Nebraska Revised Statutes homeSearch Nebraska
Neb. Rev. Stat.Chapter 52

Neb. Rev. Stat. § 52-131 (2026)

Construction lien; existence; amount; priority; enforcement

Edition and currency
text as last checked Oct. 2026 (this copy records no edition or section history). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTtext as last checked Oct. 2026 (this copy records no edition or section history) cited 1989–2026 15citing cases
At a glance

Courts have cited this section in 15 opinions since 1989, 3 of them in the last five years. The most litigated part is subsection (1) (8 cases).

(1) A person who furnishes services or materials pursuant to a real estate improvement contract has a construction lien, only to the extent provided in the Nebraska Construction Lien Act, to secure the payment of his or her contract price.

(2) A lien arises under the act only if the claimant records a lien within the time specified by section 52-137.

(3) Real estate to which a construction lien attaches is specified by section 52-133, and limitations on the existence of a lien for materials are specified by section 52-134.

(4) The amount of a claimant's lien is specified by section 52-136. The content of the notice of the right to assert a lien to be given to the owner under section 52-136 is specified by section 52-135.

(5) The priority of a claimant's lien as against other construction-lien claimants is specified in section 52-138, and priority as against claimants other than construction-lien claimants is specified in section 52-139.

(6) Foreclosure of a lien under the act is governed by section 52-155, and the time within which an action to foreclose must be brought by section 52-140.

The 15 cases that cite Neb. Rev. Stat. § 52-131 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENTilt-Up Concrete, Inc. v. Star City/Fed., Inc., 582 N.W.2d 604 (Neb. 1998).
cites § 52-131 3×subsections: (1)cited by 42 cases
Where it cites § 52-131
“1) Tilt-Up entered into a lump-sum contract with Star City, (2) Tilt-Up was a prime contractor, (3) the lack of substantial performance of the contract did not eliminate Tilt-Up’s construction lien, (4) Tilt-Up had a construction lien for more than the reasonable value of…”
The case’s holding
A person who furnishes services or materials pursuant to a real estate improvement contract has a construction lien.
Later courts cite it for
“who furnishes services or materials pursuant to a real estate improvement contract has a construction lien,” · 2 citing courts
2
GREENEcho Grp. v. Tradesmen Internat., 980 N.W.2d 869 (Neb. 2022).
cites § 52-131 2×subsections: (1) (4)cited by 8 cases
Where it cites § 52-131
“- 742 - Nebraska Supreme Court Advance Sheets 312 Nebraska Reports ECHO GROUP V.”
The case’s holding
Under the Nebraska Construction Lien Act, substituting a lien release surety bond for a construction lien does not cap recovery, and prejudgment interest may be awarded in lien foreclosure actions.
Later courts cite it for
“a formal legal document entailing rights and obligations, such as a contract, deed, legislative act, etc.; any document formally drawn up so as to have legal effect.” · 2 citing courts
3
GREENOmaha Constr. Indus. Pension Plan v. Child.'s Hosp., 642 N.W.2d 849 (Neb. Ct. App. 2002).
cites § 52-131 4×subsections: (1)cited by 6 cases
Where it cites § 52-131
“§ 52-131. There is no language which prohibits employees of a subcontractor from filing a construction lien.”
4
GREENSorenson v. Dager, 601 N.W.2d 564 (Neb. Ct. App. 1999).
cites § 52-131 2×subsections: (1)cited by 31 cases
Where it cites § 52-131
“A “real estate improvement contract” is defined as “an agreement to perform services, including labor, or to furnish materials for the purpose of producing a change in the physical condition of land or of a structure.”
5
GREENFranksen v. Crossroads Jt. Venture, 515 N.W.2d 794 (Neb. 1994).
cites § 52-131 1×subsections: (1)cited by 38 cases
Where it cites § 52-131
“§ 52-131(1). If at the time a construction lien is recorded there is a recorded notice of commencement covering the improvement pursuant to which the lien arises, the lien is on the contracting owner’s real estate described in the notice of commencement.”
The case’s holding
A person placed on inquiry regarding an agent's authority with reasonable means of inquiry is charged with knowledge of the facts that such inquiry would reveal.
Later courts cite it for
“one who is placed on inquiry as to an agent's or employee's authority, and who has reasonable means of making inquiry, occupies the same position in law as if he had actual knowledge of the employee's lack of authority, because he is charged with knowledge of the facts which the inquiry would have developed.” · 2 citing courts
cites § 52-131 1×subsections: (1)cited by 13 cases
Reversed by Bricklayers of Western Pennsylvania Combined Funds, Inc. v. Scott's Development Co. (2014): the Supreme Court of Pennsylvania's own opinion in this case.
Where it cites § 52-131
“2d 849 (2002) (holding that, under Neb.Rev.Stat. § 52-131(1), "an employee of a subcontractor may file a lien against the property owner”); Divane v.”
7
GREENMid-Am. Maint., Inc. v. Bill Morris Ford, Inc., 442 N.W.2d 869 (Neb. 1989).
cites § 52-131 2×cited by 6 cases
Where it cites § 52-131
“Morris said he did not know what specific items Ford would not have purchased, adding, “I don’t know anything about a roof.”
Later courts cite it for
“a construction lien is not valid absent a contract between the parties” · 1 citing court
8
GREENIn re WorldCom, Inc., 362 B.R. 96 (Bankr. S.D.N.Y. 2007).
cites § 52-131 1×cited by 8 cases
Where it cites § 52-131
“Prior to the Second Supplemental Briefing, the Debtors argued, that even if the Lien was valid when filed, the Lien lapsed because Waldinger failed to bring a suit to foreclose the Lien (the “Foreclosure Action”) within the statutory time period required by Nebraska Law…”
Later courts cite it for
“an act to maintain or continue perfection of a lien” · 2 citing courts
9
GREENHulinsky v. Parriott, 441 N.W.2d 883 (Neb. 1989).
cites § 52-131 1×cited by 6 cases
Where it cites § 52-131
“§ 52-131. Hulinsky clearly has a lien under the act.”
10
GREENTaylor v. Taylor, 764 N.W.2d 101 (Neb. 2009).
cites § 52-131 2×cited by 1 case
Where it cites § 52-131
“[6] Under § 52-131, to have a construction lien, Shirley must have had a real estate improvement contract with Leatha.”
11
GREENNore Elec. v. S & H Holdings, 3 N.W.3d 895 (Neb. 2024).
cites § 52-131 3×subsections: (1) 2× (2)cited by 0 cases
Where it cites § 52-131
“30 Both S&H and RIP qualify as owners. With these principles in mind, we turn to the issues raised by the parties.”
12
NO FLAGIn re MBA Poultry, L.L.C., 251 B.R. 82 (Bankr. D. Neb. 2000).
cites § 52-131 1×cited by 2 cases
Where it cites § 52-131
“§ 52-131. A real estate improvement contract is an agreement to perform services or to furnish materials for the purpose of producing a change in the physical condition of land or of a structure, including construction or installation on, above, or below the surface of land, and…”
13
NO FLAGArtisan Pools, Inc. v. Siemer, No. A-25-246 (Neb. Ct. App. May 12, 2026).
cites § 52-131 1×subsections: (1)cited by 0 casesunpublished
Where it cites § 52-131
“” § 52-131(1). Section 52-157 provides, in relevant part: (2) If in bad faith a claimant records a lien, overstates the amount for which he or she is entitled to a lien, or refuses to execute a release of a lien, the court may: (a) Declare his or her lien void; and -3- (b) Award…”
14
GREENFru-Con Constr. Corp. v. Controlled Air, No. 08-1712 (8th Cir. July 24, 2009).
cites § 52-131 1×cited by 0 cases
Where it cites § 52-131
“1998) (quoting Neb. Rev. Stat. § 52-131 (1)). 3 This was a correct analysis.”
15
NEUTRALIn re Mba Poultry, LLC, 251 B.R. 82 (Bankr. D. Neb. 2000).
cites § 52-131 1×cited by 0 cases
Where it cites § 52-131
“§ 52-131. A real estate improvement contract is an agreement to perform services or to furnish materials for the purpose of producing a change in the physical condition of land or of a structure, including construction or installation on, above, or below the surface of land, and…”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
198920072026

