Michigan Compiled Laws homeSearch Michigan
Mich. Comp. LawsMichigan Compiled LawsChapter 247Act 368 of 1925

Mich. Comp. Laws § 247.184 (2026)

Consent of county or state to construction.

Edition and currency
laws through the 2026 session (checked Aug. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2026 session (checked Aug. 2026) cited 1968–2003 6citing cases
At a glance

Courts have cited this section in 6 opinions since 1968.

HIGHWAY OBSTRUCTIONS AND ENCROACHMENTS; USE OF HIGHWAY BY PUBLIC UTILITIES


Act 368 of 1925


247.184 Consent of county or state to construction.

Sec. 14.

    (1) A person that proposes to construct a telegraph, telephone, power line or cable television line, broadband line, pipe lines, wires, cables, poles, conduits, sewers, or like structures upon, over or under a county road or bridge, shall obtain the consent of the board of county road commissioners before commencing work.

    (2) A person that proposes to construct a telegraph, telephone, power line, cable television line, broadband line, pipe line, wires, cables, poles, conduits, sewers or like structures, upon, over or under a state trunk line highway, or upon, over or under any bridge that this state has participated in constructing, shall obtain the consent of the state highway commissioner before commencing work.

History: 1925, Act 368, Eff. Aug. 27, 1925 ;-- CL 1929, 4054 ;-- CL 1948, 247.184 ;-- Am. 1972, Act 268, Imd. Eff. Oct. 11, 1972 ;-- Am. 2018, Act 450, Eff. Mar. 21, 2019

The 6 cases that cite Mich. Comp. Laws § 247.184 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENCandelaria v. B C Gen. Contractors, Inc, 600 N.W.2d 348 (Mich. Ct. App. 1999).
cites § 247.184 4×cited by 67 cases
Where it cites § 247.184
“§ 247.184; MSA 9.264. On the day of the accident, Horizon applied for a permit from the MDOT that would allow it to perform the work described.”
The case’s holding
A general contractor is not liable for negligence to third parties or employees of an independent contractor unless it retains control over the method of the work.
Later courts cite it for
“if the employer of a person or business ostensibly labeled an 'independent contractor' retains control over the method of the work, there is in fact no contractee-contractor relationship, and the employer may be vicariously liable under the principles of master and servant.” · 4 citing courts
2
GREENMcMillan v. State High. Comm'n, 393 N.W.2d 332 (Mich. 1986).
cites § 247.184 2×cited by 56 cases
Where it cites § 247.184
“See also MCL 247.184; MSA 9.264, which requires the specific approval of county and state authorities for, inter alia, the placement of utility poles in or near a public highway.”
The case’s holding
A jury must decide whether a utility company breached its duty of reasonable care regarding the placement and maintenance of poles when reasonable minds differ on the risk of harm.
Later courts cite it for
“when reasonable minds may differ regarding the application of the reasonableness of the risk of harm, the question is best left to the jury.” · 2 citing courts
3
GREENAffiliated FM Ins. v. Dep't of State Highways & Transp., 272 N.W.2d 239 (Mich. Ct. App. 1978).
cites § 247.184 2×cited by 9 cases
Where it cites § 247.184
“It is a distinct civil wrong arising or resulting from the invasion of a legally protected interest * * *." 66 CJS, Nuisances, § 1b, p 729.”
4
GREENUnion Twp. v. City of Mount Pleasant, 158 N.W.2d 905 (Mich. 1968).
cites § 247.184 2×cited by 22 cases
Where it cites § 247.184
“” CL 1948, § 247.184 (Stat Ann 1958 Rev § 9.264). Defendant’s counsel urges us to read the two statutory sections as mutually exclusive, that is to say, that when the county’s consent is required by section 14, the township’s consent otherwise required by section 13 need not be…”
The case’s holding
A public utility must obtain consent from both the county and the township before constructing a pipeline within a county road running through the township; the county's consent alone is insufficient.
Later courts cite it for
“refused arbitrarily and unreasonably . .. .” · 2 citing courts
5
GREENMayor of Lansing v. Pub. Serv. Comm'n, 666 N.W.2d 298 (Mich. Ct. App. 2003).
cites § 247.184 1×cited by 10 cases
Where it cites § 247.184
“4 The city cursorily mentions MCL 247.184, which mandates the consent of county and state authorities.”
6
NEUTRALCandelaria v. Horizon Cablevision, Inc, 653 N.W.2d 630 (Mich. Ct. App. 2002).
cites § 247.184 1×cited by 3 cases
Where it cites § 247.184
“MCL 247.184 (emphasis added). Further, under the recognized exceptions to the general rule of nonliability for a contractor’s negligence, our Supreme Court has refused to impose a nondelegable duty where the risk resulted from absence of safety measures or negligence of an…”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
196819852003

One bar per year. Tallest: 1 case in 1968. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Mich. Ct. App.4Mich.2
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2026 session (checked Aug. 2026). Syfert holds no earlier or later version of this section.

Michigan Compiled Laws Home  |  Search Michigan  |  Search cases for this section  |  syfert.com