & Kleiser, Inc., 258 Ga. 161, 366 S.E.2d 292 (1988).

No amendment of expired claims.

- O.C.G.A. § 9-11-15(c) which permits amendments to relate back to the time of the original pleading, is inapplicable to an expired action to enforce a lien under O.C.G.A. § 44-14-361.1(a)(2)'s three-month limitations period. Tri-City Constr. Co. v. Sandy Plains Partnership, 206 Ga. App. 506, 426 S.E.2d 57 (1992).

Lis pendens proper where specific performance requested.

- Where purchasers requested specific performance of a contract requiring the property involved to be sold to them, the property was "directly involved," lis pendens was proper, the pleadings were privileged, and its filing was simply notice of the suit, not defamation of the title. Panfel v. Boyd, 187 Ga. App. 639, 371 S.E.2d 222 (1988).

Materialman's allegedly inadequate notice.

- Trial court properly granted summary judgment to the materialman on its action to recover on a lien release bond after an electrical subcontractor did not pay for materials supplied to it by the materialman, and despite the claim of the general contractor and the surety that the materialman did not comply with a lien statute notice requirement; the lien statute notice requirement was meant to protect prospective purchasers from unknowingly buying property encumbered by liens and did not apply to the materialman's situation because the materialman, acting as a lien claimant, was attempting to recover on a lien discharge bond that the general contractor and the surety had filed to discharge the lien against the electrical contractor. Washington Intl Ins. Co. v. Hughes Supply, Inc., 271 Ga. App. 50, 609 S.E.2d 99 (2004).

Action untimely filed.

- A supplier of equipment had not brought its claim against a contractor within 12 months of when the claim became due, as required by O.C.G.A. § 44-14-361.1(a)(3); the 12-month period did not include a period for the inspection of the returned equipment, but was determined from the last date the equipment was furnished for the improvement of the real estate. Cent. Atlanta Tractor Sales, Inc. v. Athena Dev., LLC, 289 Ga. App. 355, 657 S.E.2d 290 (2008).

Concurrent action.

- Subcontractor did not fail to comply with the lien statute in filing a concurrent action against a general contractor on the underlying contract and against the property owner and the surety on the discharge bond because the concurrent action filed by the subcontractor against the general contractor, the owner, and the surety was permitted by the decision of the court of appeals in a prior case; in that case, the court of appeals determined that the subcontractor's action against the general contractor and its action against the owner to enforce the lien could be brought concurrently and could be combined in the same petition. Madison Retail Suwanee, LLC v. Orion Enters. Sales & Serv., 309 Ga. App. 712, 711 S.E.2d 71 (2011).

Insolvency, Absconding, etc., of Contractor or Subcontractor

Notice in action against property owner.

- The fact that a materialman timely filed notice of claim to enforce a lien against the bankrupt general contractor pursuant to O.C.G.A. § 44-14-361.1(a)(3) did not mean that it was not required to file a second notice pursuant to O.C.G.A. § 44-14-361.1(a)(4) in connection with an action against the property owner. Calhoun/Johnson Co. v. Houston Family Trust No. 1, 236 Ga. App. 793, 513 S.E.2d 759 (1999).

Because O.C.G.A. § 44-14-361.1(a)(4) provided that where a contractor was adjudicated bankrupt or, if after an action was filed, no final judgment could be obtained against the contractor because of its adjudication in bankruptcy, the materialman was not required to file an action or obtain judgment against the contractor before enforcing a lien against the improved property; moreover, the materialman could enforce the lien directly against the property by filing an action against the owner within 12 months from the time the lien became due. SAKS Assocs., LLC v. Southeast Culvert, Inc., 282 Ga. App. 359, 638 S.E.2d 799 (2006).

A property owner is entitled to credit for any payments made to the contractor which are shown by competent and relevant evidence to have been applied to valid claims for material or labor. Taverrite v. Lowe's of Franklin, Inc., 166 Ga. App. 346, 304 S.E.2d 78 (1983).

Cost of completing work deducted from contract price when contractor abandons contract.

- Where a contractor, under a definite contract containing a stipulated price for the entire work, undertakes to erect a building on a lot of land and abandons the construction of the building, the owner may complete the work; and if the owner does so, the necessary cost of so doing may be deducted from the contract price, and the property will be subject to the liens of materialmen and laborers to the extent only of the balance. Adams v. W.P. Stephens Lumber Co., 158 Ga. App. 761, 282 S.E.2d 217 (1981).

