Massachusetts General Laws homeSearch Massachusetts
Mass. Gen. LawsPart I Title III Chapter 30

Mass. Gen. Laws ch. 30, § 39N (2026)

Construction contracts; equitable adjustment in contract price for differing subsurface or latent physical conditions

Edition and currency
text as last checked Sept. 2026 (this copy records no edition or section history). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTtext as last checked Sept. 2026 (this copy records no edition or section history) cited 1980–2026 16citing cases
At a glance

Courts have cited this section in 16 opinions since 1980, 3 of them in the last five years.

Section 39N. Every contract subject to section forty-four A of chapter one hundred and forty-nine or subject to section thirty-nine M of chapter thirty shall contain the following paragraph in its entirety and an awarding authority may adopt reasonable rules or regulations in conformity with that paragraph concerning the filing, investigation and settlement of such claims:

If, during the progress of the work, the contractor or the awarding authority discovers that the actual subsurface or latent physical conditions encountered at the site differ substantially or materially from those shown on the plans or indicated in the contract documents either the contractor or the contracting authority may request an equitable adjustment in the contract price of the contract applying to work affected by the differing site conditions. A request for such an adjustment shall be in writing and shall be delivered by the party making such claim to the other party as soon as possible after such conditions are discovered. Upon receipt of such a claim from a contractor, or upon its own initiative, the contracting authority shall make an investigation of such physical conditions, and, if they differ substantially or materially from those shown on the plans or indicated in the contract documents or from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the plans and contract documents and are of such a nature as to cause an increase or decrease in the cost of performance of the work or a change in the construction methods required for the performance of the work which results in an increase or decrease in the cost of the work, the contracting authority shall make an equitable adjustment in the contract price and the contract shall be modified in writing accordingly.

