Michigan Compiled Laws homeSearch Michigan
Mich. Comp. LawsMichigan Compiled LawsChapter 324Act 451 of 1994

Mich. Comp. Laws § 324.5505 (2026)

Installation, construction, reconstruction, relocation, alteration, or modification of process or process equipment; permit to install or operate required; rules; trial operation; rules for issuance of general permit or certain exemptions; temporary locations; nonrenewable permits; failure of department to act on applications; appeal of permit actions.

Edition and currency
laws through the 2026 session (checked Aug. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2026 session (checked Aug. 2026) cited 2000–2021 14citing cases
At a glance

Courts have cited this section in 14 opinions since 2000, 2 of them in the last five years. The most litigated part is subsection (8) (12 cases).

NATURAL RESOURCES AND ENVIRONMENTAL PROTECTION ACT


Act 451 of 1994


324.5505 Installation, construction, reconstruction, relocation, alteration, or modification of process or process equipment; permit to install or operate required; rules; trial operation; rules for issuance of general permit or certain exemptions; temporary locations; nonrenewable permits; failure of department to act on applications; appeal of permit actions.

Sec. 5505.

    (1) Except as provided in subsection (4), a person shall not install, construct, reconstruct, relocate, alter, or modify any process or process equipment without first obtaining from the department a permit to install, or a permit to operate authorized pursuant to rules promulgated under subsection (6) if applicable, authorizing the conduct or activity.

    (2) The department shall promulgate rules to establish a permit to install program to be administered by the department. Except as provided in subsections (4) and (5), the permit to install program is applicable to each new or modified process or process equipment that emits or may emit an air contaminant. The start date for emissions offsets eligible to be applied to a permit to install shall be the date established by federal rule or, if a date is not established by federal rule, January 1 of the year after the emissions baseline year used for the purpose of preparing the relevant state implementation plan. The department shall make available information in the permit database and the air emissions inventory established under section 5503(k), to identify emissions reductions that may be used as emissions offsets. This subsection does not authorize the department to seek permit changes to make emissions reductions available for use as emissions offsets.

    (3) A permit to install may authorize the trial operation of a process or process equipment to demonstrate that the process or process equipment is operating in compliance with the permit to install issued under this section.

    (4) The department may promulgate rules to provide for the issuance of general permits and to exempt certain sources, processes, or process equipment or certain modifications to a source, process, or process equipment from the requirement to obtain a permit to install or a permit to operate authorized pursuant to rules promulgated under subsection (6). However, the department shall not exempt any new source or modification that would meet the definition of a major source or major modification under parts C and D of title I of the clean air act, 42 USC 7470 to 7515.

    (5) The department may issue a permit to install, a general permit, or a permit to operate authorized under rules promulgated under subsection (6) if applicable, that authorizes installation, operation, or trial operation, as applicable, of a source, process, or process equipment at numerous temporary locations. Such a permit shall do both of the following:

    (a) Include terms and conditions necessary to ensure compliance with all applicable requirements of this part, the rules promulgated under this part, and the clean air act, including those necessary to ensure compliance with all applicable ambient air standards, emission limits, and increment and visibility requirements pursuant to part C of title I of the clean air act, 42 USC 7470 to 7492, at each location.

    (b) Require the owner or operator of the process, source, or process equipment to notify the department at least 10 days in advance of each change in location. However, if electronic notification is used, the notification shall be given at least the following number of business days before the change of location:

    (i) 5 business days unless subparagraph (ii) applies.

    (ii) 2 business days, if, at least 10 days before the change of location, the owner provided the department a list of anticipated operating locations for that calendar year and if the change of location is on that list.

    (6) The department may promulgate rules to establish a program that authorizes issuance of nonrenewable permits to operate for sources, processes, or process equipment that are not subject to the requirement to obtain a renewable operating permit pursuant to section 5506.

    (7) The failure of the department to act on an administratively and technically complete application for a permit to install, a general permit, or a permit to operate authorized under rules promulgated under subsection (6), in accordance with a time requirement established pursuant to this part, rules promulgated under this part, or the clean air act may be treated as a final permit action solely for the purposes of obtaining judicial review in a court of competent jurisdiction to require that action be taken by the department on the application without additional delay.