One bar per year. Tallest: 2 cases in 1989. 2026 is a partial year. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Neb.7Neb. Ct. App.3Bankr. D. Neb.28th Cir.1Bankr. S.D.N.Y.1Pa. Super. Ct.1
By subsection
(1)8 cases
Echo Grp. v. Tradesmen Internat., 980 N.W.2d 869 (Neb. 2022).“- 742 - Nebraska Supreme Court Advance Sheets 312 Nebraska Reports ECHO GROUP V.”
Tilt-Up Concrete, Inc. v. Star City/Fed., Inc., 582 N.W.2d 604 (Neb. 1998).“1) Tilt-Up entered into a lump-sum contract with Star City, (2) Tilt-Up was a prime contractor, (3) the lack of substantial performance of the contract did not eliminate Tilt-Up’s construction lien, (4) Tilt-Up had a construction lien for more than the reasonable value of…”
Franksen v. Crossroads Jt. Venture, 515 N.W.2d 794 (Neb. 1994).“§ 52-131(1). If at the time a construction lien is recorded there is a recorded notice of commencement covering the improvement pursuant to which the lien arises, the lien is on the contracting owner’s real estate described in the notice of commencement.”
Sorenson v. Dager, 601 N.W.2d 564 (Neb. Ct. App. 1999).“A “real estate improvement contract” is defined as “an agreement to perform services, including labor, or to furnish materials for the purpose of producing a change in the physical condition of land or of a structure.”
Bricklayers of W. Pennsylvania Combined Funds, Inc. v. Scott's Dev. Co., 41 A.3d 16 (Pa. Super. Ct. 2012).“2d 849 (2002) (holding that, under Neb.Rev.Stat. § 52-131(1), "an employee of a subcontractor may file a lien against the property owner”); Divane v.”
Showing the top 5 of 8. More in the list view →
(2)1 case
Nore Elec. v. S & H Holdings, 3 N.W.3d 895 (Neb. 2024).“30 Both S&H and RIP qualify as owners. With these principles in mind, we turn to the issues raised by the parties.”
(4)1 case
Echo Grp. v. Tradesmen Internat., 980 N.W.2d 869 (Neb. 2022).
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: text as last checked Oct. 2026 (this copy records no edition or section history). Syfert holds no earlier or later version of this section.