Maine Revised Statutes

Me. Rev. Stat. tit. 35, § 2482 (2026)

Permits to construct facilities

✓ current as of May 2026
Find cases: SyfertCases citing this section ME-LEGlegislature.maine.gov JustiaTitle on Justia CornellLII Search CasesGoogle Scholar
(REPEALED)
SECTION HISTORY
PL 1967, c. 262, §6 (RPR). PL 1987, c. 141, §A5 (RP).
Notes of Decisions
Cited in 2 cases, 1967–1971 · leading case: Bangor-Hydro Elec. Co. v. Johnson, 226 A.2d 371 (Me. 1967).
Bangor-Hydro Elec. Co. v. Johnson, 226 A.2d 371 (Me. 1967). · cites it 2× “h it owns transmission lines consisting of wooden poles with wires attached, which poles are set into the ground within the limits of designated public highways and their locations in each instance authorized by written permits obtained from the public officials, authorized to…”
Cent. Maine Power Co. v. Waterville Urban Renewal Auth., 281 A.2d 233 (Me. 1971). “We do recognize that the municipal officers of Waterville, a city with a population under 40,000 inhabitants, were not expressly empowered under 35 M.R.S.A. § 2482 to revoke the location of poles of electric companies and order their removal upon the grant of other suitable…”
Annotations are extracted automatically from the opinions in the Syfert caselaw corpus and ranked by authority, recency, and treatment. Dots show Syfertize treatment of the citing case itself.