The trial court correctly granted the property owner's motion for summary judgment as the $59,928 applied under the contract plus the $123,974 spent to complete the house, totaled $183,902, which was $1,902 in excess of the contract price. Maverick Materials, Inc. v. Kauffman, 227 Ga. App. 102, 488 S.E.2d 690 (1997).

Contractor's liability for materials where subcontractor abandons project.

- Where, before construction of a building was completed, a materialman filed its claim of lien for unpaid materials supplied to a subcontractor, and the owner continued to make payments to the contractor who continued to pay the subcontractor, the subcontractor's eventual bankruptcy and abandonment of the project were the responsibility of the contractor. That abandonment had no bearing on the materialman's right to foreclose its lien for such materials as were furnished to the subcontractor and actually used in the project. Mayer Elec. Supply Co. v. Federal Ins. Co., 195 Ga. App. 191, 393 S.E.2d 270 (1990).

Foreclosure Proceedings

In a lien foreclosure materialman must distinguish between an individual and the individual's corporation and must bring an action against the correct account debtor. Ben Hill Ready Mix Concrete Co. v. Prather, 160 Ga. App. 149, 286 S.E.2d 481 (1981); D & N Elec., Inc. v. Underground Festival, Inc., 202 Ga. App. 435, 414 S.E.2d 891 (1991).

Materialman or subcontractor not entitled to judgment in rem where entire contract price expended.

- Where it is necessary to expend the entire contract price in completing the construction called for by the contract, the materialman or subcontractor is not entitled to a judgment in rem against the property. Adams v. W.P. Stephens Lumber Co., 158 Ga. App. 761, 282 S.E.2d 217 (1981).

Procedural error made error in lien draft irrelevant.

- An attorney was properly granted summary judgment in a legal malpractice suit as to an issue of whether the attorney inadequately drafted a lien as the lien foreclosure action was filed by another attorney, who failed to comply with the notice requirement of O.C.G.A. § 44-14-361.1(a), which made the adequacy of the legal description in the lien irrelevant due to that procedural error. Bonner Roofing & Sheet Metal Co. v. Karsman, 285 Ga. App. 586, 646 S.E.2d 763 (2007).

Dormancy of judgment on materialman's lien.

- Trial court erred in granting summary judgment to the lumber company in the company's suit against the property owner to foreclose on a materialman's lien to recover the price of materials sold to the contractor and used to construct the owner's home because the dormancy statute barred foreclosure on the lien more than seven years after the lien was perfected because, when the lumber company failed to take action on the default judgment against the contractor, and the judgment became unenforceable at the end of seven years, the lien was no longer valid and there was nothing to foreclose upon. Lang v. Brand-Vaughan Lumber Co., Inc., 339 Ga. App. 710, 792 S.E.2d 461 (2016).

Required showing.

- To establish and foreclose a lien on the owner's property it must be shown that the owner contracted with someone for these supplies to be furnished, that the person to whom the plaintiff furnished them was connected with that contract, and that the value of the material was within the contract price to which the owner agreed. Spicewood, Inc. v. Dykes Paving & Constr. Co., 199 Ga. App. 165, 404 S.E.2d 305 (1991).

RESEARCH REFERENCES

17B Am. Jur. Pleading and Practice Forms, Mechanics' Liens, § 97.

ALR.

- Delivery of material to building site as sustaining mechanic's lien - modern cases, 32 A.L.R.4th 1130.

Application of relation-back doctrine permitting change in party after statute of limitations has run in state court action - construction cases, 104 A.L.R.6th 1.

Cases Citing O.C.G.A. § 44-14-361.1

Total Results: 11  |  Sort by: Relevance  |  Newest First

Copy

Few v. Capitol Materials, Inc., 559 S.E.2d 429 (Ga. 2002).

Cited 19 times | Published | Supreme Court of Georgia | Jan 14, 2002 | 274 Ga. 784, 2002 Fulton County D. Rep. 151