    (8) Any person may appeal the issuance or denial by the department of a permit to install, a general permit, or a permit to operate authorized in rules promulgated under subsection (6), for a new source in accordance with section 631 of the revised judicature act of 1961, 1961 PA 236, MCL 600.631. Petitions for review shall be the exclusive means to obtain judicial review of such a permit and shall be filed within 90 days after the final permit action, except that a petition may be filed after that deadline only if the petition is based solely on grounds arising after the deadline for judicial review. Such a petition shall be filed no later than 90 days after the new grounds for review arise. Appeals of permit actions for existing sources are subject to section 5506(14).

    

    

History: 1994, Act 451, Eff. Mar. 30, 1995 ;-- Am. 2005, Act 57, Imd. Eff. June 30, 2005 ;-- Am. 2019, Act 120, Eff. Feb. 13, 2020

PopularName Notes:

Act 451

PopularName Notes:

NREPA
The 14 cases that cite Mich. Comp. Laws § 324.5505 most heavily, weighted by court and treatment. RelevanceNewestTreatment
cites § 324.5505 51×subsections: (8) 43× (6) 3× (1) (2)cited by 90 cases
Where it cites § 324.5505
“The first is the presence of an indefinite article preceding the word "permit" in MCL 324.”
The case’s holding
Statutory language must be construed in light of its context rather than in isolation.
Later courts cite it for
“the principal goal of statutory interpretation is to give effect to the legislature's intent, and the most reliable evidence of that intent is the plain language of the statute.” · 34 citing courts
2
GREENWolverine Power Supply Coop., Inc v. Dep't of Env't Quality, 777 N.W.2d 1 (Mich. Ct. App. 2009).
cites § 324.5505 16×subsections: (8) 5× (1) 2× (2) 2× (4)cited by 12 cases
Where it cites § 324.5505
“MCL 324.5505 (1) GENERAL PROVISIONS MCL 324.”
3
GREENNat. Resources Def. Council v. Dep't of Env't Quality, 832 N.W.2d 288 (Mich. Ct. App. 2013).
cites § 324.5505 3×subsections: (8) 3×cited by 48 cases
Where it cites § 324.5505
“3 The Legislature has provided in MCL 324.5505(8) that “[a]ny person may appeal the issuance or *85 denial by the department of a permit to install.”
The case’s holding
An administrative agency does not act as a tribunal if its procedures lack quasi-judicial characteristics such as the right to a contested case hearing.
Later courts cite it for
“quasi-judicial proceedings include procedural characteristics common to courts, such as a right to a hearing, a right to be represented by counsel, the right to submit exhibits, and the authority to subpoena witnesses and require parties to produce documents.” · 9 citing courts
4
GREENSouth Dearborn Env't Improvement Ass'n v. Dep't of Env't Quality, 891 N.W.2d 233 (Mich. Ct. App. 2016).
cites § 324.5505 4×subsections: (8) 2× (1)cited by 10 cases
Where it cites § 324.5505
“Section 5505(1) prohibits the installation, construction, reconstruction, relocation, alteration, or modification of “any process or process equipment without first obtaining from the [DEQ] a permit to install, or a permit to operate authorized pursuant to rules promulgated…”
The case’s holding
A permit to install issued after notice and a hearing is governed by the Administrative Procedures Act, so the 60-day period for appealing the agency decision applies.
Later courts cite it for
“will not reverse when the lower court reaches the correct result, albeit for the wrong reason.” · 4 citing courts
5
GREENPreserve the Dunes, Inc v. Dep't of Env't Quality, 684 N.W.2d 847 (Mich. 2004).
cites § 324.5505 2×cited by 38 cases
Where it cites § 324.5505
“In the soil erosion and 10 See also MCL 324.5505 and 324.3106, requiring permits for activities that may pollute the air and water without imposing stringent eligibility criteria.”
The case’s holding
The Michigan Environmental Protection Act does not authorize a collateral challenge to an agency's permit eligibility determination unrelated to whether the conduct will pollute, impair, or destroy natural resources.
Later courts cite it for
“fixed by rule or otherwise, by the state or an instrumentality, agency, or political subdivision of the state” · 1 citing court
6
