Massachusetts General Laws homeSearch Massachusetts
Mass. Gen. LawsPart I Title III Chapter 30

Mass. Gen. Laws ch. 30, § 62H (2026)

Action or proceeding alleging improper determination of need for environmental impact report or noncompliance with law; notice; commencement; matters raised

Edition and currency
text as last checked Sept. 2026 (this copy records no edition or section history). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTtext as last checked Sept. 2026 (this copy records no edition or section history) cited 1979–2010 16citing cases
At a glance

Courts have cited this section in 16 opinions since 1979.

Section 62H. An agency or person intending to commence an action or proceeding alleging an improper determination of whether a project requires the preparation of an environmental impact report under section sixty-two A, shall first provide notice of intention to commence such action or proceeding within sixty days of issuance of notice of such determination. An agency or person intending to commence an action or proceeding alleging that a final environmental impact report fails to comply with the requirements of sections sixty-two to sixty-two G, inclusive, shall first provide notice of intention to commence such action or proceeding within sixty days of issuance of notice of availability of said final environmental impact report pursuant to section sixty-two C. Said notices of intention shall be in such form as the secretary of environmental affairs shall prescribe, shall identify with particularity the issues to be considered in any such action or proceeding, shall be in lieu of the notice and waiting period required by section seven A of chapter two hundred and fourteen, and shall be provided to the attorney general, the agency or person proposing the project and the secretary of environmental affairs.

Any action or proceeding alleging an improper determination that a project requires the preparation of an environmental impact report under section sixty-two A shall commence no later than thirty days following the first issuance of a permit or grant of financial assistance by an agency or no later than sixty days after issuance of notice of such determination, whichever occurs later, for a private project, or no later than one hundred and twenty days after issuance of notice of such determination for a public project. Any action or proceeding alleging that a final environmental impact report fails to comply with the provisions of sections sixty-two to sixty-two G, inclusive, shall commence no later than thirty days following the first issuance of a permit or grant of financial assistance by an agency for a private project or no later than one hundred and twenty days after issuance of notice of availability of said final environmental impact report under section sixty-two C, for a public project.

No allegation shall be made in any action or proceeding under this section unless the matter complained of was raised at the appropriate point in the administrative review procedures; provided that a matter may be raised upon a showing that it is material and that it was not reasonably possible with due diligence to have raised it during such procedures or that the matter sought to be raised is of critical importance to the environmental impact of the project.

If a court determines that an agency or person proposing a project has knowingly concealed a material fact or knowingly submitted false information in any form or report required under sections sixty-two to sixty-two H, inclusive, limits on the manner and time in which actions or proceedings may be commenced shall not apply and the secretary of environmental affairs may require the preparation and review of such forms or reports as may be necessary to correct any deficient form or report.

The secretary of environmental affairs shall, after consultation with other secretaries of executive offices and with agencies not within executive offices, promulgate reasonable rules and regulations to carry out the purposes of sections sixty-two to sixty-two H, inclusive.