...rialman's lien against his property by filing a bond. Because the release of the lien through the filing of a bond does not create a separate action, we hold that the supplier is still required to commence an action against the contractor under OCGA § 44-14-361.1 before suing the property owner on the bond....
...d. [1] *430 1. The Georgia General Assembly has enacted a detailed statutory scheme for creating special liens on real property, including liens of materialmen who furnish materials for the building, repairing, or improving of the property. [2] OCGA § 44-14-361.1(a) sets out the provisions for perfecting a lien....
...onths of when the claim became due; and (d) file a notice of the action with the superior court clerk of the county where the lien was filed so that the clerk can enter information about the lawsuit in county records. [3] Subparagraph (a)(4) of OCGA § 44-14-361.1 permits the materialman to bring an action directly against the property owner to enforce the lien against the property without "filing an action or obtaining judgment against the contractor ......
...id before the supplier. OCGA § 44-14-364 permits the property owner to discharge the lien on its real estate by filing a bond in the superior court clerk's office. The legislature has mandated strict compliance with these statutory provisions. OCGA § 44-14-361.1 expressly provides that liens "shall not be effective or enforceable" unless created or declared according to the statute....
...Applying the rule of strict construction, we conclude that the property owner's filing of a bond does not relieve the supplier of the necessity of attempting to perfect its lien by filing a claim against the contractor. Instead, we hold that a lien claimant must commence a timely action against the contractor under OCGA § 44-14-361.1(a)(3) as a prerequisite to suing the owner on the bond....
...an interest in the real estate, and the real estate is no longer affected after the bond discharges the lien on the property. Subsequent court of appeals decisions have refused to extend the Burgess decision to other procedural requirements in OCGA § 44-14-361.1(a), including commencing an action against the contractor within 12 months....
...bankruptcy proceeding since the debt arose six days after Perez filed its bankruptcy petition. [15] Because Capitol did not commence a timely action against Perez before proceeding against Few on his bond or fall within any of the exceptions in OCGA § 44-14-361.1(a)(4), it was not entitled to summary judgment. Judgment reversed. All the Justices concur. NOTES [1] See Few v. Capitol Materials, 247 Ga.App. 93, 543 S.E.2d 102 (2000). [2] See OCGA § 44-14-361. [3] See OCGA § 44-14-361.1(a)(1)-(3). [4] See OCGA § 44-14-361.1(a)....
...234, 387 S.E.2d 430 (1989) (since this action involves a bond, a materialman's failure to file notice of suit is irrelevant); All Phase Elec. Supply Co. v. Foster & Cooper, Inc., 193 Ga.App. 232, 233, 387 S.E.2d 429 (1989) (materialman's failure to file notice under § 44-14-361.1(a)(3) does not bar recovery on its suit on the bond)....
Copy

Palmer v. Duncan Wholesale, Inc., 413 S.E.2d 437 (Ga. 1992).

Cited 19 times | Published | Supreme Court of Georgia | Feb 13, 1992 | 262 Ga. 28, 42 Fulton County D. Rep. 20

...FLETCHER, Justice. We granted a writ of certiorari to the Court of Appeals in Duncan Wholesale v. Palmer, 198 Ga. App. 255 (401 SE2d 291) *29 (1990) to consider whether a materialman, who has lost his lien for failure to comply with the notice requirement of OCGA § 44-14-361.1 (a) (3), may take advantage of a subsequent bankruptcy filing by the contractor and breathe new life into the lien by proceeding under OCGA § 44-14-361.1 (a) (4)....
...of the labor and materials used in the construction. Duncan Wholesale, Inc. ("Duncan") supplied the contractor with some of the materials used, [1] however, the contractor did not fully pay Duncan for the materials it had supplied. Pursuant to OCGA § 44-14-361.1 (a) (2), Duncan filed for record a statutory claim of lien against the improved property owned by the Palmers and the holders of the security deed (hereinafter collectively referred to as the "owners"). Thereafter, pursuant to OCGA § 44-14-361.1 (a) (3), Duncan filed a suit on account against the contractor, who was alive and living in Georgia at that time....
...However, in filing the suit on account, Duncan failed to file the notice required by subparagraph (a) (3). [2] Shortly after the complaint was served upon him, the contractor filed for bankruptcy protection. Duncan then filed an action in rem against the improved property, pursuant to OCGA § 44-14-361.1 (a) (4), seeking to enforce its lien directly against the property. The owners sought to have the latter action dismissed arguing that Duncan's failure to file the notice required by OCGA § 44-14-361.1 (a) (3) in the suit against the contractor was fatal to the commencement of Duncan's subsequent action in rem. The trial court agreed and dismissed the action. Duncan appealed and the Court of Appeals reversed the trial court's dismissal, holding that the failure to file the notice required by OCGA § 44-14-361.1 (a) (3) in the action against the contractor was not fatal to the present action because Duncan was no longer proceeding under that subparagraph but was now proceeding under subparagraph (a) (4)....
...Consequently, we have long recognized that statutes involving materialman's liens must be strictly construed in favor of the property owner and against the materialman. Green v. Farrar Lumber Co., 119 Ga. 30, 32-33 (46 SE 62) (1903). The introductory language of OCGA § 44-14-361.1 (a) provides: To make good the liens specified in paragraphs (1) through (8) of subsection (a) of Code Section 44-14-361, they must be created and declared in accordance with the following provisions, and on failure of any of them the lien shall not be effective or enforceable....
...However, in filing such action, Duncan failed to file the notice with the superior court clerk required by subparagraph (a) (3). In so doing, Duncan failed to follow the statutory provisions required "[t]o make good the [lien]" and, because of such failure, "the lien shall not be effective or enforceable." OCGA § 44-14-361.1....
...or, the only effect of the contractor's subsequent bankruptcy filing would have been to relieve Duncan of the necessity of obtaining a judgment against the contractor before proceeding to obtain an in rem judgment against the improved property. OCGA § 44-14-361.1 (a) (4)....
...The Court of Appeals erred by reversing the trial court's dismissal of Duncan's action in rem. Judgment reversed. Clarke, C. J., Weltner, P. J., Bell, Hunt and Benham, JJ., concur. NOTES [1] In supplying materials to the contractor, Duncan complied with OCGA § 44-14-361.1 (a) (1). [2] The actions involved in this litigation took place in 1988 and 1989 and, at that time, the notice required by OCGA § 44-14-361.1 (a) (3) had to be filed as follows: ......
Copy