GREENCity of Jackson v. Thompson-McCully Co., 608 N.W.2d 531 (Mich. Ct. App. 2000).
cites § 324.5505 2×subsections: (8) 2×cited by 49 cases
Where it cites § 324.5505
“However, the court determined that this was not a mepa case, but a nrepa (Natural Resources and Environmental Protection Act) case, presumably under MCL 324.5505(8); MSA 13A.5505(8), which governs appeals of permits to install under the nrepa.”
The case’s holding
An issue is moot if an event occurs that renders it impossible for the court to grant relief even if it decides in favor of the party.
Later courts cite it for
“renders it impossible for the court, if it should decide in favor of appellants, to grant relief” · 3 citing courts
7
NO FLAGSouth Dearborn Env't Improvement Assn v. Deq, No. 154526 (Mich. July 17, 2018).
cites § 324.5505 72×subsections: (8) 60× (6) 3× (1) (2)cited by 0 cases
Where it cites § 324.5505
“A petition for judicial review of the issuance or denial of any of the types of permits for an existing source that are governed by MCL 324.5505 and MCL 324.5506 must be filed within 90 days of the DEQ’s final permit action.”
8
NO FLAGSouth Dearborn Env't Improvement Assn v. Deq, No. 154524 (Mich. July 17, 2018).
cites § 324.5505 72×subsections: (8) 60× (6) 3× (1) (2)cited by 0 cases
Where it cites § 324.5505
“A petition for judicial review of the issuance or denial of any of the types of permits for an existing source that are governed by MCL 324.5505 and MCL 324.5506 must be filed within 90 days of the DEQ’s final permit action.”
9
REDPreserve the Dunes, Inc v. Dep't of Env't Quality, 655 N.W.2d 263 (Mich. Ct. App. 2002).
cites § 324.5505 1×subsections: (8)cited by 9 cases
Reversed by Preserve the Dunes, Inc v. Department of Environmental Quality (2004): the Michigan Supreme Court's own opinion in this case.
Where it cites § 324.5505
“In the air pollution context, MCL 324.5505(8) provides that any appeal of the issuance or denial of a permit in that section must be taken within ninety days after the final permit action and exclusively pursuant to the rja.”
Later courts cite it for
“standard for pollution or antipollution device or procedure” · 2 citing courts
10
NO FLAGSouth Dearborn Env't Improvement Assn v. Deq, No. 350032 (Mich. Ct. App. Mar. 18, 2021).
cites § 324.5505 5×subsections: (2) 2× (5)(a) (8)cited by 0 cases
Where it cites § 324.5505
“5512(1)(h) also requires that the DEQ promulgate rules to implement MCL 324.5505, which is related to “source, process, or process equipment,” and MCL 324.”
11
NO FLAGSierra Club v. Dep't of Env't Great Lakes & Energy, No. 350083 (Mich. Ct. App. Jan. 7, 2021).
cites § 324.5505 2×subsections: (8)cited by 0 casesunpublished
Where it cites § 324.5505
“5505 provides, in relevant part: (1) Except as provided in subsection (4), a person shall not install, construct, reconstruct, relocate, alter, or modify any process or process equipment without first obtaining from the department a permit to install, or a permit to operate…”
12
NO FLAGSouth Dearborn Env't Improvement Assn v. Deq, No. 154524 (Mich. Apr. 7, 2017).
cites § 324.5505 1×subsections: (8)cited by 0 cases
Where it cites § 324.5505
“The parties shall file supplemental briefs within 42 days of the date of this order addressing: (1) whether MCL 324.5505(8) and MCL 324.5506(14) prescribe the applicable time period for filing a petition for judicial review of the Department of Environmental Quality’s issuance…”
13
NO FLAGSouth Dearborn Env't Improvement Assn v. Deq, No. 154524 (Mich. Apr. 7, 2017).
cites § 324.5505 1×subsections: (8)cited by 0 cases
Where it cites § 324.5505
“The parties shall file supplemental briefs within 42 days of the date of this order addressing: (1) whether MCL 324.5505(8) and MCL 324.5506(14) prescribe the applicable time period for filing a petition for judicial review of the Department of Environmental Quality’s issuance…”
14
NO FLAGPreserve the Dunes Inc v. Dept of Env't Quality, No. 122612 (Mich. July 30, 2004).
cites § 324.5505 1×cited by 0 cases
Where it cites § 324.5505
“In the soil erosion and 10 See also MCL 324.5505 and 324.3106, requiring permits for activities that may pollute the air and water without imposing stringent eligibility criteria.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
200020102021