The 16 cases that cite Mass. Gen. Laws ch. 30, § 39N most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENSutton Corp. v. Metro. Dist. Comm'n, 667 N.E.2d 838 (Mass. 1996).
cites § 39N 7×cited by 16 cases
Where it cites § 39N
“5 By a letter dated April 27, 1981, Sutton advised the MDC that it had encountered a “changed condition” within the scope of G. L. c. 30, § 39N (1994 ed.), and requested permission to use a substitute system for compacting the soil.”
2
GREENNota Constr. Corp. v. Keyes Assocs., Inc., 694 N.E.2d 401 (Mass. App. Ct. 1998).
cites § 39N 1×cited by 131 cases
Where it cites § 39N
“See G. L. c. 30, § 39N. Notwithstanding the presence of disputed facts, Keyes argues Nota’s claim is barred because the economic loss doctrine, Bay State-Spray & Provincetown S.”
The case’s holding
An exception to the economic loss doctrine permits recovery for economic losses resulting from negligent misrepresentation.
Later courts cite it for
“in order to recover for negligent misrepresentation a plaintiff must prove that the defendant (1) in the course of his business, (2) supplies false information for the guidance of others (3) in their business transactions, (4) causing and resulting in pecuniary loss to those others (5) by their justifiable reliance upon the information, and (6) with failure to exercise reasonable care or competence in obtaining or communicating the information.” · 17 citing courts
3
GREENSutton Corp. v. Metro. Dist. Comm'n, 652 N.E.2d 627 (Mass. App. Ct. 1995).
cites § 39N 4×cited by 5 cases
Where it cites § 39N
“The MDC denied the existence of a changed soil condition and did not respond to Sutton’s request for formal approval of a substitute method.”
Later courts cite it for
“a contractor who fails to adhere to the strict claims provisions of a public works contract forfeits all rights to recovery of damages or extra compensation unless the agency waives compliance therewith or the contractor is excused from compliance.” · 2 citing courts
4
GREENGlynn v. City of Gloucester, 401 N.E.2d 886 (Mass. App. Ct. 1980).
cites § 39N 1×cited by 55 cases
Where it cites § 39N
“771, § 1A; 7 G. L. c. 30, § 39N, inserted by St. 1972, c.”
The case’s holding
A public agency waives contract compliance only through clear, decisive, and unequivocal conduct by an authorized representative indicating it will not insist on adherence to the agreement.
Later courts cite it for
“clear, decisive, and unequivocal conduct on the part of an authorized representative of the agency indicating that it would not insist on adherence to the agreement.” · 3 citing courts
5
GREENGlynn v. City of Gloucester, 487 N.E.2d 230 (Mass. App. Ct. 1986).
cites § 39N 2×cited by 10 cases
Where it cites § 39N
“” See also G. L. c. 30, § 39N, inserted by St. 1972, c.”
Later courts cite it for
“were it otherwise, the contractual and statutory framework for the resolution of disputed claims would be virtually meaningless.” · 2 citing courts
6
GREENFramingham Heavy Equip. Co. v. John T. Callahan & Sons, Inc., 807 N.E.2d 851 (Mass. App. Ct. 2004).
cites § 39N 1×cited by 7 cases
Where it cites § 39N
“In any event, as the judge correctly noted, Framingham was legally entitled to be paid under G. L. c. 30, § 39N, for the changed site conditions.”
7
GREENB. J. Harland Elec. Co. v. Granger Bros., 510 N.E.2d 765 (Mass. App. Ct. 1987).
cites § 39N 1×cited by 12 cases
Where it cites § 39N
“XXII of the contract sets out, verbatim, the language of G. L. c. 30, § 39N, inserted by St. 1972, c.”
8
GREENCelco Constr. Corp. v. Town of Avon, 26 N.E.3d 202 (Mass. App. Ct. 2015).
cites § 39N 4×cited by 1 case
Where it cites § 39N
“See G. L. c. 30, § 39N. The town refused Celco’s request, Celco filed a complaint in the Superior Court, and a judge of that court allowed the town’s motion for summary judgment.”
9
GREENSkopek Bros. v. Webster Hous. Auth., 416 N.E.2d 1006 (Mass. App. Ct. 1981).
cites § 39N 1×cited by 4 cases
Where it cites § 39N
“This is an action by which, in the only aspect still material (count 6 of the amended complaint), the plaintiff, as the general contractor on a project for the construction of housing for the elderly, sought an “equitable adjustment” (G. L. c. 30, § 39N, inserted by St. 1972, c.”
10
NO FLAGJ.F. White Contracting Co. v. Commonwealth of Massachusetts, No. 2184CV01172-BLS2 (Mass. Super. Ct. Mar. 9, 2026).
cites § 39N 5×cited by 0 cases
Where it cites § 39N
“White claims that, under G.L. c. 30, § 39N, and related contract provisions, it is entitled to an equitable adjustment in the contract price to cover extra costs incurred because conditions at culvert work sites differed substantially or materially from those shown on MassDOT’s…”
11
NO FLAGN.E. Bridge Contractors, Inc. v. City of Lawrence., No. 22-P-0283 (Mass. App. Ct. July 24, 2023).
cites § 39N 4×cited by 0 casesunpublished
Where it cites § 39N
“In addition, the contract incorporated by reference the Massachusetts Highway Department's Standard Specifications for Highways and Bridges, and those specifications recited the requirements of G. L. c. 30, § 39N. Under G. L. c. 30, § 39N, all contracts subject to G.”
12
NO FLAGEnfield Builders, Inc. v. Commonwealth of Massachusetts, No. 2184CV01075-BLS2 (Mass. Super. Ct. May 12, 2025).
cites § 39N 2×cited by 0 cases
Where it cites § 39N
“G.L. c. 30, § 39N. EBI’s purported claim under G.”
13
NO FLAGGoudreau Corp. v. City of Springfield, 1 Mass. L. Rptr. 547 (Mass. Super. Ct. 1994).
cites § 39N 3×cited by 0 cases
Where it cites § 39N
“At some point, not disclosed in the record, Goudreau requested an equitable adjustment of the contract pursuant to G.L.c. 30, §39N. This request was based on the allegedly “differing subsurface and latent physical conditions” in the sewer.”
14
NO FLAGD'Allessandro Corp. v. City of Cambridge, 5 Mass. L. Rptr. 168 (Mass. Super. Ct. 1996).
cites § 39N 1×cited by 0 cases
Where it cites § 39N
“Chapter 30, §39N provides that when a claim is made for an adjustment in the contract price the contracting authority shall make an investigation of such physical conditions, and, if they differ substantially or materially.”
15
NO FLAGNorth Star Serv., Inc. v. New England Sports Mgmt. Corp., 7 Mass. L. Rptr. 491 (Mass. Super. Ct. 1997).
cites § 39N 1×cited by 0 cases
Where it cites § 39N
“11 (1996); G.L.c. 30, §39N. On the contrary, the provisions of the contract quoted above not only required the contractor, here the plaintiff, thoroughly to familiarize itself with site conditions, but also expressly stated that contractual information regarding subsurface condi…”
16
NO FLAGWest Valley Corp. v. City of Worcester, 8 Mass. L. Rptr. 672 (Mass. Super. Ct. 1998).
cites § 39N 1×cited by 0 cases
Where it cites § 39N
“The plaintiff seeks an equitable adjustment to the contract price for this additional work, based on M.G.L.c. 30, §39N, which provides: If, during the progress of the work, the contractor or the awarding authority discovers that the actual subsurface or latent physical…”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
198020032026

One bar per year. Tallest: 2 cases in 1996. 2026 is a partial year. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Mass. App. Ct.9Mass. Super. Ct.6Mass.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: text as last checked Sept. 2026 (this copy records no edition or section history). Syfert holds no earlier or later version of this section.

Massachusetts General Laws Home  |  Search Massachusetts  |  Search cases for this section  |  syfert.com