Browning v. Gaster Lumber Co., 475 S.E.2d 576 (Ga. 1996).

Cited 13 times | Published | Supreme Court of Georgia | Sep 9, 1996 | 267 Ga. 72, 96 Fulton County D. Rep. 3217

...e $41,000 was applied before or after Gaster's lien was filed. The trial court held that because the aggregate amount of liens [1] exceeded the contract price of the improvements made, the Brownings had a complete defense to Gaster's lien under OCGA § 44-14-361.1(e) and discharged the lien....
...were disbursed to the other materialmen and laborers before the filing of Gaster's lien. Gaster Lumber Co. v. Browning, 219 Ga.App. 435(1), 465 S.E.2d 524 (1995). We granted the writ of certiorari to consider whether an owner is entitled under OCGA § 44-14-361.1 to claim credit for those sums the owner pays the contractor before the lien is filed, which sums are shown to have been disbursed post-lien to other potential lien claimants....
...man's lien only by showing that the contractor has disbursed sums received for the project at a time when no materialman or laborer had filed for record any claim of lien. Therefore, we affirm the Court of Appeals. In construing the language in OCGA § 44-14-361.1, we recognize that because materialman's liens are in derogation of the common law, statutes involving such liens must be strictly construed in favor of the property owner and against the materialman....
...Farrar Lumber, supra, one of the first cases to construe the materialman's lien statute, holding that its purpose is "to protect materialmen and laborers for work done and material furnished to contractors who fail or refuse to pay." Id. at 33, 46 S.E. 62. Turning to the specific language in the statute, OCGA § 44-14-361.1(a)(4) provides in pertinent part that the owner of the real estate improved, who has paid the agreed price or any part of same, may set up the payment in any action brought and prove by competent and relevant evidence that the payments were applied as provided by law....
...rties entitled to receive them. Furthermore, the language requires the payments that are applied to be "as provided by law," *578 which we construe as referencing the strict hierarchy established by the Legislature for the ranking of liens. See OCGA § 44-14-361.1(b) (date of filing of lien); OCGA § 44-14-361.1(c) (rank based on nature of lien, e.g., taxes, laborers, landlords). There is no question but that under this statutory scheme, a lien properly filed and recorded is superior to any inchoate lien claim. Based on the plain language in the statute, we construe the phrase "applied as provided by law" in OCGA § 44-14-361.1(a)(4) as conditioning the property owner's defense upon proof that the payments were ultimately disbursed to materialmen and laborers in proper order according to the hierarchical rank set forth in subsections (b) and (c) of the statute....
...r a lien is filed and recorded may not be set up in defense of a foreclosure action on such lien unless such payments were made to parties with superior-ranking lien claims. Accordingly, we conclude that an owner is not entitled to credit under OCGA § 44-14-361.1(a)(4) where pre-lien payments to the contractor are disbursed post-lien by the contractor in payment of inferior-ranked, inchoate claims of materialmen and laborers. Nothing in Green v. Farrar Lumber, supra, conflicts with our interpretation of OCGA § 44-14-361.1(a)(4)....
...urnished to the contractor, filed subsequently to payment and application of the full contract price as above indicated." (Emphasis supplied.) The Court of Appeals, however, has explicitly recognized that the relevant time for the defense under OCGA § 44-14-361.1(a)(4) is the time the contractor disburses payment to other materialmen, not the time the owner pays the contractor....
...[3] Based on our analysis of the statutory language and the case law interpreting it, we conclude that it is the responsibility of the owner to see that the contractor disburses the money received in a proper manner at a time before liens are filed and that the owner cannot avail himself of the defense in OCGA § 44-14-361.1(a)(4) unless he can prove that the payments made to the contractor "`were "properly appropriated," i.e., paid before the filing of the lien.'" Gaster Lumber Co....
...NOTES [1] The trial court's calculation of the aggregate amount of liens included the Brownings' post-abandonment expenditures plus the $41,000 paid on inchoate claims on the property. [2] Although Green construes the language in the predecessor to subsection (e) of OCGA § 44-14-361.1, its holding has been applied in cases proceeding under the subsequently-enacted language in subsection (a)(4)....
Copy