The 16 cases that cite Mass. Gen. Laws ch. 30, § 62H most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENCummings v. Sec'y of Env't Affairs, 524 N.E.2d 836 (Mass. 1988).
cites § 62H 14×cited by 28 cases
Where it cites § 62H
“Of course, in the absence of such jurisdiction, further inquiry in this case with respect to the notice provisions of G.L.c. 30, § 62H, would be inappropriate.”
The case’s holding
A citizen suit statute for environmental damage does not grant a court jurisdiction to challenge a public official's administrative determination regarding environmental impact reports.
Later courts cite it for
“in the hands of a disinterested public official with expertise in environmental matters, shared by his or her staff but not ordinarily by judges.” · 2 citing courts
2
GREENTown of Canton v. Comm'r of Massachusetts High. Dep't, 919 N.E.2d 1278 (Mass. 2010).
cites § 62H 9×cited by 25 cases
Where it cites § 62H
“We granted two applications for direct appellate review in this case to interpret the provision set forth in G. L. c. 30, § 62H, second par., requiring that an action challenging the certification of an environmental impact report (EIR) for a “private” development project “shall…”
Later courts cite it for
“construe statutes that relate to the same subject matter as a harmonious whole and avoid absurd results.” · 3 citing courts
3
GREENTown of Hull v. Massachusetts Port Auth., 806 N.E.2d 901 (Mass. 2004).
cites § 62H 5×cited by 8 cases
Where it cites § 62H
“This case requires us to interpret, for the first time, the provision set forth in G. L. c. 30, § 62H, fourth par., that creates an exception to the time limit for challenges to environmental impact reports if the project proponent has “knowingly concealed a material fact or…”
cites § 62H 2×cited by 22 cases
Where it cites § 62H
“Moreover, the regulations promulgated by the Secretary pursuant to G. L. c. 30, § 62H, reinforce the statute and provide that, for projects such as International Place, where no public financial assistance is being sought, “the scope of the EIR shall be limited to no more than…”
5
GREENEnos v. Sec'y of Env't Affairs, 432 Mass. 132 (2000).
cites § 62H 1×cited by 64 cases
Where it cites § 62H
“214, § 7A, nor G. L. c. 30, § 62H, confers subject matter jurisdiction for a suit challenging the Secretary’s discretionary decision not to require an EIR.”
The case’s holding
A party has standing only if it can allege an injury within the area of concern of the statute or regulatory scheme under which the injurious action occurred.
Later courts cite it for
“a party has standing when it can allege an injuiy within the area of concern of the statute or regulatoiy scheme under which the injuri ous action has occurred.” · 5 citing courts
6
GREENBenevolent & Prot. Order of Elks v. Plan. Bd., 531 N.E.2d 1233 (Mass. 1988).
cites § 62H 1×cited by 37 cases
Where it cites § 62H
“214, § 7A, and G. L. c. 30, § 62H (1986 ed.). Cummings, supra at 613, 618 .”
The case’s holding
Promulgated regulations have the force of law and bind the agency, but disregard of such rules constitutes reversible error only if the violation is prejudicial.
Later courts cite it for
“promulgated regulations have the force of law, and bind the agency.” · 2 citing courts
cites § 62H 1×cited by 34 cases
Where it cites § 62H
“The town also sought preliminary and permanent injunctions preventing the authority and the secretary from proceeding with the project until they publish reports complying with MEPA, the regulations implementing MEPA, and the special procedures, and preventing the further…”
The case’s holding
A court lacks jurisdiction to review an interim environmental certification because the relevant statute does not confer jurisdiction and the plaintiff has not exhausted administrative remedies.
8
GREENAm. Hoechest Corp. v. DEPT. OF PUB. Utils., 399 N.E.2d 1 (Mass. 1980).
cites § 62H 1×cited by 26 cases
Where it cites § 62H
“30, § 61, required the department to make a “finding describing the environmental impact, if any,” of the reduced rate and that the department’s order as it relates to the reduced rate must be overruled for failure to make such a finding. Such contentions should have been…”
The case’s holding
A utility rate classification or discount is lawful unless it is unduly or irrationally discriminatory, and cost of service need not be the sole justification for differential treatment of customers.
Later courts cite it for
“unduly or irrationally discriminatory,” · 1 citing court
9
GREENBaker v. Coxe, 940 F. Supp. 409 (D. Mass. 1996).
cites § 62H 1×cited by 13 cases
Where it cites § 62H
“However, the Bakers are not barred from bringing this claim by virtue of their having previously appealed an adverse administrative determination pursuant to M.G.L. c. 30, § 62H. See Custodio, 964 F.”
Later courts cite it for
“the court must accept as true all of the allegations made in the complaint and draw all reasonable inferences in the plaintiffs favor.” · 3 citing courts
10
GREENRoxse Homes, Inc. v. Adams, 83 F.R.D. 398 (D. Mass. 1979).
cites § 62H 2×cited by 4 cases
Where it cites § 62H
“For example, one of the potentially applicable statutes, Mass.Gen.Laws c. 30, § 62H, provides in part: If a court determines that an agency or person proposing a project has knowingly concealed a material fact or knowingly submitted false information in any form or report…”
11
GREENEnos v. Sec'y of Env't Affairs, 719 N.E.2d 874 (Mass. App. Ct. 1999).
cites § 62H 1×cited by 3 cases
Where it cites § 62H
“The Secretary makes no argument that the plaintiffs have not complied *242 with G. L. c. 30, § 62H, requiring prior notice to the Secretary of any intention to commence an action alleging failure to comply with MEPA.”
12
NO FLAGTown of Canton v. Paiewonsky, 25 Mass. L. Rptr. 378 (Mass. Super. Ct. 2008).
cites § 62H 2×cited by 0 cases
Where it cites § 62H
“On November 21, 2007, Canton filed written notice of its intent to commence an action for judicial review of the Secretary’s certification of the FEIR, pursuant to G.L.c. 30, §62H. On January 24, 2008, the Department of Environmental Protection issued a Sewer Connection Permit,…”
13
NO FLAGTown of Barnstable v. Cape Wind Assocs., LLC, 27 Mass. L. Rptr. 111 (Mass. Super. Ct. 2010).
cites § 62H 2×cited by 0 cases
Where it cites § 62H
“*115 On April 21 and 22, 2007, the Town and the Alliance sent timely notice of intent to sue to CWA, DFW, the Secretary, and the Attorney General pursuant to G.L.c. 30, §62H. The plaintiffs filed this action on August 16, 2007 and thereafter, amended their complaint once by…”
14
NO FLAGTen Residents v. Boston Redevelopment Auth., 21 Mass. L. Rptr. 324 (Mass. Super. Ct. 2006).
cites § 62H 1×cited by 0 cases
Where it cites § 62H
“Thus the Residents have already received the relief they seek in Count I: consideration by the Secretary of the tularemia incident under G.L.c. 30, §62H. Memorandum and Order at 11.”
15
NO FLAGBaker v. Coxe, 3 Mass. L. Rptr. 65 (Mass. Super. Ct. 1994).
cites § 62H 1×cited by 0 cases
Where it cites § 62H
“Plaintiffs filed this lawsuit pursuant to G.L.c. 30, §62H and 301 C.M.R. §11.20 alleging that the determination requiring the EIR was improper and that the EIR as required was overly broad.”
16
NO FLAGHootstein v. Coxe, 5 Mass. L. Rptr. 620 (Mass. Super. Ct. 1996).
cites § 62H 1×cited by 0 cases
Where it cites § 62H
“It is well-established that MEPA, through G.L.c. 30, §62H, “does not purport to grant jurisdiction" on the Superior Court, but rather provides for a limitations period on the commencement of actions.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
197919942010

One bar per year. Tallest: 2 cases in 1988. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Mass.8Mass. Super. Ct.5D. Mass.2Mass. App. Ct.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: text as last checked Sept. 2026 (this copy records no edition or section history). Syfert holds no earlier or later version of this section.

Massachusetts General Laws Home  |  Search Massachusetts  |  Search cases for this section  |  syfert.com