Massachusetts General Laws homeSearch Massachusetts
Mass. Gen. LawsPart I Title III Chapter 30

Mass. Gen. Laws ch. 30, § 39J (2026)

Public construction contracts; effect of decisions of contracting body or administrative board

Edition and currency
text as last checked Sept. 2026 (this copy records no edition or section history). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTtext as last checked Sept. 2026 (this copy records no edition or section history) cited 1965–2013 13citing cases
At a glance

Courts have cited this section in 13 opinions since 1965.

Section 39J. Notwithstanding any contrary provision of any contract for the construction, reconstruction, alteration, remodeling, repair or demolition of any public building or public works by the commonwealth, or by any county, city, town, district, board, commission or other public body, when the amount of the contract is more than five thousand dollars in the case of the commonwealth and more than two thousand dollars in the case of any county, city, town, district, board, commission or other public body, a decision, by the contracting body or by any administrative board, official or agency, or by any architect or engineer, on a dispute, whether of fact or of law, arising under said contract shall not be final or conclusive if such decision is made in bad faith, fraudulently, capriciously, or arbitrarily is unsupported by substantial evidence, or is based upon error of law.

The 13 cases that cite Mass. Gen. Laws ch. 30, § 39J most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
YELLOWJ. A. Sullivan Corp. v. Commonwealth, 494 N.E.2d 374 (Mass. 1986).
cites § 39J 2×cited by 206 cases
Overruled by G4S Technology LLC v. Massachusetts Technology Park Corp. on other grounds: 2 citing opinions limit it to other grounds.
Where it cites § 39J
“” According to the Commonwealth’s argument, the architect was empowered to reject the plaintiff’s request for additional expenses for ledge removal (and he did) and under G. L. c. 30, § 39J, 5 the architect’s decision, not having been made in bad faith or in a fraudulent,…”
The case’s holding
A contract must be construed to give reasonable effect to every provision and clause contained within the instrument.
Later courts cite it for
“a finding is 'clearly erroneous' when although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed.” · 19 citing courts
2
GREENMassachusetts High. Dep't v. Perini Corp., 981 N.E.2d 721 (Mass. App. Ct. 2013).
cites § 39J 2×cited by 9 cases
Where it cites § 39J
“The project director’s decisions could be appealed to the board of commissioners of the Massachusetts Highway Department or to the Superior Court, pursuant to G. L. c. 30, § 39J. As work on the project progressed, hundreds of disputes arose involving additional costs incurred by…”
3
GREENAcmat Corp. v. Daniel O'connell's Sons, Inc., 455 N.E.2d 652 (Mass. App. Ct. 1983).
cites § 39J 1×cited by 8 cases
Where it cites § 39J
“G. L. c. 30, § 39J. Compare Hurley v. Boston, 244 Mass.”
4
GREENFontaine Bros. v. Springfield, 617 N.E.2d 1002 (Mass. App. Ct. 1993).
cites § 39J 1×cited by 6 cases
Where it cites § 39J
“Although the words “final” and “binding” have a terminal and unconditional quality, the power of the architect on a construction job is, of course, not without limit.”
5
GREENJ.J. Finn Elec. Serv., Inc. v. P & H Gen. Contractors, Inc., 432 N.E.2d 116 (Mass. App. Ct. 1982).
cites § 39J 1×cited by 3 cases
Where it cites § 39J
“of the several kinds of work to be done under [the] contract, and [to] decide all questions ... as to the interpretation of the .”
6
GREENA. Bonfatti & Co. v. Town of Rockport, 429 N.E.2d 75 (Mass. App. Ct. 1981).
cites § 39J 1×cited by 1 case
Where it cites § 39J
“” G. L. c. 30, § 39J, inserted by St. 1961, c.”
7
NEUTRALPeabody N.E., Inc. v. Town of Marshfield, 4 Mass. L. Rptr. 413 (Mass. Super. Ct. 1995).
cites § 39J 2×cited by 2 cases
Where it cites § 39J
“00 and, subject to further modification by the Master, Conclusion 31 is to be amended to refer to M.G.L.c. 30, §39J. C. CHAPTER 93A In Findings 448 and 449 and Conclusion 47, the Master found that certain actions on the part of Marshfield and/or Metcalf & Eddy were made in bad…”
8
NO FLAGJohn J. Petruzzi-William E. Forrester, Inc. v. Massachusetts Tpk. Auth., 9 Mass. L. Rptr. 184 (Mass. Super. Ct. 1998).
cites § 39J 10×cited by 0 cases
Where it cites § 39J
“The MTA now moves for summary judgment on the grounds that Petruzzi-Foixester is liable under the contract for any cost incurred for time lost due to bad weather, that Petruzzi-Forrester is precluded from disputing its other claims because it failed to follow the required claim…”
9
cites § 39J 1×cited by 1 case
Where it cites § 39J
“The dispute was whether open balcony floors or porch floors could be regarded *799 as roofs and includable in the obligation of Hampden under its subcontract. The judge found no support in fact or law for the contention that the decision made by the chairman of the State Housing…”
10
NO FLAGOstrow Elec. Co. v. J.L. Marshall & Sons, Inc., 798 N.E.2d 310 (Mass. App. Ct. 2003).
cites § 39J 2×cited by 0 cases
Where it cites § 39J
“See G. L. c. 30, § 39J. As to the terms of addendum 7, Ostrow submitted an affidavit referencing addendum 7’s exclusion of “outlet boxes” from work to be done by the audiovisual subcontractor, and averred, “I knew from my experience and the Mass.”
11
NO FLAGZeraschi & Son, Inc. v. R.W. Granger & Sons, Inc., 13 Mass. L. Rptr. 187 (Mass. Super. Ct. 2001).
cites § 39J 1×cited by 0 cases
Where it cites § 39J
“As a threshold issue, the DCPO argues that language contained in the DCPO’s “Notice to Contractors” coupled with G.L.c. 30, §39J 4 empowered the architect to order Zeraschi to perform the lead coated copper flashing, and that the decision, not having been made in bad faith or in…”
12
NO FLAGCCM Corp. v. Massachusetts Tpk. Auth., 5 Mass. L. Rptr. 58 (Mass. Super. Ct. 1996).
cites § 39J 1×cited by 0 cases
Where it cites § 39J
“Pursuant to M.G.L.c. 30, §39J, the decisions of an engineer so designated are final and conclusive unless such decision was “made in bad faith, fraudulently, capriciously, or arbitrarily, or is unsupported by substantial evidence, or is based upon error of law.”
13
NO FLAGJRJ Constr. Co. v. R.W. Granger & Sons, Inc., 10 Mass. L. Rptr. 385 (Mass. Super. Ct. 1999).
cites § 39J 1×cited by 0 cases
Where it cites § 39J
“G.L.c. 30, §39J also addresses the decisions of architects under public construction contracts.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
196519892013

One bar per year. Tallest: 1 case in 1965. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Mass. App. Ct.6Mass. Super. Ct.5Mass.2
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: text as last checked Sept. 2026 (this copy records no edition or section history). Syfert holds no earlier or later version of this section.

Massachusetts General Laws Home  |  Search Massachusetts  |  Search cases for this section  |  syfert.com