U. S. Filter Distrib. Grp., Inc. v. Barnett, 273 Ga. 254 (Ga. 2000).

Cited 11 times | Published | Supreme Court of Georgia | Nov 13, 2000 | 538 S.E.2d 739

...Filter Distribution Group’s petition for certiorari in this materialmen’s lien case in order to address whether the Court of Appeals correctly held in U S. Filter Distrib. v. Barnett, 241 Ga. App. 759 (1) (526 SE2d 912) (1999) that the requirement of OCGA § 44-14-361.1 (a) (2) that a lien be filed “within three months after the material or machinery is furnished” is not subject to calculation in accordance with the general provision for the computation of time specified in OCGA § 1-3-1 (d) (3)....
...Filter filed a lien on the property. When U. S. Filter filed suit to recover under appellees’ lien discharge bond, the trial court denied its motion for summary judgment finding that U. S. Filter had failed to file its lien within the three-month limit set forth in OCGA § 44-14-361.1 (a) (2)....
...not be counted but the last day shall be counted” and that in situations where the last day falls on Saturday, Sunday, or a public and legal holiday as set forth in OCGA § 1-4-1, the last day will be deemed to fall on the next business day. OCGA § 44-14-361.1 (a) (2) specifically provides that the lien must be filed “within three months after the material......
...limited strictly to the meaning of the language employed and not extended beyond the plain and explicit terms of the statute. Honeycutt v. Edwards, 136 Ga. App. 486 (1) (221 SE2d 678) (1975). Hence, this Court construed a predecessor statute to OCGA § 44-14-361.1 (a) (2) to find that the calculation of the three-month period begins on the first day upon which the right could lawfully have been asserted....
...In other words, the last day on which materials have been furnished falls “within” the three-month period and is included as the first day for calculating the appropriate filing time. Id. We have applied this specific method of computing the three-month time. *255period in OCGA § 44-14-361.1 (a) (2) in accordance with the mandate that Georgia’s materialmen’s lien law “should be dealt with according to the strictest rules of strict construction.” Green v. Farrar Lumber Co., 119 Ga. 30, 33 (46 SE 62) (1903). OCGA § 44-14-361.1 (a) (2) comes within the exception provided in OCGA § 1-3-1 (d) (3) because its application to the materialmen’s lien statute would have the unauthorized consequence of expanding the three-month filing period beyond the time specified in the lien statute. Although OCGA § 44-14-361.1 (a) (2) specifically requires filing within three months of the furnishing of materials, OCGA § 1-3-1 (d) (3) allows filing within three months and one day, since it does not include in its calculation the first day within the three-month period....
...ainst the materialman. Palmer v. Duncan Wholesale, 262 Ga. 28, 30 (1) (413 SE2d 437) (1992); Green v. Farrar Lumber, supra, 119 Ga. at 32-33. Accordingly, we agree with the Court of Appeals that because of the strict construction applicable to OCGA § 44-14-361.1 (a) (2), calculation of the three-month filing period therein comes within the exception to OCGA § 1-3-1 (d) (3)....
Copy

Benning Constr. Co. v. Dykes Paving & Constr. Co., 426 S.E.2d 564 (Ga. 1993).