One bar per year. Tallest: 3 cases in 2018. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Mich.7Mich. Ct. App.7
By subsection
(1)5 cases
S. Dearborn Envtl. Improvement Ass'n v. Dep't of Envtl. Quality, 917 N.W.2d 603 (Mich. 2018).“The first is the presence of an indefinite article preceding the word "permit" in MCL 324.”
Wolverine Power Supply Coop., Inc v. Dep't of Env't Quality, 777 N.W.2d 1 (Mich. Ct. App. 2009).“MCL 324.5505 (1) GENERAL PROVISIONS MCL 324.”
South Dearborn Env't Improvement Ass'n v. Dep't of Env't Quality, 891 N.W.2d 233 (Mich. Ct. App. 2016).“Section 5505(1) prohibits the installation, construction, reconstruction, relocation, alteration, or modification of “any process or process equipment without first obtaining from the [DEQ] a permit to install, or a permit to operate authorized pursuant to rules promulgated…”
South Dearborn Env't Improvement Assn v. Deq, No. 154526 (Mich. July 17, 2018).“A petition for judicial review of the issuance or denial of any of the types of permits for an existing source that are governed by MCL 324.5505 and MCL 324.5506 must be filed within 90 days of the DEQ’s final permit action.”
South Dearborn Env't Improvement Assn v. Deq, No. 154524 (Mich. July 17, 2018).“A petition for judicial review of the issuance or denial of any of the types of permits for an existing source that are governed by MCL 324.5505 and MCL 324.5506 must be filed within 90 days of the DEQ’s final permit action.”
(2)5 cases
South Dearborn Env't Improvement Assn v. Deq, No. 350032 (Mich. Ct. App. Mar. 18, 2021).“5512(1)(h) also requires that the DEQ promulgate rules to implement MCL 324.5505, which is related to “source, process, or process equipment,” and MCL 324.”
South Dearborn Env't Improvement Assn v. Deq, No. 154526 (Mich. July 17, 2018).
South Dearborn Env't Improvement Assn v. Deq, No. 154524 (Mich. July 17, 2018).
(4)1 case
(5)(a)1 case
South Dearborn Env't Improvement Assn v. Deq, No. 350032 (Mich. Ct. App. Mar. 18, 2021).
(6)4 cases
South Dearborn Env't Improvement Assn v. Deq, No. 154526 (Mich. July 17, 2018).
South Dearborn Env't Improvement Assn v. Deq, No. 154524 (Mich. July 17, 2018).
(8)12 cases
Nat. Resources Def. Council v. Dep't of Env't Quality, 832 N.W.2d 288 (Mich. Ct. App. 2013).“3 The Legislature has provided in MCL 324.5505(8) that “[a]ny person may appeal the issuance or *85 denial by the department of a permit to install.”
City of Jackson v. Thompson-McCully Co., 608 N.W.2d 531 (Mich. Ct. App. 2000).“However, the court determined that this was not a mepa case, but a nrepa (Natural Resources and Environmental Protection Act) case, presumably under MCL 324.5505(8); MSA 13A.5505(8), which governs appeals of permits to install under the nrepa.”
Showing the top 5 of 12. More in the list view →
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2026 session (checked Aug. 2026). Syfert holds no earlier or later version of this section.

Michigan Compiled Laws Home  |  Search Michigan  |  Search cases for this section  |  syfert.com