Cited 8 times | Published | Supreme Court of Georgia | Mar 8, 1993 | 263 Ga. 16, 92 Fulton County D. Rep. 958

...The Court of Appeals affirmed Benning Constr. Co. v. Dykes Paving &c. Co., 204 Ga. App. 73 (418 SE2d 620) (1992), holding that Lanier was a subcontractor within the meaning of OCGA § 44-14-360 (9), and, therefore, Dykes was entitled to a claim of lien under OCGA § 44-14-361.1....
Copy

COE & PAYNE Co. v. Foster & Kleiser, Inc., 366 S.E.2d 292 (Ga. 1988).

Cited 8 times | Published | Supreme Court of Georgia | Apr 7, 1988 | 258 Ga. 161

...The trial court allowed the amendment. Foster & Kleiser, Inc., then moved for judgment on the pleadings on the ground that no action to foreclose the lien had been initiated against it (i.e., Foster & Kleiser, Inc.) within the twelve-month period provided by OCGA § 44-14-361.1....
Copy

Noland Co. v. Ford Motor Co., 369 S.E.2d 910 (Ga. 1988).

Cited 6 times | Published | Supreme Court of Georgia | Jul 14, 1988 | 258 Ga. 469

...fe sub-contracted with Noland *470 for materials of a value of $13,181.16, which were delivered to the site. In 1984 Huffman-Wolfe, with its debt to Noland unpaid, filed a voluntary petition in bankruptcy. Noland complied with the provisions of OCGA § 44-14-361.1 (a) (2) and (4) in filing a claim of lien in the amount of $11,832.47 against real property owned by Ford and in commencing an action in rem to foreclose its lien against the real property of Ford into which Noland's materials had been incorporated. Noland did not immediately file a notice of the commencement of the action in the office of the clerk of the county in which Ford's real property was located, as indicated in OCGA § 44-14-361.1 (a) (3), but did file such a notice sixty-six days later....
...ection 44-14-361, they must be created and declared in accordance with the following provisions, and on failure of any of them the lien shall not be effective or enforceable. Ford contends that because Noland did not file the notice required by OCGA § 44-14-361.1 (a) (3) until sixty-six days after the commencement of its action to foreclose, Noland has failed to comply with the code section, and its action should be dismissed. The Court of Appeals agreed, Ford Motor Co. v. Noland Co., 186 Ga. App. 541 (368 SE2d 763) (1988). This court granted certiorari to determine whether a lien claimant who institutes an action under the provisions of OCGA § 44-14-361.1 (a) (4) must comply with the notice provision of OCGA § 44-14-361.1 (a) (3) in order to enforce a lien. 1. OCGA § 44-14-361.1 (a) (3) regulates the institution of an action against a contractor or sub-contractor to recover the amount of a lien claim, and requires that: [A]t the time of filing such action, the party claiming the lien shall file a notice with the clerk of the superior court of the county wherein the subject lien was filed. This statute then details the requisite information for the notice. 2. OCGA § 44-14-361.1 (a) (4) regulates the institution of an action in rem against real property that has been improved by material furnished by the lien claimant, when the defaulting contractor is a bankrupt. No requirement is set out in this subparagraph for the filing of a notice with the clerk of the superior court in the county where the lien was filed. 3. We do not construe the requirements of OCGA § 44-14-361.1 (a) (3) to impose a requirement of notice when an action is instituted under the provisions of OCGA § 44-14-361.1 (a) (4). OCGA § 44-14-361.1 *471 (a) (3) states: The commencement of an action for the recovery of his claim within 12 months from the time the same shall become due....
Copy

Consol. Sys., Inc. v. AMISUB (McIntosh Trail Reg'l Med. Ctr.), Inc., 261 Ga. 590 (Ga. 1991).

Cited 4 times | Published | Supreme Court of Georgia | Sep 13, 1991 | 408 S.E.2d 109

...he sale of real property owned by AMI on which Consolidated had filed a materialman’s lien. AMI moved to dismiss the complaint, on the ground the lien was unenforceable because Consolidated had failed to comply with the notice requirements of OCGA § 44-14-361.1 (a) (3)....
...In Count Three, Consolidated sought *591attorney fees and expenses under OCGA § 9-15-14. The trial court treated AMI’s motion to dismiss as a motion for summary judgment. After a hearing, the court granted AMI’s motion and dismissed Consolidated’s complaint, on the ground Consolidated gave defective notice under § 44-14-361.1 (a) (3)....
...Reconsideration denied October 3, 1991. Culbreth & Clarke, J. Caleb Clarke III, for appellant. Mullins, Whalen & Shepherd, Newton M. Galloway, Bannister & Black, Charles C. Black, for appellee. *5911. Consolidated admits that it gave defective notice under § 44-14-361.1 (a) (3), but contends that defective notice should not render a lien unenforceable, and that therefore the trial court erred in granting summary judgment to AMI on Count One of its complaint. We conclude that the filing of imperfect notice does render the lien unenforceable and that the court did not err in granting AMI’s motion on Count One. OCGA § 44-14-361.1 sets forth the requirements for the creation of materialmen’s liens, and § 44-14-361.1 (a) provides that “on failure of any of them the lien shall not be effective or enforceable.” The creation of liens under § 44-14-361.1 is in derogation of the common law, and strict compliance with the requirements of § 44-14-361.1 is required. Allied Electrical Contractors v. Kern &c., 184 Ga. App. 747, 748 (362 SE2d 452) (1987). Because Consolidated gave defective notice under § 44-14-361.1 (a) (3), Consolidated’s lien is rendered unenforceable under the plain language of the statute....
...Therefore, the court only had before it a motion for partial summary judgment, and erred in granting AMI’s motion on Consolidated’s entire complaint. Frank Woods Constr. Co. v. Randi, 177 Ga. App. 438, 439 (2) (339 SE2d 406) (1986). Moreover, the defective notice under § 44-14-361.1 (a) (3) would not be a defense to Count Two of Consolidated’s complaint, as, under the terms of § 14-44-361.1, the defective notice only renders Consolidated’s lien unenforceable. Judgment affirmed in part; reversed in part. All the Justices concur, except Clarke, C....
Copy

Massey v. Duke Builders, Inc, 849 S.E.2d 186 (Ga. 2020).

Published | Supreme Court of Georgia | Sep 28, 2020 | 310 Ga. 153

...We express no opinion on that issue. See Doctors Hosp. of Augusta v. Alicea, 299 Ga. 315, 321-322 n.7 (788 SE2d 392) (2016). 4 express or implied contract, subcontract, or purchase order subject to subsection (e) of Code Section 44-14-361.1.” Under subsection (c), which was added to OCGA § 44-14-361 in 2013, the lien claimant can file a lien “based on the contracted price of the work, which includes overhead costs and profit, rather than just on the val...
...the “amount due and owing” under the contract. Thus, the lien is limited to amounts actually due to the claimant based on the work completed at the time the lien is filed, not amounts that the claimant was expecting to receive for future work under the contract. OCGA § 44-14-361.1 (e) also mentions the contract price but again limits the lien to the contract price of work already done by referring to the work in the past tense: “In no event shall the aggregate amount of 5 ...
...direct that the lien be amended by Duke Builders, the Court of Appeals added an extra step that does not appear to have been taken in the cases cited above involving partially improper liens. All of those cases, however, were decided before OCGA § 44-14-361.1 (a.1) was enacted in 2010....
Copy

US Filter Distrib. Grp. v. Barnett, 538 S.E.2d 739 (Ga. 2000).

Published | Supreme Court of Georgia | Nov 13, 2000 | 273 Ga. 254, 2000 Fulton County D. Rep. 4174

...Filter Distribution Group's petition for certiorari in this materialman's lien case in order to address whether the Court of Appeals correctly held in U.S. Filter Distrib. v. Barnett, 241 Ga.App. 759(1), 526 S.E.2d 912 (1999) that the requirement of OCGA § 44-14-361.1(a)(2) that a lien be filed "within three months after the material or machinery is furnished" is not subject to calculation in accordance with the general provision for the computation of time specified in OCGA § 1-3-1(d)(3)....
...Filter filed a lien on the property. When U.S. Filter filed suit to recover under appellees' lien discharge bond, the trial court denied its motion for summary judgment finding that U.S. Filter had failed to file its lien within the three-month limit set forth in OCGA § 44-14-361.1(a)(2)....
...ll not be counted but the last day shall be counted" and that in situations where the last day falls on Saturday, Sunday, or a public and legal holiday as set forth in OCGA § 1-4-1, the last day will be deemed to fall on the next business day. OCGA § 44-14-361.1(a)(2) specifically provides that the lien must be filed "within three months after the material *740 ......
...limited strictly to the meaning of the language employed and not extended beyond the plain and explicit terms of the statute. Honeycutt v. Edwards, 136 Ga.App. 486(1), 221 S.E.2d 678 (1975). Hence, this Court construed a predecessor statute to OCGA § 44-14-361.1(a)(2) to find that the calculation of the three-month period begins on the first day upon which the right could lawfully have been asserted....
...In other words, the last day on which materials have been furnished falls "within" the three month period and is included as the first day for calculating the appropriate filing time. Id. We have applied this specific method of computing the three-month time period in OCGA § 44-14-361.1(a)(2) in accordance with the mandate that Georgia's materialman's lien law "should be dealt with according to the strictest rules of strict construction." Green v. Farrar Lumber Co., 119 Ga. 30, 33, 46 S.E. 62 (1903). OCGA § 44-14-361.1(a)(2) comes within the exception provided in OCGA § 1-3-1(d)(3) because its application to the materialmen's lien statute would have the unauthorized consequence of expanding the three month filing period beyond the time specified in the lien statute. Although OCGA § 44-14-361.1(a)(2) specifically requires filing within three months of the furnishing of materials, OCGA § 1-3-1(d)(3) allows filing within three months and one day, since it does not include in its calculation the first day within the three month period....
...aterialman. Palmer v. Duncan Wholesale, 262 Ga. 28, 30(1), 413 S.E.2d 437 (1992); Green v. Farrar Lumber, supra, 119 Ga. at 32-33, 46 S.E. 62. Accordingly, we agree with the Court of Appeals that because of the strict construction applicable to OCGA § 44-14-361.1(a)(2), calculation of the three-month filing period therein comes within the exception to OCGA § 1-3-1(d)(3)....
...850 (1897) as authority for holding that OCGA § 1-3-1(d)(3) is not applicable. Prior to 1985, OCGA § 1-3-1(d)(3) did apply only to statutory periods which were measured in days. This absence of any applicable statute compelled this Court in Jones to compute the three-month period contained in the predecessor to OCGA § 44-14-361.1(a)(2) by applying the general judicially-prescribed method of computation....
...318, 433 S.E.2d 410 (1993); Loveless v. Grooms, 180 Ga.App. 424, 425, 349 S.E.2d 281 (1986). This broad provision clearly superseded the Jones method of computation of the time prescribed for the exercise of the privilege of filing a claim of lien pursuant to OCGA § 44-14-361.1(a)(2), unless the period of time prescribed in that lien statute comes within the exception in OCGA § 1-3-1(d)(3) for "time period computations specifically applying to other laws...." OCGA § 44-14-361.1(a)(2) cannot come within this exception, however, because that statute "does not itself provide for any method of computing the [three-month] period provided therein." Davis v....
Copy

Consol. Sys. v. Amisub, 408 S.E.2d 109 (Ga. 1991).

Published | Supreme Court of Georgia | Sep 13, 1991 | 261 Ga. 590

...the sale of real property owned by AMI on which Consolidated had filed a materialman's lien. AMI moved to dismiss the complaint, on the ground the lien was unenforceable because Consolidated had failed to comply with the notice requirements of OCGA § 44-14-361.1(a)(3)....
...In Count Three, Consolidated sought attorney fees and expenses under OCGA § 9-15-14. The trial court treated AMI's motion to dismiss as a motion for summary judgment. After a hearing, the court granted AMI's motion and dismissed Consolidated's complaint, on the ground Consolidated gave defective notice under § 44-14-361.1(a)(3). Consolidated has now filed this appeal, and we affirm in part and reverse in part. 1. Consolidated admits that it gave defective notice under § 44-14-361.1(a)(3), but contends that defective notice should not render a lien unenforceable, and that therefore the trial court erred in granting summary judgment to AMI on Count One of its complaint. We conclude that the filing of imperfect notice does render the lien unenforceable and that the court did not err in granting AMI's motion on Count One. OCGA § 44-14-361.1 sets forth the requirements for the creation of materialmen's liens, and § 44-14-361.1(a) provides that "on the failure of any of them the lien shall not be effective or enforceable." The creation of liens under § 44-14-361.1 is in derogation of the common law, and strict compliance with the requirements of § 44-14-361.1 is required. Allied Electrical Contractors v. Kern & Co., 184 Ga.App. 747, 748, 362 S.E.2d 452 (1987). Because Consolidated gave defective notice under § 44-14-361.1(a)(3), Consolidated's lien is rendered unenforceable under the plain language of the statute....
...Therefore, the court only had before it a motion for partial summary judgment, and erred in granting AMI's motion on Consolidated's entire complaint. Frank Woods Construction Co., Inc. v. Randi, 177 Ga.App. 438, 439(2), 339 S.E.2d 406 (1986). Moreover, the defective notice under § 44-14-361.1(a)(3) would not be a defense to Count Two of Consolidated's complaint, as, under the terms of § 44-14-361.1, the defective notice only renders Consolidated's lien unenforceable....